Facts
ONGC hired Swiber in 2010 for an offshore project valued at USD 148.2 million
Source reference: p.2The project was completed on May 24, 2012, after multiple extensions granted with a reservation of ONGC’s right to liquidated damages (LD)
Source reference: p.3Per Consent Terms recorded in 2016, Swiber maintained a Bank Guarantee (BG) of USD 14.82 million, which they agreed would remain valid for only 120 days post-award
Source reference: p.18, 22On September 30, 2025, an Arbitral Tribunal rejected ONGC’s claim for LD and directed the return of the BG
Source reference: p.5ONGC challenged the award under Section 34 and filed this Section 9 petition seeking to extend the BG beyond its June 15, 2026, expiry, citing Swiber’s insolvency/liquidation in Singapore and the risk of non-recovery
Source reference: p.6, 13Issues
1. Whether an unsuccessful party in an arbitration can seek interim protection under Section 9 of the Act post-award
Source reference: para. 282. Whether the "rare and compelling" threshold for post-award interim relief was met, especially considering prior Consent Terms regarding the BG's duration
Source reference: para. 42, 49Law Applied
The Court applied Section 9 of the Arbitration and Conciliation Act, 1996, regarding interim measures by the Court
Source reference: p.1Supreme Court precedent in Home Care Retail Marts (P) Ltd. v. Haresh N. Sanghavi (2026), which established that while an unsuccessful party can invoke Section 9 post-award, the threshold is significantly higher and requires "extraordinary" or "rare and compelling" circumstances
Source reference: p.16, 25, 41Distinguished ONGC v. Larsen & Toubro Ltd. (2026), where interim protection was granted because the Tribunal had partially upheld the claim, unlike the total rejection in the present case
Source reference: p.19, 43Reasoning
The Court reasoned that once an award is delivered, the findings—including the rejection of ONGC's claim—operate unless set aside
Source reference: p.25The Court found that ONGC failed to disclose the 2016 Consent Terms in this petition, which specifically limited the BG's life to 120 days post-award (expiring Jan 28, 2026); seeking an extension now would effectively rewrite a voluntary contract
Source reference: p.31, 32While Swiber’s liquidation in Singapore created a risk of non-recovery, this "apprehension" did not create a legal right to override the Tribunal’s decision to return the security
Source reference: p.37, 42ONGC’s delay in filing the Section 9 petition (waiting until May 2026 for a June 15 expiry) undermined its plea of genuine urgency
Source reference: p.34, 35The Court concluded that an "arguable" challenge under Section 34 is insufficient to meet the "extraordinary" standard required to maintain security after a total loss in arbitration
Source reference: p.38, 41Holding
The Court dismissed the petition
It held that ONGC failed to establish "exceptional and compelling circumstances" to justify post-award protection under Section 9, specifically refusing to direct the renewal or extension of the USD 14.82 million Bank Guarantee
Source reference: para. 75(iii)The Court clarified that this decision does not reflect on the merits of the pending Section 34 challenge
Source reference: para. 75(iv)A request for stay/continuation of the BG pending appeal was also rejected as it would constitute granting the final relief already denied
Source reference: para. 77Acts & Sections Cited
4 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.
Arbitration and Conciliation Act, 19964
Original Court PDF
Oil And Natural Gas Corporation LimitedvsSwiber Offshore Construction Pte Limited
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
