01Facts
The South Eastern Railway (SER) leased a 24 MT parcel van attached to train nos. 18045/18046 to the respondent for two years under an agreement dated 16 August 2024, valid until 3 September 2026.
¶ 2During the lease, the respondent was twice found guilty of overloading, and punitive charges were imposed.
¶ 3On 17 February 2026, the respondent booked a consignment declared at 21,040 kg. Weighment at Padmapukur en route showed overloading of 1,330 kg. The SER imposed a punitive charge of Rs. 32,019 on 18 February 2026 and refused re-weighment.
¶ 4–5Treating this as the third overloading, the SER terminated the lease by notice dated 21 February 2026 under Para 14.3 of Freight Marketing Circular (FMC) No. 12 of 2022.
¶ 5A writ petition (WPA No. 4403 of 2026) led to an order dated 23 February 2026 directing re-weighment by an alternative method, which the SER did not challenge.
¶ 6, 28Two re-weighments (EIMWB at Andul and manual weighment at Shalimar) showed the consignment within permissible limits. By letter dated 3 March 2026, the SER invited the respondent to seek reinstatement.
¶ 7, 29 · ¶ 8, 29After a third-party FIR dated 5 March 2026 alleging missing packages, the SER, by letter dated 11 March 2026, held the 3 March letter in abeyance and treated the 21 February termination as continuing, alleging tampering and unauthorised unloading.
¶ 9, 30–31No show cause notice preceded the 11 March 2026 letter.
¶ 23, 35The respondent's writ petition (WPA No. 5361 of 2026) was allowed by the Single Judge on procedural impropriety and natural justice grounds. The appellants appealed.
¶ 10, 24–26 · ¶ 102Issues
i.1. Whether the writ petition was maintainable despite the availability of arbitration and a departmental appeal as alternative remedies.
¶ 17, 21, 36ii.2. Whether the SER could terminate the lease under Para 14.3 of FMC No. 12 of 2022 on the basis of a third overloading, where re-weighments had found no overloading, and on the basis of subsequent allegations of tampering.
¶ 32–34iii.3. Whether the termination notice dated 11 March 2026 was issued in violation of the principles of natural justice and was procedurally improper, given that no show cause notice was issued.
¶ 35, 3703Law Applied
Para 14.3 of FMC No. 12 of 2022, under which a contract is terminated on detection of a third overloading beyond the tolerance limit (1 tonne for parcel vans), was examined by the Court.
¶ 32(c)Paras 28.2 and 28.3 of FMC No. 11 of 2022 (termination on 30 days' notice, and punitive termination without notice for serious violation) were not invoked by the SER and were therefore not considered.
¶ 32(a)–(b), 33A show cause notice must precede any state or public authority action having civil consequences for a citizen, grounded in the rule of audi alteram partem and the duty of fair conduct by the State, even where the contract or circular does not expressly require one.
¶ 35The existence of an alternative remedy is not an absolute bar to a writ petition, particularly where the impugned action breaches natural justice, and arbitrary and unreasonable State action is open to judicial review.
¶ 36The respondent's contention under Section 73 of the Railways Act, 1989 (punitive charges only on established overloading) was recorded but not decided.
¶ 22Provisions in the judgment · 1 · Linked ones open on LawLens
Railways Act, 1989 Section 73
04Reasoning
The Court held the writ maintainable because the respondent challenged arbitrary, procedurally unfair State action, and the alleged breach of natural justice made the alternative remedy no bar.
¶ 36On the merits, the Court confined itself to the only ground on which the contract was terminated, namely the third overloading under Para 14.3.
¶ 33The SER's own two re-weighments found no overloading, and the SER accepted this by its 3 March 2026 letter.
¶ 29, 34The SER's later assertion that the respondent's tampering had skewed the re-weighments was, in the Court's view, neither conclusive nor final, and was yet to be proved. The Court therefore did not decide whether tampering occurred. Instead, it held that the respondent was entitled to be heard on those allegations before the contract was terminated again.
¶ 34Although neither Para 14.3 nor the contract required a show cause notice, the Court found that fairness required one, given the civil consequences of termination.
¶ 35The absence of any such opportunity made the 11 March 2026 termination manifestly arbitrary and procedurally improper.
¶ 35, 3705Holding
(i) The writ petition was maintainable notwithstanding the alternative remedies of arbitration and departmental appeal, since the impugned action was taken in breach of natural justice.
¶ 36(ii) The SER could not rely on subsequent, unproven tampering allegations to revive a termination founded on a third overloading that its own re-weighments had disproved.
¶ 34(iii) The termination notice dated 11 March 2026 was issued without a show cause notice and was procedurally improper and in violation of natural justice; it is not sustainable in law.
¶ 35, 37The Court affirmed the Single Judge's judgment and order dated 17 March 2026 in WPA No. 5361 of 2026, dismissed M.A.T. No. 1024 of 2026, vacated any interim orders, and made no order as to costs.
¶ 38–39Original Court PDF
UNION OF INDIA AND ORSvsMOHD ABDUL WADOOD
Click to open original judgment