Gauhati High Court
Administrative and Public LawContract Law

Public authorities must verify contractual work claims and pay amounts found due within prescribed timelines.

M/S Ramawtar Agarwalla vs The State Of Assam And 4 Ors

Gauhati High CourtJUDGMENT: August 12, 20263 MIN READSOURCE JUDGMENT
Public authorities must verify contractual work claims and pay amounts found due within prescribed timelines.. M/S Ramawtar Agarwalla vs The State Of Assam And 4 Ors. Gauhati High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioner, a proprietary concern, was awarded the contract for “Construction of Public Auditorium at Ambagan under Lawkhowa Dev. Block.” It claimed to have satisfactorily completed 53% of the work under the contract valued at ₹1,80,00,000 and incurred expenditure of ₹93,32,551

Source reference: p.2

The petitioner’s Running Account Bill was acknowledged by the Chief Executive Officer, Nagaon Zila Parishad, on 16.03.2016, but payment was not made

Source reference: p.3

In an earlier writ petition, WP(C) No. 3441/2017, the High Court, by order dated 24.11.2023, directed the authorities to verify the petitioner’s entitlement and disburse the payable amount within four months of receipt of the certified order

Source reference: p.3

Despite service of that order on 05.12.2023, the authorities neither conducted the verification nor made payment. The petitioner therefore invoked Article 226 of the Constitution seeking appropriate relief

Source reference: pp.3–4

The respondents did not deny issuance of the work but contended that the petitioner’s entitlement was subject to verification

Source reference: p.5
02

Issues

1. Whether the respondent authorities failed to comply with the directions issued in the earlier order dated 24.11.2023 by not verifying the petitioner’s entitlement and not making payment of the certified contractual dues

Source reference: pp.3, 6

2. Whether the respondent authorities should be directed to verify the work executed by the petitioner and pay the amount, if any, found payable

Source reference: pp.4–6

3. Whether a time-bound mechanism should be prescribed for verification, payment or communication of the reasons for rejection or reduction of the petitioner’s claim

Source reference: pp.5–6
03

Law Applied

The Court exercised its supervisory and remedial jurisdiction under Article 226 of the Constitution of India to enforce compliance with its earlier directions and to secure performance of a public authority’s acknowledged contractual obligation.

Source reference: p.4

The applicable principle was that a contractor is entitled to payment only to the extent of work duly executed and certified after verification by the competent authorities

Source reference: p.4

The Court further applied the principle that administrative inaction or disregard of a binding judicial direction is impermissible and may warrant further judicial directions for compliance

Source reference: p.6

No specific statutory provision or judicial precedent was cited in the judgment.

Source reference: no citation
04

Reasoning

The Court accepted that the petitioner had been awarded the work and that its claim of execution and expenditure had not been specifically denied by the respondents

Source reference: p.5

However, because the exact amount payable depended upon verification of the work actually completed and certified, the Court did not direct immediate payment of the entire claimed sum of ₹93,32,551

Source reference: pp.4–5

Instead, it noted that the earlier order had already required verification and payment, yet the authorities had taken no action despite receiving the certified order

Source reference: pp.3, 6

This failure constituted not merely non-payment but also disregard of the Court’s earlier direction.

Source reference: no citation

The Court therefore ordered a fresh, time-bound verification and required payment of the amount found due, while also directing that the petitioner be informed if its claim was rejected or reduced

Source reference: p.6
05

Holding

The writ petition was disposed of with directions to Respondent Nos. 2 to 5 to verify the amount payable for the work executed by the petitioner

Verification was to be completed within one month of service of the certified judgment upon the Commissioner, Panchayat and Rural Development Department

Source reference: p.5

Any amount found payable was to be paid within five months after completion of verification, with no overall delay beyond six months from service of the judgment

Source reference: p.6

If the petitioner was found entitled to no amount, or to an amount lower than claimed, the Commissioner or delegatee was required to inform the petitioner within one month of service of the judgment

Source reference: p.6

An affidavit of compliance was directed to be filed within eight months, failing which the matter would be placed before the Court for further orders

Source reference: p.6
Gauhati High Court

Original Court PDF

M/S Ramawtar AgarwallavsThe State Of Assam And 4 Ors

Gauhati High Court · August 12, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment