NCLAT

### Reconciliation Requests and Contractual Default Windows Constitute Pre-Existing Dispute Barring Section 9 Proceedings Key Legal Takeaways: * Pre-Existing Dispute: Persistent requests for account reconciliation, disputes over invoice discrepancies, and potential Liquidated Damages (LD) claims via email correspondence prior to a Section 8 demand notice constitute a "plausible contention" of a pre-existing dispute under the *Mobilox* standard. * Premature Default: If the contract stipulates that "default" only occurs after a specific period (e.g., 365 days) from the due date, a Section 9 application filed before the expiry of such period is premature and maintainable. * Nature of Reconciliation: Following the *Sabarmati Gas* precedent, the need for "reconciliation"—defined as an adjustment of amounts to reach an agreement—indicates a lack of consensus on the debt, thereby establishing a legal dispute that necessitates investigation beyond summary insolvency proceedings.

M/s. Sri Bajrang Wind Park Developers v. M/s Inox Wind Infrastructure Services Limited & Ors. Company Appeal (AT) (Insolvency) No. 630 of 2024.

NCLAT2 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Appellant (Operational Creditor), a partnership firm, was engaged by the Respondent (Corporate Debtor) for wind energy projects.

Source reference: no citation

The Appellant raised 75 invoices totaling approx. ₹111 Crore, of which approx. ₹25.72 Crore remained unpaid.

Source reference: para. 2

The Appellant issued a Demand Notice under Section 8 of the IBC on 02.07.2019.

Source reference: para. 2

The Respondent replied on 17.07.2019, denying the debt and later invoked arbitration on 04.02.2020, claiming damages of ₹54.50 Crore due to delays.

Source reference: para. 10

The Adjudicating Authority (NCLT, Ahmedabad) rejected the Section 9 application on 13.12.2023, citing a pre-existing dispute and lack of default.

Source reference: para. 5
02

Issues

Whether the Section 9 application was maintainable in light of a "pre-existing dispute" between the parties.

Source reference: para. 37

Whether the demand notice was premature based on the specific "default" clauses in the Work Order.

Source reference: para. 46
03

Law Applied

The court primarily applied Section 9 of the Insolvency and Bankruptcy Code, 2016, regarding the initiation of CIRP by an operational creditor.

Source reference: p. 3

It relied on the definition of "dispute" under Section 5(6) of the Code.

Source reference: para. 21

The court followed the "plausible contention" test established in *Mobilox Innovations Pvt. Ltd. v. Kirusa Software Pvt. Ltd.*, which mandates the rejection of an application if a dispute truly exists and is not spurious or moonshine.

Source reference: para. 48

Furthermore, it applied the principle from *Sabarmati Gas Ltd. v. Shah Alloys Ltd.*, holding that communications for reconciliation of accounts can evidence a pre-existing dispute.

Source reference: para. 47
04

Reasoning

The Tribunal found that extensive email correspondence dated 17.08.2018, 13.11.2018, and 05.12.2018—all prior to the Section 8 Demand Notice—contained specific discrepancies regarding invoices, tax issues, and claims for Liquidated Damages (LD) due to project delays.

Source reference: paras. 40-41

These communications indicated that the debt was not "undisputed" as the Respondent had explicitly stated that final payments were subject to reconciliation of generation losses and LD.

Source reference: para. 40

The Tribunal noted that the parties were already in active arbitration before a former Supreme Court judge where the Respondent had filed claims exceeding the Appellant’s dues.

Source reference: para. 45

Additionally, Clause 38 of the Work Order stipulated that a "default" only occurs 365 days after the due date; since the final invoices were dated May 2019, the July 2019 Demand Notice was contractually premature.

Source reference: para. 46
05

Holding

The NCLAT upheld the Adjudicating Authority's order, holding that the Section 9 petition was not maintainable due to a genuine, pre-existing dispute and the premature nature of the demand notice.

The Tribunal dismissed the appeal, noting that even though the parties mentioned a potential settlement during the pendency of the judgment, no formal consent or agreement was produced to override the merits.

Source reference: paras. 53-54

The Appeal was dismissed with no orders as to costs.

Source reference: para. 54
NCLAT

Original Court PDF

M/s. Sri Bajrang Wind Park Developers v. M/s Inox Wind Infrastructure Services Limited & Ors. Company Appeal (AT) (Insolvency) No. 630 of 2024.

NCLAT

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment