Facts
The respondent was awarded a government contract for a water supply project in Kishtwar and subsequently entered into a sub-contract agreement with the petitioner on 03.05.2013
Source reference: p. 1-2The petitioner alleged that the respondent breached the agreement by withholding payments beyond the agreed 2% retention and failing to open an escrow account
Source reference: p. 2The petitioner initially filed a civil suit for specific performance; however, the Commercial Court, Jammu, directed the parties to arbitration on 06.11.2025, noting the existence of an arbitration clause
Source reference: p. 2, 4The petitioner served a legal notice invoking arbitration on 12.11.2025, but the respondent failed to appoint an arbitrator, contesting the petition on the grounds that the notice was undated and never received
Source reference: p. 3-5Issues
1. Whether the petitioner validly invoked the arbitration clause in accordance with Section 21 of the Arbitration and Conciliation Act, 1996, given the respondent's denial of receipt of notice
Source reference: p. 4-52. Whether a Sole Arbitrator should be appointed under Section 11 of the Act to resolve the contractual disputes
Source reference: p. 5-6Law Applied
The court applied Sections 11(5), 11(6), and 21 of the Arbitration and Conciliation Act, 1996
Source reference: p. 1, 4Section 21 stipulates that arbitral proceedings commence on the date a request for the dispute to be referred to arbitration is received by the respondent
Source reference: p. 4The court also relied on the principle of "presumption of service" regarding postal receipts for notices sent to corrected addresses
Source reference: p. 5the court upheld the autonomy of the arbitration agreement as defined in Clause 12.2 of the parties' sub-contract, which mandates referral of unresolved disputes to a sole arbitrator
Source reference: p. 5Reasoning
The court found that while the initial notice copy was undated, the petitioner subsequently provided a dated copy (12.11.2025) and a corresponding postal receipt
Source reference: p. 5Since the address on the receipt matched the respondent’s address in the petition, the court invoked a presumption of service, thereby satisfying the requirement of Section 21
Source reference: p. 5the court noted that the existence of the arbitration agreement (Clause 12.2) was undisputed and that the respondent itself had previously successfully argued for arbitration before the Commercial Court
Source reference: p. 2, 4, 5Because the parties reached an impasse and could not mutually agree on an individual, the court determined that judicial intervention under Section 11 was necessary to give effect to the arbitration clause
Source reference: p. 5-6Holding
The court allowed the petition and held that a valid dispute exists and the arbitration clause was properly invoked
The court appointed Hon'ble Mr. Justice Vinod Chatterji Koul (Retd.) as the Sole Arbitrator. The Arbitrator was directed to provide statutory disclosure under Section 12(1), and the respondent was ordered to bear the arbitration charges as per the specific terms of Clause 12.2 of the agreement
Source reference: p. 5-6Original Court PDF
JHELUM INFRA PROJECTS PVT LTD TH ITS MANAGING DIRECTOR RAJ KUMAR GUPTAvsT A INFRA PROJECTS LTD TH MANAGING DIRECTOR
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in