Delhi High CourtConstruction LawArbitration and Mediation

Respondent to Defer Disqualification Decision Pending Arbitral Adjudication of Section 17 Application Concerning Deemed Non-Performance.

PRL Projects and Infrastructure Limited v. Union of India [W.P.(C) 2827/2026 and W.P.(C) 2836/2026]

Respondent to Defer Disqualification Decision Pending Arbitral Adjudication of Section 17 Application Concerning Deemed Non-Performance.. PRL Projects and Infrastructure Limited v. Union of India [W.P.(C) 2827/2026 and W.P.(C) 2836/2026]. Delhi High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

Whether the Respondent could declare the Petitioner's bid "non-responsive" based on a pending debarment proceeding that is currently sub-judice before an Arbitral Tribunal.

The court held

The Court disposed of the petitions by directing the Respondent to defer its decision on the Petitioner's representation dated 24.02.2026 until 09.03.2026.

It also directed

This ensured that the financial bids would not be opened until after the Arbitral Tribunal heard the Petitioner's Section 17 application on 07.03.2026.

The Court clarified that it expressed no opinion on the merits of the dispute with the State of Rajasthan or the disqualification itself.

01Facts

The Petitioner challenged the Respondent's (Union of India) decision dated 20.02.2026 declaring its bids for two road construction projects in Arunachal Pradesh as "non-responsive".

p. 2

The disqualification was based on the Petitioner being deemed a "non-performer" regarding a separate project in Rajasthan.

pp. 2-3

The State of Rajasthan had issued a show-cause notice for debarment on 16.12.2025, which the Petitioner challenged under Section 9 of the Arbitration and Conciliation Act.

p. 3

The Delhi High Court had previously directed that this challenge be treated as a Section 17 application before an Arbitral Tribunal.

p. 3

While that application was pending hearing (scheduled for 07.03.2026), the Respondent declared the Petitioner technically disqualified and prepared to open financial bids of other parties.

pp. 3-4

02Issues

i.Whether the Respondent could declare the Petitioner's bid "non-responsive" based on a pending debarment proceeding that is currently sub-judice before an Arbitral Tribunal.

p. 3, para 7

ii.Whether the Court should grant interim protection to the Petitioner to prevent the opening of financial bids until the Arbitral Tribunal decides on the interim relief application.

p. 4, para 10

03Law Applied

The Court considered Clause 2.1.14 of the RFP regarding "deemed non-performers".

p. 3

It indirectly applied the principles of equity and the necessity of exhausting administrative remedies, specifically focusing on the Petitioner's right to have its representation considered by the authorities under the tender conditions and the role of the Arbitral Tribunal under Section 17 of the Arbitration and Conciliation Act, 1996 to address interim disputes.

pp. 3-4

Provisions in the judgment · 2 · Linked ones open on LawLens

Arbitration and Conciliation Act, 1996 Section 9Section 17

04Reasoning

The Petitioner argued that disqualification was premature as the State of Rajasthan had not reached a final decision and the matter was under active adjudication by an Arbitrator.

p. 3

The Respondent countered that it would first scrutinize the Petitioner’s representation dated 24.02.2026 against the disqualification before proceeding to open financial bids.

p. 4

The Court noted that the interim application before the Arbitrator specifically sought to prevent disqualification from other tenders based on the Rajasthan dispute.

p. 4

To balance the interests, the Court observed that since the Arbitral Tribunal was set to hear the matter on 07.03.2026, it would be appropriate for the Respondent to defer its final decision on the disqualification representation until after that date to allow the specialized tribunal to weigh in on the underlying debarment issue.

p. 4

05Holding

The Court disposed of the petitions by directing the Respondent to defer its decision on the Petitioner's representation dated 24.02.2026 until 09.03.2026.

pp. 4-5

This ensured that the financial bids would not be opened until after the Arbitral Tribunal heard the Petitioner's Section 17 application on 07.03.2026.

p. 4

The Court clarified that it expressed no opinion on the merits of the dispute with the State of Rajasthan or the disqualification itself.

p. 5
Delhi High Court

Original Court PDF

PRL Projects and Infrastructure Limited v. Union of India [W.P.(C) 2827/2026 and W.P.(C) 2836/2026]

Delhi High Court · no citation

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment