Bombay High Court
Arbitration and MediationContract Law

Restoration of a terminated determinable contract requires a strong case for interim mandatory relief.

S Rajakumar Propritor Of The Arungaraiamman Transports vs Bharat Petroleum Corporation Limited

Bombay High CourtJUDGMENT: August 14, 20264 MIN READSOURCE JUDGMENT
Restoration of a terminated determinable contract requires a strong case for interim mandatory relief.. S Rajakumar Propritor Of The Arungaraiamman Transports vs Bharat Petroleum Corporation Limited. Bombay High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The judgment disposed of eight connected petitions under Section 9 of the Arbitration and Conciliation Act, 1996, arising from termination of LPG transportation arrangements by BPCL and IOCL.

Source reference: para. 1–2

The petitioners had participated in a tender for transportation of bulk LPG using tank trucks offered under an “Agreement to Sell” arrangement (“ATS trucks”). Corrigendum No. 3 permitted such trucks to participate but required transfer of the Registration Certificate and PESO licence within four months of the Letter of Intent, failing which penal action could include forfeiture of caution money, termination and blacklisting.

Source reference: para. 24–27

In the lead matter, the Letter of Intent was issued on 19 October 2025, making 19 February 2026 the deadline for compliance. The truck’s Registration Certificate was transferred within time on 18 February 2026, but the application for transfer of the PESO licence was made on 23 February 2026 and the licence was transferred on 26 February 2026.

Source reference: para. 28–29

Although LPG loads were allotted even after the deadline, the respondent later sought the relevant documents, issued a show-cause notice, suspended allotments and, after considering the petitioner’s reply, terminated the arrangement on 15 June 2026 and forfeited the caution money of Rs.1,00,000.

Source reference: para. 35–37

The petitioners sought suspension of the termination, protection against forfeiture, and mandatory directions requiring the respondents to resume and continuously allot LPG loads pending constitution and completion of the arbitral proceedings.

Source reference: para. 23
02

Issues

Whether the Court should restrain the respondents from acting upon the termination orders and direct restoration and continued performance of the LPG transportation contracts pending arbitration?

Source reference: para. 23, 45–50

Whether the contracts were determinable by their nature, so that an order effectively restoring or specifically enforcing them would be impermissible under Section 14(d) of the Specific Relief Act, 1963?

Source reference: para. 38–45

Whether the respondents should be restrained from appropriating or finally dealing with the forfeited caution money until the arbitral tribunal considers the parties’ dispute?

Source reference: para. 61–62
03

Law Applied

The Court applied Section 9 of the Arbitration and Conciliation Act, 1996, governing interim measures in aid of arbitration, together with the principles applicable to interlocutory mandatory injunctions.

Source reference: no citation

Relying on Dorab Cawasji Warden v. Coomi Sorab Warden, (1990) 2 SCC 117, and Samir Narain Bhojwani v. Aurora Properties & Investments, (2018) 17 SCC 203, the Court held that an interim mandatory injunction requires a stronger case than an ordinary prima facie case, proof of irreparable or serious injury not ordinarily compensable in money, and a balance of convenience in favour of the applicant.

Source reference: para. 46–47

Section 14(d) of the Specific Relief Act bars enforcement of a contract which is determinable by its nature.

Source reference: para. 16, 38

Following the principle stated in Indian Oil Corporation Ltd., restoration of a distributorship or contractual relationship cannot ordinarily be granted where the contract is revocable in accordance with its terms, even if the termination is subsequently found wrongful.

Source reference: para. 44–45

The Court also applied the contractual provisions permitting termination on 30 days’ notice without assigning reasons, and the Corrigendum provision that penal action “may include” forfeiture, termination and blacklisting.

Source reference: para. 26, 31–32, 38–43
04

Reasoning

The Court held that the petitioners had an arguable case concerning the short delay in transferring the PESO licence, the respondents’ continued allotment of LPG loads after the contractual deadline, and whether the contractual phrase “may include” required proportionality in the choice of penalty.

Source reference: para. 31–36, 49–50

However, the petitioners’ own case showed that the PESO-transfer process had not even been initiated before the deadline; therefore, they had not established the stronger case required for an interim mandatory injunction.

Source reference: para. 28–29, 50

The requested direction to resume and continuously allot LPG loads would not merely preserve the existing position but would restore a terminated commercial relationship and compel continued performance.

Source reference: no citation

This was particularly significant because Clause 33 independently permitted termination or foreclosure on 30 days’ notice without assigning reasons, making the contract prima facie determinable.

Source reference: para. 41–45

The asserted difficulty in quantifying damages, limited operational life of the trucks and reputational injury did not satisfy the heightened threshold for mandatory interim relief.

Source reference: para. 51–55

Nevertheless, because the validity and proportionality of forfeiting the caution money remained matters for arbitration, the Court directed that the amount be preserved separately pending recourse to the arbitral tribunal.

Source reference: para. 61
05

Holding

The Court rejected the prayer for resumption and continuous allotment of LPG loads, holding that such relief would effectively restore and specifically enforce a terminated, prima facie determinable contract.

It directed the respondents to maintain the caution money of Rs.1,00,000 in a separate account and prohibited its appropriation, utilisation or final disposal until commencement of arbitration and an appropriate application before the arbitral tribunal.

Source reference: para. 61–62(ii)

This protection did not stay or set aside the termination order and did not restore or continue the transport contract.

Source reference: para. 62(iii)

The arbitral tribunal was directed to decide the disputes independently and without being influenced by the Court’s prima facie observations.

Source reference: para. 62(iv)

The petitions were disposed of without costs.

Source reference: para. 62(v)–(vi)
06

Acts & Sections Cited

3 provisions across 2 statutes referred to in this judgment. Each provision opens on LawLens.

Arbitration and Conciliation Act, 19961

Specific Relief Act, 19632

Bombay High Court

Original Court PDF

S Rajakumar Propritor Of The Arungaraiamman TransportsvsBharat Petroleum Corporation Limited

Bombay High Court · August 14, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment