Chhattisgarh High Court
Administrative and Public LawCivil Procedure and Evidence

RTI penalty requires a finding of deliberate or mala fide failure; delay alone is insufficient.

MADHURANI RATREY vs CHHATTISGARH STATE INFORMATION COMMISSION

Chhattisgarh High CourtJUDGMENT: September 09, 20263 MIN READSOURCE JUDGMENT
RTI penalty requires a finding of deliberate or mala fide failure; delay alone is insufficient.. MADHURANI RATREY vs CHHATTISGARH STATE INFORMATION COMMISSION. Chhattisgarh High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioner, Secretary/Public Information Officer of Gram Panchayat Jhapeli, challenged the order dated 16 May 2024 imposing a penalty of ₹25,000 for failure to furnish information under the Right to Information Act, 2005 within the prescribed period.

Source reference: para. 2

She contended that no proper show-cause notice had been issued, that the information had subsequently been furnished, and that the authority had not recorded any finding that the delay was mala fide, deliberate, or intentional.

Source reference: para. 2

The State Information Commission contended that the petitioner had been afforded an opportunity of hearing and that a show-cause notice had been issued.

Source reference: para. 3

It was undisputed that the requested information had ultimately been supplied to and accepted by the information seeker.

Source reference: para. 4

The High Court examined whether the penalty could be sustained merely on the basis of delay in furnishing the information.

Source reference: paras. 5–10
02

Issues

Whether a penalty under Section 20 of the Right to Information Act, 2005 could be imposed merely because of delay in furnishing information, without a specific finding that the Public Information Officer deliberately, intentionally, or mala fide failed to provide the information?

Source reference: paras. 6–10

Whether the penalty order was sustainable when the requested information had subsequently been furnished and accepted by the information seeker?

Source reference: paras. 8–10
03

Law Applied

The Court applied Sections 20(1) and 20(2) of the Right to Information Act, 2005, which govern the imposition of penalty and disciplinary action against a Public Information Officer for specified defaults in performing statutory duties.

Source reference: para. 2

The Court relied on Manohar S/o Manikrao Anchule v. State of Maharashtra, (2012) 13 SCC 14, which requires the competent authority to examine whether the failure was deliberate or negligent, whether it occurred without reasonable cause, and whether the conduct of the Public Information Officer justified the imposition of penalty.

Source reference: para. 7

Mere delay, without a specific finding of intentional, deliberate, or mala fide withholding of information, is insufficient to sustain a penalty under Section 20.

Source reference: paras. 7–9
04

Reasoning

The Court found that the impugned order proceeded essentially on the fact of delay and did not contain a categorical finding that the petitioner had deliberately, intentionally, or mala fide withheld the information.

Source reference: paras. 6, 8

Although the respondents asserted that the petitioner had received a show-cause notice and an opportunity of hearing, the authority had failed to record the necessary finding regarding deliberate failure or absence of reasonable cause, as required by the principles laid down in Manohar.

Source reference: paras. 3, 7–8

The subsequent furnishing and acceptance of the information was also a relevant circumstance that the authority ought to have considered while determining whether the delay resulted from deliberate or mala fide conduct.

Source reference: para. 9

Consequently, the penalty could not be sustained merely because the information was supplied beyond the prescribed period.

Source reference: paras. 9–10
05

Holding

The High Court held that the penalty of ₹25,000 was legally unsustainable in the absence of a specific finding that the petitioner had deliberately, intentionally, or mala fide failed to furnish the information, particularly since the information had ultimately been supplied and accepted.

The writ petition was allowed, and the order dated 16 May 2024, insofar as it imposed the penalty upon the petitioner, was quashed.

Source reference: paras. 11–13

No order as to costs was made.

Source reference: paras. 11–13
06

Acts & Sections Cited

1 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.

Right to Information Act, 20051

Chhattisgarh High Court

Original Court PDF

MADHURANI RATREYvsCHHATTISGARH STATE INFORMATION COMMISSION

Chhattisgarh High Court · September 09, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment