Bombay High CourtArbitration and MediationCivil Procedure and Evidence

Post-Award Section 9 relief requires exceptional circumstances surpassing the threshold for routine interim protection.

Oil And Natural Gas Corporation Limitedv.Swiber Offshore Construction Pte Limited

Post-Award Section 9 relief requires exceptional circumstances surpassing the threshold for routine interim protection.. Oil And Natural Gas Corporation Limited vs Swiber Offshore Construction Pte Limited. Bombay High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether an unsuccessful party in an arbitration can seek interim protection under Section 9 of the Act post-award

The court held

The Court dismissed the petition

It also directed

It held that ONGC failed to establish "exceptional and compelling circumstances" to justify post-award protection under Section 9, specifically refusing to direct the renewal or extension of the USD 14.82 million Bank Guarantee

The Court clarified that this decision does not reflect on the merits of the pending Section 34 challenge

A request for stay/continuation of the BG pending appeal was also rejected as it would constitute granting the final relief already denied

01Facts

ONGC hired Swiber in 2010 for an offshore project valued at USD 148.2 million

p. 2

The project was completed on May 24, 2012, after multiple extensions granted with a reservation of ONGC’s right to liquidated damages (LD)

p. 3

Per Consent Terms recorded in 2016, Swiber maintained a Bank Guarantee (BG) of USD 14.82 million, which they agreed would remain valid for only 120 days post-award

p. 18, 22

On September 30, 2025, an Arbitral Tribunal rejected ONGC’s claim for LD and directed the return of the BG

p. 5

ONGC challenged the award under Section 34 and filed this Section 9 petition seeking to extend the BG beyond its June 15, 2026, expiry, citing Swiber’s insolvency/liquidation in Singapore and the risk of non-recovery

p. 6, 13

02Issues

i.1. Whether an unsuccessful party in an arbitration can seek interim protection under Section 9 of the Act post-award

¶ 28

ii.2. Whether the "rare and compelling" threshold for post-award interim relief was met, especially considering prior Consent Terms regarding the BG's duration

¶ 42, 49

03Law Applied

The Court applied Section 9 of the Arbitration and Conciliation Act, 1996, regarding interim measures by the Court

p. 1

Supreme Court precedent in Home Care Retail Marts (P) Ltd. v. Haresh N. Sanghavi (2026), which established that while an unsuccessful party can invoke Section 9 post-award, the threshold is significantly higher and requires "extraordinary" or "rare and compelling" circumstances

p. 16, 25, 41

Distinguished ONGC v. Larsen & Toubro Ltd. (2026), where interim protection was granted because the Tribunal had partially upheld the claim, unlike the total rejection in the present case

p. 19, 43

Provisions in the judgment · 4 · Linked ones open on LawLens

Arbitration and Conciliation Act, 1996 Section 9Section 28Section 34Section 36

04Reasoning

The Court reasoned that once an award is delivered, the findings—including the rejection of ONGC's claim—operate unless set aside

p. 25

The Court found that ONGC failed to disclose the 2016 Consent Terms in this petition, which specifically limited the BG's life to 120 days post-award (expiring Jan 28, 2026); seeking an extension now would effectively rewrite a voluntary contract

p. 31, 32

While Swiber’s liquidation in Singapore created a risk of non-recovery, this "apprehension" did not create a legal right to override the Tribunal’s decision to return the security

p. 37, 42

ONGC’s delay in filing the Section 9 petition (waiting until May 2026 for a June 15 expiry) undermined its plea of genuine urgency

p. 34, 35

The Court concluded that an "arguable" challenge under Section 34 is insufficient to meet the "extraordinary" standard required to maintain security after a total loss in arbitration

p. 38, 41

05Holding

The Court dismissed the petition

¶ 75(i)

It held that ONGC failed to establish "exceptional and compelling circumstances" to justify post-award protection under Section 9, specifically refusing to direct the renewal or extension of the USD 14.82 million Bank Guarantee

¶ 75(iii)

The Court clarified that this decision does not reflect on the merits of the pending Section 34 challenge

¶ 75(iv)

A request for stay/continuation of the BG pending appeal was also rejected as it would constitute granting the final relief already denied

¶ 77
Bombay High Court

Original Court PDF

Oil And Natural Gas Corporation LimitedvsSwiber Offshore Construction Pte Limited

Bombay High Court · June 15, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment