Facts
The appellant, Joginder Singh, through his legal representative, challenged the award dated 12 March 2003 by which the Additional District Judge, Ludhiana did not grant the claimed compensation under the Land Acquisition Act, 1894
Source reference: p.10, para. 12The appeal was filed with an application seeking condonation of a delay of 5,831 days
Source reference: p.1, para. 1The appellant stated that he was unaware of the status of the proceedings and contended that similarly situated landowners had obtained enhanced compensation in appeals decided by the High Court
Source reference: p.1, para. 2The State conceded that the appellant’s claim was covered by the High Court’s judgment dated 25 August 2008 in RFA-1881-2000, but submitted that, in view of the inordinate delay, the appellant could not be granted statutory benefits or interest for the delayed period
Source reference: pp.1, 10, paras. 3, 16Issues
Whether the delay of 5,831 days in filing the appeal should be condoned in a land-acquisition matter where the appellant claims parity with similarly situated landowners?
Source reference: p.1, para. 1; p.10, paras. 9–11Whether, upon condonation of delay, the appellant is entitled to statutory benefits and interest for the period of delay?
Source reference: pp.4–6, para. 6; p.10, paras. 9, 17Whether the appellant’s claim for enhanced compensation is covered by the judgment in RFA-1881-2000 dated 25 August 2008?
Source reference: pp.10–11, paras. 15–17Law Applied
The Court applied Section 5 of the Limitation Act, 1963, under which delay may be condoned where sufficient cause is shown, while recognising that the discretion must be exercised judicially and cannot override the public policy underlying limitation law. It also applied Section 54 of the Land Acquisition Act, 1894, governing appeals to the High Court against an award.
Source reference: no citationRelying on Pathapati Subba Reddy (Died) by L.Rs. v. The Special Deputy Collector, 2024 (12) SCC 336, the Court noted that although a liberal approach may be adopted under Section 5, inordinate delay, negligence and want of due diligence remain relevant considerations, and the mere fact that similarly situated persons obtained relief does not automatically entitle a delayed appellant to the same relief
Source reference: pp.2–3, para. 4Under Shivamma (Dead) v. Karnataka Housing Board, 2025 SCC OnLine SC 1969, sufficient cause must cover the entire period of delay and courts should not mechanically condone enormous delays
Source reference: pp.3–4, para. 5However, New Okhla Industrial Development Authority v. Rameshwar @ Ramesh Chandra Sharma, 2022 SCC OnLine SC 1599, Suresh Kumar v. State of Haryana, 2025 SCC OnLine SC 896, and Urban Improvement Trust v. Vidhya Devi, 2024 SCC OnLine SC 3725, establish that a liberal and justice-oriented approach may be adopted in land-acquisition cases, particularly to ensure parity in compensation, but the acquiring body should not be saddled with statutory benefits or interest for the period attributable to the claimant’s delay
Source reference: pp.4–9, paras. 6–8Reasoning
The Court treated the matter as a land-acquisition case requiring a liberal approach because the appellant sought compensation at par with similarly situated landowners and the State did not dispute that the claim was covered by the earlier judgment in RFA-1881-2000
Source reference: p.10, paras. 10, 15–16Although the delay was exceptionally long—5,831 days—the Court relied on the Supreme Court’s land-acquisition jurisprudence permitting condonation of substantial delay to avoid unequal compensation among landowners
Source reference: p.10, para. 10At the same time, the Court balanced the appellant’s entitlement to parity against the public financial burden and the principle that a party should not benefit from its own delay. Accordingly, it accepted the State’s submission that no statutory benefits or interest could be awarded for the delayed period
Source reference: pp.5–6, para. 6; p.10, paras. 9, 17Holding
The application for condonation of delay was allowed, and the delay of 5,831 days in filing the appeal was condoned
The main appeal was thereafter allowed in terms of the judgment dated 25 August 2008 in RFA-1881-2000, since the appellant’s claim was conceded to be covered by that decision
Source reference: p.11, para. 17However, the appellant was expressly denied interest for the delayed period of 5,831 days and all statutory benefits
Source reference: p.11, para. 17Pending applications, if any, were disposed of
Source reference: p.11, para. 18Acts & Sections Cited
2 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.
Original Court PDF
Joginder Singh Since Deceased Through His Legal Representative Baljit SinghvsThe Land Acquisition Collector, Industries Department, Punjab Chd, And Anr
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
