Facts
The Petitioners entered into an Agreement for Sale dated 05.11.2008 with Respondent No. 1 (Developer) for a flat in Kolkata for a consideration of Rs. 57,56,000/-
Source reference: para. 3While possession was delivered upon full payment, the Respondents allegedly failed to execute the Deed of Conveyance within the stipulated 18 months
Source reference: para. 4For several years, parties engaged in correspondence regarding discrepancies in the draft deed and maintenance issues
Source reference: paras. 5-6On 19.08.2025, the Respondents expressly waived their obligation to execute the deed, claiming the demand was barred by limitation
Source reference: para. 6The Petitioners invoked the arbitration clause (Clause 11.1) via notice dated 10.09.2025
Source reference: para. 7Upon the Respondents' refusal to appoint an arbitrator, the Petitioners approached the High Court under Section 11(6) of the Arbitration and Conciliation Act, 1996
Source reference: para. 8Issues
1. Whether the court, at the Section 11 stage, can refuse reference to arbitration on the ground that the underlying claims are ex facie barred by limitation.
Source reference: para. 142. Whether the Petitioners satisfied the requirements for the appointment of an arbitrator under Section 11(6) of the Act.
Source reference: para. 18Law Applied
Section 11(6) and Section 11(6-A) of the Arbitration and Conciliation Act, 1996, which restricts judicial intervention to the examination of the existence of an arbitration agreement
Source reference: para. 16The Supreme Court's decision in SBI General Insurance Co. Ltd. v. Krish Spinning (2024), which clarified and overruled the second limb of the test in Arif Azim Co. Ltd. v. Aptech Ltd. (2024)
Source reference: paras. 15-16Article 137 of the Limitation Act, 1963, to determine the limitation period for filing the Section 11 petition itself
Source reference: para. 16Ahmadsahab Abdul Mulla (2) v. Bibijan & Ors. regarding the commencement of limitation for specific performance
Source reference: para. 9Reasoning
The Court rejected Respondent No. 1’s contention that the claim was "dead" due to a 14-year delay.
Source reference: para. 10The Court reasoned that following the latest precedent in Krish Spinning, the referral court's inquiry is strictly limited to two aspects: (a) the prima facie existence of a valid arbitration agreement, and (b) whether the Section 11 petition was filed within three years of the refusal to appoint an arbitrator.
Source reference: para. 16The Court noted that whether the underlying claim for the conveyance deed is time-barred is a mixed question of fact and law—involving continuous assurances and negotiations—which must be decided by the Arbitral Tribunal, not the referral court.
Source reference: para. 17The Court found that the Section 11 petition was timely as it was filed shortly after the Respondents' formal refusal in 2025.
Source reference: para. 18Holding
The Court held that the objection regarding the limitation of the underlying claims is a matter for the Arbitrator to decide and cannot be a ground for refusing reference at the Section 11 stage.
The Court found that a valid arbitration agreement exists and the Section 11 petition is within limitation.
Source reference: para. 18The petition was allowed, and Mr. Sounak Bhattacharya was appointed as the Sole Arbitrator.
Source reference: para. 20The Arbitrator was granted the liberty to decide all objections, including limitation and maintainability, as preliminary issues.
Source reference: para. 21Original Court PDF
PRAMOD KUMAR NEOTIA AND ANRvsSWASTIK PROJECT PRIVATE LIMITED COMPANY AND ANR
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in