01Facts
The parties entered into a Contract Agreement on 07.12.2012 for certain works
p. 2The Arbitrator, vide award dated 23.01.2020, awarded the Respondent ₹4,80,37,967/-, finding that the termination of the contract by the Appellant was wrongful due to a force majeure event (Nepal earthquake)
pp. 3-4The Appellant challenged this award under Section 34 of the Arbitration and Conciliation Act, 1996, primarily alleging a computational error in Claim No. 6 (Performance Bank Guarantee - PBG) and Claim No. 12
p. 5Specifically, the Appellant argued that a mobilization advance of ₹93,01,410/- already recovered was not adjusted in the PBG refund
p. 7The Single Judge dismissed the Section 34 petition on 24.07.2024, noting that this adjustment plea was never raised before the Arbitrator
p. 6The Appellant then filed this appeal under Section 37, restricting the challenge solely to Claim No. 6
p. 702Issues
i.1. Whether the learned Single Judge erred in declining to interfere with the Award under Section 34 when the Appellant alleged a failure to account for the adjustment of mobilization advance in Claim No. 6.
p. 2 / para 3ii.2. Whether the Court in an appeal under Section 37 can entertain a fresh factual plea regarding computational errors that was not raised before the Arbitrator.
p. 15 / para 4103Law Applied
The Court applied Section 37 of the Arbitration and Conciliation Act, 1996, which governs appeals against orders setting aside or refusing to set aside an arbitral award
p. 1The scope of interference under Section 37 is narrower than under Section 34 and does not permit re-appreciation of evidence or de novo factual findings, as established in MMTC Ltd. v. Vedanta Ltd., UHL Power Co. Ltd. v. State of Himachal Pradesh, and NHAI v. M. Hakeem.
pp. 10-11The supervisory role of the court is limited to instances of patent illegality or jurisdictional error as per McDermott International Inc. v. Burn Standard Co. Ltd.
p. 11Provisions in the judgment · 3 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 33Section 34Section 37
04Reasoning
The Court observed that Claim No. 6 (PBG refund) and Claim No. 7 (Mobilization Advance) were distinct. The Arbitrator found the contract termination illegal, making the PBG encashment wrongful
p. 12Regarding the alleged non-adjustment of ₹93,01,410/-, the Court noted that the Appellant failed to raise this specific plea in its Statement of Defence before the Arbitrator
p. 3 & 6the Respondent filed an affidavit clarifying that the mobilization advance was indeed adjusted through RA bills and PBG encashment, and the final award was computed after such adjustments
pp. 13-14The Court reasoned that to interfere would require a reconciliation of accounts and re-evaluation of facts, which is prohibited under Section 37
¶ 39Since the Appellant could not demonstrate "patent illegality" but only a "speculative apprehension" of double payment, no grounds for interference existed
¶ 4005Holding
The Court held that since the material on record showed the mobilization advance was accounted for and the factual plea was not raised during arbitration, the award did not suffer from patent illegality
¶ 40-42The Court dismissed the appeal, holding that the learned Single Judge correctly declined to interfere with the Award. The final order upheld the judgment dated 24.07.2024 and dismissed the Appellant's challenge to the computation of Claim No. 6
pp. 15 / para 40-43Original Court PDF
Ircon International LimitedvsM/S. Tantia Construction Limited
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
