01Facts
The land was granted in 1956 to the original grantee.
It was sold through a registered sale deed in 1970.
¶ 6 · p. 6In 2016, resumption proceedings were initiated before the Assistant Commissioner, about 46 years after the sale and 37 years after the commencement of the PTCL Act.
¶ 6 · p. 6The Assistant Commissioner rejected the claim.
¶ 6 · pp. 6–7On appeal, the Deputy Commissioner allowed it and ordered resumption, without considering the delay or the petitioners' plea of laches.
¶ 6 · p. 7The impugned order dated 07.01.2026 (Annexure-G) is challenged in this writ petition under Articles 226 and 227.
¶ 2, 4 · pp. 3–4Respondents 3 to 6 contended that the resumption was justified by violations of the PTCL Act and sought dismissal.
¶ 4 · p. 502Issues
i.1. Whether the Deputy Commissioner erred in directing resumption without examining the delay of about 46 years from the registered sale deed and 37 years from the commencement of the PTCL Act, and the plea of laches.
¶ 6 · pp. 6–7ii.2. Whether the resumption order dated 07.01.2026 can be legally sustained in view of the extraordinary delay.
¶ 6 · p. 7 · ¶ 7 · p. 703Law Applied
The PTCL Act, the statute under which resumption was sought, though the judgment does not cite any specific section.
¶ 6 · p. 6A Division Bench ruling, not named in the judgment, which held that laches is the primary requirement in resumption of lands and that restoration action filed after a significant delay may be barred by laches.
¶ 6 · p. 7 · no citationFailure to consider a material and relevant consideration, here delay and laches, vitiates the impugned order.
¶ 6 · p. 7The writ of certiorari under Articles 226 and 227 was the relief employed to quash the order.
¶ 8 · p. 704Reasoning
The Deputy Commissioner was required to examine whether invoking the PTCL Act after such a long lapse was justified, particularly since rights in the land had crystallised under the registered sale deed of 1970.
¶ 6 · p. 7Because the Deputy Commissioner overlooked the 46-year delay and the laches plea, he failed to consider a material and relevant factor.
¶ 6 · p. 7Applying the Division Bench principle that delayed restoration action may be barred by laches, the resumption order could not be sustained.
¶ 6 · p. 7The court did not record any finding on the respondents' allegations of PTCL Act violations, as its decision rested on the failure to consider delay and laches.
¶ 4, 6 · pp. 5–705Holding
The Deputy Commissioner's order directing resumption cannot be legally sustained because it failed to consider delay and laches, which vitiated the order.
¶ 6 · p. 7 · ¶ 7 · p. 7The writ petition is allowed. The order dated 07.01.2026 (Annexure-G) is quashed by a writ of certiorari, and the authority concerned is directed to mutate or restore the petitioners' names in the revenue records for the subject land. Any interim order stands discharged and pending interlocutory applications, if any, are disposed of.
¶ 8 · p. 7 · ¶ 9 · p. 7 · p. 8Original Court PDF