01Facts
The plaintiff (Respondent 1) filed a suit for specific performance against the defendant (Appellant) based on a registered agreement of sale dated 06.09.2012 for land measuring 5 acres 12 guntas
p. 5The total consideration was Rs. 92,00,000/-, of which Rs. 5,00,000/- was paid as advance, with the balance due within three months
pp. 5-6The plaintiff alleged the defendant delayed execution due to property disputes (OS No. 139/2012) and executed a subsequent unregistered agreement on 22.06.2013
p. 6The defendant contended the transaction was a loan, the documents were concocted, and the suit was barred by limitation
pp. 7-8The Trial Court decreed the suit in favor of the plaintiff
p. 4The defendant appealed, arguing a lack of "readiness and willingness" and that half the land had been acquired by the government
pp. 18-2102Issues
i.1. Whether the Trial Court erred in finding that the plaintiff proved his readiness and willingness to perform the contract
p. 23 / para. 27ii.2. Whether the Appellate Court has the power to examine continuous readiness and willingness during the pendency of the appeal
p. 24 / para. 27iii.3. Whether the relief of specific performance or refund of earnest money is appropriate under the circumstances
p. 24 / para. 2703Law Applied
The court applied Section 16(c) of the Specific Relief Act (pre-2018 amendment), which mandates that a plaintiff must aver and prove continuous readiness and willingness to perform the contract from its inception until the decree
p. 33, 41It adhered to the principles in U.N. Krishnamurthy v. A.M. Krishnamurthy (2023), establishing that "readiness" refers to financial capacity and "willingness" to mental conduct
p. 28, 46The court also relied on K.S. Vidyanadam v. Vairavan (1997) and Saradamani Kandappan v. S. Rajalakshmi (2011), which held that even if time is not the essence of a contract for immovable property, the court must apply strict scrutiny to delays and cannot ignore time limits stipulated in agreements
p. 47, 49Provisions in the judgment · 6 · Linked ones open on LawLens
Code of Civil Procedure, 1908 Section 96Section 41
Specific Relief Act, 1963 Section 10Section 16Section 20
Limitation Act, 1963 Section 57
04Reasoning
The Court found that while the plaintiff proved the execution of the agreement, he failed to demonstrate "readiness and willingness"
¶ 37-44Critically, the balance consideration was Rs. 87,00,000/-, but the plaintiff’s bank records (Ex. P12) showed a balance of only Rs. 10,279/- until early 2016. Large sums were deposited only during the evidence stage in March 2016, nearly 3.5 years after the agreement’s three-month deadline
pp. 19, 39-40The Court observed that the plaintiff waited until the "fag end" of the limitation period to file the suit without explaining the delay
pp. 36-37Furthermore, the second agreement of 2013 was not proved as no witnesses were examined
p. 32The Court held that the Appellate Court is a continuation of the original proceedings and must re-examine the plaintiff's financial capacity to ensure it remained consistent even after the Trial Court decree
¶ 31-3305Holding
The Court answered the issues in favor of the Appellant, holding that the plaintiff failed to satisfy the mandatory requirements of Section 16(c) regarding financial readiness
¶ 45-46The High Court set aside the Trial Court’s decree for specific performance. However, acknowledging that the defendant received Rs. 5,00,000/- and did not prove it was a loan, the Court ordered a refund of the advance amount with 12% interest per annum from the date of the agreement (06.09.2012) until realization. The appeal was allowed-in-part
pp. 53-54Original Court PDF
SRI T M BASAVARAJvsSRI L VINODH
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
