Facts
The Appellant, a High Tension consumer operating a 7 MW Captive Power Plant (CPP) in Maharashtra, sought reduction of its contract demand from 5300 kVA to 3000 kVA in 1998
Source reference: p. 4Respondent No. 1 (MSEDCL) refused, citing circulars imposing "take-or-pay" obligations and minimum off-take requirements
Source reference: p. 4-5In the first round of litigation (Case No. 35 of 2002), the Maharashtra Electricity Regulatory Commission (MERC) quashed these circulars and ordered a refund
Source reference: p. 7This was upheld by the Appellate Tribunal (APTEL) in 2007
Source reference: p. 8-10However, the Hon’ble Supreme Court, in Civil Appeal No. 4304 of 2007 (decided on 28.02.2020), set aside both orders, ruling that the circulars were validly issued before MERC’s establishment and had been illegally quashed
Source reference: p. 10Following this, the Appellant filed a fresh petition (No. 17 of 2021) before MERC seeking various refunds and declarations, which MERC dismissed on 12.07.2021, prompting this appeal
Source reference: p. 2-3, 11Issues
1. Whether the issues of reduction of contract demand and extension of supply from the CPP remained alive following the Supreme Court’s judgment in Civil Appeal No. 4304 of 2007
Source reference: p. 112. Whether the Appellants were entitled to refunds and rectified billing despite the Supreme Court's restoration of the MSEB circulars
Source reference: p. 11-12Law Applied
The court applied the principle of judicial finality and the doctrine of merger regarding the Supreme Court's judgment under Section 125 of the Electricity Act, 2003
Source reference: p. 12It relied on the validity of administrative circulars (Circular Nos. 602, 619, 627, 651, and 663) which established "take-or-pay" obligations and minimum off-take requirements for CPP holders
Source reference: p. 12-13Under Section 44 of the Electricity (Supply) Act, 1948, the court recognized that permissions to install CPPs are subject to the policy conditions and rules framed by the State Electricity Board
Source reference: p. 14-15Reasoning
The Tribunal rejected the Appellant's contention that the Supreme Court had only addressed the legality of the circulars while leaving the issues of "contract demand" and "extension of supply" untouched
Source reference: p. 11Upon reviewing the original Memorandum of Appeal filed before the Supreme Court, the Tribunal noted that MSEDCL had specifically challenged the findings on contract demand and unauthorized supply
Source reference: para 7 & 8, p. 14The Tribunal reasoned that since the Supreme Court set aside the entirety of the previous orders and restored the circulars, the legal basis for the Appellant's claims—the quashing of those circulars—had been removed
Source reference: p. 15The restoration of the circulars automatically reinstated the "take-or-pay" and minimum off-take obligations, making the Appellant's request for contract demand reduction inconsistent with the restored regulatory framework
Source reference: p. 15-16Holding
The Tribunal held that the petition filed by the Appellant before the Commission was a "misconceived and malafide attempt" to re-litigate matters already settled by the Supreme Court
The Tribunal affirmed that the Supreme Court's judgment dated 28.02.2020 was comprehensive, covering all issues including contract demand. Consequently, the Appeal was dismissed, and the MERC order dated 12.07.2021 was upheld
Source reference: p. 16Original Court PDF
EUROTEX INDUSTRIES AND EXPORTS LIMITEDvsMAHARASHTRA STATE ELECTRICITY DISTRIBUTION COMPANY LTD. & Anr
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in