Gujarat High Court

Post-Award Claims of Measurement Discrepancies and De Facto Excess Land Acquisition Are Not Maintainable Under Article 226.

RAMESHBHAI CHIMANBHAI PATEL vs COLLECTOR / ARBITRATOR, DISTRICT NAVSARI

Gujarat High CourtJUDGMENT: May 05, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioner, an agriculturist, owned land in Village Toli, Navsari (Block No. 498).

Source reference: no citation

Notifications for the acquisition of 767 sq. mtrs. of this land for the Vadodara–Mumbai Expressway were issued in 2014 and 2015.

Source reference: para. 4, 8

An award for compensation was declared on 19.03.2020, and the petitioner subsequently sought redetermination of compensation through an Arbitrator under Section 3G(5) of the National Highways Act.

Source reference: para. 8

In the arbitral award dated 26.08.2021, the Arbitrator made incidental remarks regarding the possibility of re-measuring land if discrepancies existed.

Source reference: para. 9

Following a 2022 DILR measurement report showing a current holding of 2,418 sq. mtrs., the petitioner alleged that the National Highways Authority of India (NHAI) had taken possession of 569 sq. mtrs. in excess of the acquired 767 sq. mtrs.

Source reference: para. 6, 11
02

Issues

1. Whether the petitioner can challenge the measurement of acquired land and seek relief for alleged excess possession after the conclusion of acquisition proceedings and receipt of compensation.

Source reference: para. 14, 15

2. Whether an Arbitrator appointed under Section 3G(5) of the National Highways Act has the jurisdiction to adjudicate disputes regarding the physical measurement or area of land acquired.

Source reference: para. 16, 17
03

Law Applied

Section 3G(5) of the National Highways Act, 1956, which limits the Arbitrator's jurisdiction to disputes regarding the "determination of the amount" of compensation and does not extend to the correctness of the land measurement itself.

Source reference: para. 16

Principle of waiver and laches, noting that land measurement objections must be raised at the survey stage under Section 3B of the National Highways Act, 1956.

Source reference: para. 8
04

Reasoning

The Court found the petition "wholly misconceived" and "misleading".

Source reference: para. 2, 19

It reasoned that the petitioner remained silent during the statutory objection periods (Sections 3A and 3D) and only raised the measurement issue after receiving compensation in 2020.

Source reference: para. 8, 15

The Court sharply criticized the Collector/Arbitrator for including observations about land measurement in the arbitral award, noting that Section 3G(5) is strictly restricted to redetermining the amount of compensation; thus, any comments on area discrepancies were "alien to the controversy".

Source reference: para. 16, 17

The Court observed that the 2022 DILR report merely stated the current land area and did not prove that the NHAI was in possession of the alleged "excess" area.

Source reference: para. 12, 13
05

Holding

The Court dismissed the petition, holding that the dispute was raised at a belated stage and was unsupported by evidence showing the NHAI possessed more land than the 767 sq. mtrs. acquired by law.

The Court clarified that observations regarding land measurement by an Arbitrator under Section 3G(5) are outside their legal mandate and cannot be used as a basis to initiate new proceedings.

Source reference: para. 18

No order as to costs was made.

Source reference: para. 20
Gujarat High Court

Original Court PDF

RAMESHBHAI CHIMANBHAI PATELvsCOLLECTOR / ARBITRATOR, DISTRICT NAVSARI

Gujarat High Court · May 05, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment