APTEL
Administrative and Public LawCommercial and Corporate Law

Project-specific tariff determination remanded for reconsideration of disputed costs, flood damage, and subsidy deductions.

M/s Devi Energies Pvt. Ltd. vs Arunachal Pradesh State Electricity Regulatory Commission & Ors.

APTELJUDGMENT: October 06, 20262 MIN READSOURCE JUDGMENT
Project-specific tariff determination remanded for reconsideration of disputed costs, flood damage, and subsidy deductions.. M/s Devi Energies Pvt. Ltd. vs Arunachal Pradesh State Electricity Regulatory Commission & Ors.. APTEL. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The appellant developed the 24 MW Dikshi Small Hydro Electric Project under an MoU with the Government of Arunachal Pradesh and entered into civil-works contracts with a contractor, including a renegotiated contract with revised rates

Source reference: pp. 3–4

After the project was commissioned on 19 September 2019, the appellant challenged parts of the Commission’s tariff order dated 20 December 2019, which had approved the project’s capital cost and determined its generation tariff

Source reference: pp. 4–5

The appeal concerned the Commission’s reduction of civil-works costs and interest during construction, its disallowance of costs attributed to flood damage, and its deduction of a ₹5 crore subsidy that the appellant said it had not received

Source reference: pp. 5–7
02

Issues

1. Whether the Commission’s restriction of civil-works costs and interest during construction in determining the project’s capital cost required reconsideration.

Source reference: pp. 5–6

2. Whether the Commission’s disallowance of additional restoration costs arising from three floods, based on the lower insurance settlement, required reconsideration.

Source reference: p. 6

3. Whether the Commission’s deduction of a ₹5 crore subsidy from capital cost, despite the appellant’s claim that it had not received the subsidy, required reconsideration.

Source reference: pp. 6–7
03

Law Applied

The judgment cites no statute, precedent, or specific legal doctrine as the basis for its decision.

Source reference: no citation

It notes that the appellant’s tariff petition was made under the Arunachal Pradesh State Electricity Regulatory Commission (Terms and Conditions for Tariff Determination from Renewable Energy Sources) Regulations, 2018, but does not interpret or apply those Regulations to decide the merits.

Source reference: p. 4

The Tribunal instead ordered reconsideration after noting the Commission’s express request, made during the hearing and in its written submissions, that the matter be remanded.

Source reference: p. 7
04

Reasoning

The Tribunal did not determine whether the Commission’s treatment of the civil-works costs, flood-related expenditure, or subsidy was legally or factually correct.

Source reference: p. 7

Given the Commission’s request for remand, the Tribunal considered it appropriate to return those disputed matters to the Commission for fresh consideration, with a reasonable opportunity of hearing for the parties.

Source reference: p. 7
05

Holding

The Tribunal set aside the Commission’s order only to the extent challenged in the appeal and remanded the identified issues for fresh consideration after hearing the parties.

It directed the Commission to endeavour to complete that exercise within three months.

Source reference: pp. 7–8

The appeal was allowed to that extent, and any pending interlocutory applications were disposed of.

Source reference: pp. 7–8
APTEL

Original Court PDF

M/s Devi Energies Pvt. Ltd.vsArunachal Pradesh State Electricity Regulatory Commission & Ors.

APTEL · October 06, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment