Facts
ONGC hired Swiber in 2010 for an offshore project valued at USD 148.2 million
Source reference: p.2The project was completed on May 24, 2012, after multiple extensions granted with a reservation of ONGC’s right to liquidated damages (LD)
Source reference: p.3Per Consent Terms recorded in 2016, Swiber maintained a Bank Guarantee (BG) of USD 14.82 million, which they agreed would remain valid for only 120 days post-award
Source reference: p.18, 22On September 30, 2025, an Arbitral Tribunal rejected ONGC’s claim for LD and directed the return of the BG
Source reference: p.5ONGC challenged the award under Section 34 and filed this Section 9 petition seeking to extend the BG beyond its June 15, 2026, expiry, citing Swiber’s insolvency/liquidation in Singapore and the risk of non-recovery
Source reference: p.6, 13Issues
1. Whether an unsuccessful party in an arbitration can seek interim protection under Section 9 of the Act post-award
Source reference: para. 282. Whether the "rare and compelling" threshold for post-award interim relief was met, especially considering prior Consent Terms regarding the BG's duration
Source reference: para. 42, 49Law Applied
The Court applied Section 9 of the Arbitration and Conciliation Act, 1996, regarding interim measures by the Court
Source reference: p.1Supreme Court precedent in Home Care Retail Marts (P) Ltd. v. Haresh N. Sanghavi (2026), which established that while an unsuccessful party can invoke Section 9 post-award, the threshold is significantly higher and requires "extraordinary" or "rare and compelling" circumstances
Source reference: p.16, 25, 41Distinguished ONGC v. Larsen & Toubro Ltd. (2026), where interim protection was granted because the Tribunal had partially upheld the claim, unlike the total rejection in the present case
Source reference: p.19, 43Reasoning
The Court reasoned that once an award is delivered, the findings—including the rejection of ONGC's claim—operate unless set aside
Source reference: p.25The Court found that ONGC failed to disclose the 2016 Consent Terms in this petition, which specifically limited the BG's life to 120 days post-award (expiring Jan 28, 2026); seeking an extension now would effectively rewrite a voluntary contract
Source reference: p.31, 32While Swiber’s liquidation in Singapore created a risk of non-recovery, this "apprehension" did not create a legal right to override the Tribunal’s decision to return the security
Source reference: p.37, 42ONGC’s delay in filing the Section 9 petition (waiting until May 2026 for a June 15 expiry) undermined its plea of genuine urgency
Source reference: p.34, 35The Court concluded that an "arguable" challenge under Section 34 is insufficient to meet the "extraordinary" standard required to maintain security after a total loss in arbitration
Source reference: p.38, 41Holding
The Court dismissed the petition
It held that ONGC failed to establish "exceptional and compelling circumstances" to justify post-award protection under Section 9, specifically refusing to direct the renewal or extension of the USD 14.82 million Bank Guarantee
Source reference: para. 75(iii)The Court clarified that this decision does not reflect on the merits of the pending Section 34 challenge
Source reference: para. 75(iv)A request for stay/continuation of the BG pending appeal was also rejected as it would constitute granting the final relief already denied
Source reference: para. 77Original Court PDF
Oil And Natural Gas Corporation LimitedvsSwiber Offshore Construction Pte Limited
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in