Facts
The petitioners challenged orders rejecting their applications under Section 18 of the Land Acquisition Act, 1894, concerning land acquired for the Dharoi, Vatrak and other schemes.
Source reference: paras. 1–5; pp. 1–3The award under Section 11(1) was passed on 29 June 2005. The petitioners contended that they had never been served the mandatory notice under Section 12(2) or a certified copy of the award. They claimed to have filed applications objecting to the award on 29 June 2006, but those applications were allegedly misplaced and were taken up only after approximately eleven years.
Source reference: paras. 1–5; pp. 1–3Show-cause notices were issued in 2017 and 2018 proposing rejection on the ground of delay, followed by rejection orders dated 18 July 2018.
Source reference: paras. 1–5; pp. 1–3The petitioners’ explanations and their assertion regarding non-service of the Section 12(2) notice were allegedly not addressed in the impugned orders.
Source reference: paras. 1–5; pp. 1–3In its affidavit, the competent authority admitted that no record of service of the Section 12(2) notice could be found.
Source reference: para. 7; p. 4Issues
Whether the rejection of the petitioners’ applications under Section 18 of the Land Acquisition Act, 1894 solely on the ground of delay, without addressing their explanation for delay, was legally sustainable
Source reference: paras. 4–7; pp. 3–4Whether the impugned orders were vitiated by violation of natural justice and failure to record reasons, particularly when the petitioners disputed service of the mandatory notice under Section 12(2)
Source reference: paras. 5–7; pp. 3–4Whether the applications filed by the petitioners in 2006 were required to be forwarded to the competent civil court for a reference under Section 18
Source reference: para. 8; p. 4Law Applied
The Court applied Section 11(1) of the Land Acquisition Act, 1894, concerning the making of the land acquisition award, and Section 12(2), which requires intimation of the award to interested persons and is relevant to the computation of limitation for seeking a reference.
Source reference: paras. 5–7; pp. 3–4Section 18 provides the mechanism for referring objections to the measurement, amount of compensation, persons to whom it is payable or apportionment of compensation to the competent civil court.
Source reference: paras. 5–7; pp. 3–4The Court further applied the principles of natural justice and the duty of an administrative or quasi-judicial authority to pass a reasoned and non-arbitrary order.
Source reference: paras. 5–7; pp. 3–4An authority deciding limitation or delay must consider the affected party’s specific explanation and material contentions; an order merely stating that an application is delayed, without reasons or consideration of the objections, is legally unsustainable.
Source reference: paras. 5–7; pp. 3–4Reasoning
The Court found that the impugned orders did not disclose any reasons beyond the bare conclusion that the Section 18 applications were delayed.
Source reference: paras. 5–7; pp. 3–4They failed to consider the petitioners’ specific explanation that their applications had been filed in 2006 but were misplaced, as well as their contention that no Section 12(2) notice or certified copy of the award had been served.
Source reference: paras. 5–7; pp. 3–4This failure breached the requirement of a reasoned decision and the principles of natural justice.
Source reference: paras. 5–7; pp. 3–4The Court also relied on the authority’s admission that no record of service of the Section 12(2) notice was available, which substantially supported the petitioners’ case regarding non-service of the statutory intimation.
Source reference: para. 7; p. 4Consequently, the rejection orders could not stand, and the applications had to be processed for consideration by the competent civil court under Section 18.
Source reference: no citationHolding
The Gujarat High Court allowed the petition and quashed and set aside the orders rejecting the petitioners’ Section 18 applications filed in 2006.
The Deputy Collector/Special Land Acquisition Officer was directed to forward those applications to the competent civil court for registration and adjudication on merits under Section 18 of the Land Acquisition Act, 1894.
Source reference: para. 8; p. 5The forwarding process was directed to be completed within two weeks from receipt of the Court’s order.
Source reference: para. 8; p. 5The petition was accordingly allowed, with no order as to costs.
Source reference: para. 9; p. 5Acts & Sections Cited
3 provisions across 1 statute referred to in this judgment. Linked provisions open on LawLens.
Land Acquisition Act, 18943
Original Court PDF
SOLANKI VALAJI BHARUJI SINCE DECEASED THROUGH HEIRSvsSTATE OF GUJARAT
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
