01Facts
The respondent was awarded a government contract for a water supply project in Kishtwar and subsequently entered into a sub-contract agreement with the petitioner on 03.05.2013
pp. 1-2The petitioner alleged that the respondent breached the agreement by withholding payments beyond the agreed 2% retention and failing to open an escrow account
p. 2The petitioner initially filed a civil suit for specific performance; however, the Commercial Court, Jammu, directed the parties to arbitration on 06.11.2025, noting the existence of an arbitration clause
p. 2, 4The petitioner served a legal notice invoking arbitration on 12.11.2025, but the respondent failed to appoint an arbitrator, contesting the petition on the grounds that the notice was undated and never received
pp. 3-502Issues
i.1. Whether the petitioner validly invoked the arbitration clause in accordance with Section 21 of the Arbitration and Conciliation Act, 1996, given the respondent's denial of receipt of notice
pp. 4-5ii.2. Whether a Sole Arbitrator should be appointed under Section 11 of the Act to resolve the contractual disputes
pp. 5-603Law Applied
The court applied Sections 11(5), 11(6), and 21 of the Arbitration and Conciliation Act, 1996
p. 1, 4Section 21 stipulates that arbitral proceedings commence on the date a request for the dispute to be referred to arbitration is received by the respondent
p. 4The court also relied on the principle of "presumption of service" regarding postal receipts for notices sent to corrected addresses
p. 5the court upheld the autonomy of the arbitration agreement as defined in Clause 12.2 of the parties' sub-contract, which mandates referral of unresolved disputes to a sole arbitrator
p. 5Provisions in the judgment · 4 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 11Section 12Section 21Section 8
04Reasoning
The court found that while the initial notice copy was undated, the petitioner subsequently provided a dated copy (12.11.2025) and a corresponding postal receipt
p. 5Since the address on the receipt matched the respondent’s address in the petition, the court invoked a presumption of service, thereby satisfying the requirement of Section 21
p. 5the court noted that the existence of the arbitration agreement (Clause 12.2) was undisputed and that the respondent itself had previously successfully argued for arbitration before the Commercial Court
p. 2, 4, 5Because the parties reached an impasse and could not mutually agree on an individual, the court determined that judicial intervention under Section 11 was necessary to give effect to the arbitration clause
pp. 5-605Holding
The court allowed the petition and held that a valid dispute exists and the arbitration clause was properly invoked
p. 5The court appointed Hon'ble Mr. Justice Vinod Chatterji Koul (Retd.) as the Sole Arbitrator. The Arbitrator was directed to provide statutory disclosure under Section 12(1), and the respondent was ordered to bear the arbitration charges as per the specific terms of Clause 12.2 of the agreement
pp. 5-6Original Court PDF
JHELUM INFRA PROJECTS PVT LTD TH ITS MANAGING DIRECTOR RAJ KUMAR GUPTAvsT A INFRA PROJECTS LTD TH MANAGING DIRECTOR
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
