Facts
The Appellant, BEST, is a local authority and distribution licensee in the Island City of Mumbai
Source reference: p.2Respondent No. 2 (TPC-D) was granted a parallel distribution license on 14.08.2014 for 25 years
Source reference: p.4TPC-D submitted a Network Rollout Plan for the areas overlapping with BEST, which the Maharashtra Electricity Regulatory Commission (MERC) approved via a combined order dated 12.06.2017
Source reference: p.7This plan allowed TPC-D to develop its distribution network in two phases over a seven-year period
Source reference: p.16BEST challenged this order, contending that phased development violates the Universal Service Obligation (USO), encourages "cherry-picking" of high-end consumers, and creates an uneven playing field
Source reference: p.11Issues
1. Whether the phased development of a distribution network over seven years is permitted under the Electricity Act, 2003 or if it contravenes the Universal Service Obligation under Section 43
Source reference: p.10 / para. 272. Whether the approved rollout plan violates the specific conditions of the distribution license granted to TPC-D
Source reference: p.21 / para. 403. Whether the MERC failed to consider practical difficulties and stranded assets in the approved consumer migration/switchover protocol
Source reference: p.24 / para. 46Law Applied
The court primarily applied Section 42(1) of the Electricity Act, 2003, which mandates licensees to develop an efficient and economical distribution system
Source reference: p.13It also applied Section 43, regarding the duty to supply electricity on request within stipulated timelines, acknowledging that such supply may require extensions of distribution mains
Source reference: p.14The 6th Proviso to Section 14 was cited regarding the grant of parallel licenses
Source reference: p.13The Tribunal relied on its own precedent in *Noida Power Company Limited v. PVVNL*, holding that laying an entire network is not a precondition for a license
Source reference: p.15The Supreme Court's ruling in *BEST v. MERC (2015) 2 SCC 438* regarding the exemption of local authorities from providing open access under Section 42(3)
Source reference: p.25Reasoning
The Tribunal reasoned that Section 42(1) implies a continuous, progressive obligation to develop infrastructure rather than a one-time requirement to cover an entire area instantly
Source reference: para. 33The MERC’s two-phase approach—prioritizing areas with existing substations (Phase I) before expanding to new areas (Phase II)—was deemed an "optimal approach" to prevent scattered, unplanned development and "cherry-picking"
Source reference: para. 35-36The Tribunal noted that BEST’s challenge to the principle of phased development was barred by *res judicata* as the same issue was previously decided against them in Appeal No. 216 of 2014
Source reference: para. 33-34Regarding the migration protocol, the Tribunal found that the 3-day information-sharing window had functioned effectively since 2009 in other Mumbai sectors and that pending legal disputes cannot be used to block a consumer's right to switch licensees
Source reference: para. 51-53Finally, the "stranded assets" argument was rejected because the Electricity Act expressly permits competition and network duplication in the same area
Source reference: para. 54Holding
The Appellate Tribunal dismissed the appeal and upheld the MERC’s order dated 12.06.2017
Phased development of a distribution network is legally permissible and does not violate the USO under Section 43
Source reference: para. 33the rollout plan was consistent with TPC-D’s license conditions as it balanced cost-effectiveness with USO requirements
Source reference: para. 45the switchover protocol was valid, noting that as a local authority, BEST is not required to provide open access, making TPC-D’s network duplication an "inevitable statutory outcome"
Source reference: para. 54Original Court PDF
Municipal Corporation of Greater Mumbai (BEST Undertaking) v. Maharashtra Electricity Regulatory Commission & Ors., Appeal No. 279 of 2017.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in