01Facts
The Petitioner, a Special Purpose Vehicle (SPV), was awarded two 70 MW solar projects in Bhadla Solar Park, Rajasthan
¶ 2Power Purchase Agreements (PPAs) were executed with NTPC (Respondent No. 2) with a Scheduled Commercial Operation Date (SCOD) of June 1, 2017
¶ 3Due to delays in the transmission system provided by the State Transmission Utility (RRVPNL), commissioning was delayed until August 2017
¶ 4, 40Consequently, NTPC encashed the Petitioner’s Performance Bank Guarantees totaling INR 7.6 Crores as Liquidated Damages (LD) on September 25, 2018
¶ 5, 11The CERC initially rejected the Petitioner's plea for SCOD extension and LD waiver
¶ 8In Appeal No. 126 of 2022, the Tribunal set aside the CERC order, extended the SCOD, and directed NTPC to refund the LD
¶ 10The Petitioner subsequently filed this Review Petition seeking (i) carrying cost/interest on the refunded LD and (ii) compensation for generation loss of INR 16 Crores due to transmission non-availability
¶ 1102Issues
i.1. Whether the failure to adjudicate the claim for generation loss in the main appeal constitutes an "error apparent on the face of record" justifying a review under Order XLVII Rule 1 of the CPC.
¶ 19-24ii.2. Whether the Petitioner is entitled to carrying cost/interest on the liquidated damages amount ordered to be refunded by NTPC.
¶ 25-3203Law Applied
The Tribunal applied the narrow standards of review jurisdiction under Section 114 and Order XLVII Rule 1 of the Code of Civil Procedure (CPC), which permit review only for discovery of new evidence, errors apparent on the face of record, or other sufficient analogous reasons
¶ 13-16It relied on Kamlesh Verma v. Mayawati, which established that a review is not an "appeal in disguise" and cannot be used to argue points not raised in the original hearing
¶ 17Regarding interest, the Tribunal applied the Doctrine of Restitution, noting that interest is a necessary corollary to the return of money unjustly retained, as established in Alok Shanker Pandey v. Union of India and Dr. Purnima Advani v. Govt. of NCT
¶ 26, 30Provisions in the judgment · 2 · Linked ones open on LawLens
Code of Civil Procedure, 1908 Section 114Section 47
04Reasoning
Regarding the claim for generation loss, the Tribunal observed that the Petitioner failed to agitate this point during oral arguments or in written submissions in the main appeal
¶ 19-20Citing Priyanka Communications v. Tata Capital, the Tribunal held that a counsel’s failure to argue a pleaded point is not a ground for review; a party cannot seek "forensic archaeological excavation" of the record to revive abandoned claims
¶ 23-24Regarding carrying cost, the Tribunal found an "error apparent" in its previous judgment, as it had inadvertently omitted the interest aspect despite holding the levy of LD to be "unjust and untenable"
¶ 27-28Since NTPC was "unjustly enriched" by encashing the bank guarantees in 2018, the principle of restitution required the Petitioner to be compensated for the time-value of money
¶ 27, 31The Tribunal noted that even if not specifically pleaded, interest/carrying cost can be granted in furtherance of the intention of the parties and equity
¶ 29-3005Holding
The Review Petition was partly allowed
¶ 34The Tribunal dismissed the claim for generation loss as it was not argued in the main appeal
¶ 24However, it modified Paragraph 42 of the original judgment to hold that the Petitioner is entitled to carrying cost at the State Bank of India Prime Lending Rate (SBI PLR) on the INR 7.6 Crores
¶ 32-33NTPC was directed to pay this carrying cost from the date the Bank Guarantees were encashed until the date of actual refund
¶ 33Original Court PDF
M/s Solaire Surya Urja Pvt. Ltd.vsCentral Electricity Regulatory Commission & Ors
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
