Facts
The Petitioner filed five petitions under Section 11(6) of the Arbitration and Conciliation Act, 1996, seeking the appointment of a sole arbitrator.
Source reference: p. 2The disputes arose from five similarly worded Development Agreements dated 30.06.2011, each containing an identical arbitration clause (Clause 20) designating Delhi as the venue.
Source reference: p. 3The Petitioner invoked arbitration via legal notices dated 21.12.2022.
Source reference: p. 3While the existence of the arbitration agreement was undisputed, the Respondent contended that the claims were barred by the law of limitation.
Source reference: p. 3Previous court orders had directed parties to seek a consensus on an arbitrator or explore settlement, both of which failed.
Source reference: p. 4Issues
1. Whether the court, under Section 11(6) of the Act, should resolve the issue of limitation or refer it to the Arbitral Tribunal.
Source reference: p. 3-4 / para. 112. Whether an arbitrator should be appointed to adjudicate the disputes via a composite reference given the failure of the parties to reach a consensus.
Source reference: p. 4 / para. 6Law Applied
The Court applied Section 11(6) and 11(6-A) of the Arbitration and Conciliation Act, 1996, which confines judicial scrutiny to the prima facie existence of an arbitration agreement.
Source reference: p. 5It relied heavily on the three-judge bench decision in *SBI General Insurance Co. Ltd. v. Krish Spinning*, which integrated the seven-judge bench ruling in *In re: Interplay Between Arbitration Agreements under Arbitration Act and Stamp Act*.
Source reference: p. 4-5These precedents establish that the referral court must not conduct a "laborious enquiry" into contested facts like "accord and satisfaction" or limitation, as such matters fall within the exclusive domain of the Arbitral Tribunal under the principle of competence-competence (Section 16).
Source reference: p. 6Reasoning
The Court observed that since the petitions were filed within three years of the notice invoking arbitration, the underlying issue of whether the substantive claims are time-barred is a matter for the Arbitral Tribunal to decide.
Source reference: p. 4Following the mandate in *Krish Spinning*, the Court limited its interference to verifying the existence of the arbitration agreement.
Source reference: p. 8It reasoned that the court’s role is purely facilitative—to resolve the deadlock in appointment—rather than adjudicative.
Source reference: p. 5By appointing an arbitrator, the Court ensures arbitral autonomy and adheres to the legislative intent of minimal judicial interference.
Source reference: p. 7The Court noted the parties were *ad idem* (in agreement) regarding the reference of disputes to arbitration, even though they could not agree on the specific personnel.
Source reference: p. 8Holding
The Court allowed the petitions and directed a composite reference for the five matters.
It held that the issue of limitation is within the domain of the Arbitral Tribunal.
Source reference: p. 4The Court appointed Hon’ble Mr. Justice B.R. Gavai, Former Chief Justice of India, as the Sole Arbitrator.
Source reference: p. 8The proceedings are to be conducted under the aegis of the Delhi International Arbitration Centre (DIAC) following its rules and fee schedule.
Source reference: p. 8-9All rights and contentions regarding the merits and counter-claims were kept open for the Arbitrator’s determination.
Source reference: p. 9Original Court PDF
Satnam Enterprises Private Limited v. Uppal Chadha Hi-Tech Developers Pvt. Ltd. [ARB.P. 634/2024 and connected matters.]
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in