Delhi High CourtArbitration and MediationCivil Procedure and Evidence

Scope of Appeal under Section 37 is limited to examining whether the Section 34 Court exceeded its jurisdiction.

Ircon International Limitedv.M/S. Tantia Construction Limited

Scope of Appeal under Section 37 is limited to examining whether the Section 34 Court exceeded its jurisdiction.. Ircon International Limited vs M/S. Tantia Construction Limited. Delhi High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the learned Single Judge erred in declining to interfere with the Award under Section 34 when the Appellant alleged a failure to account for the adjustment of mobilization advance in Claim No. 6.

The court held

The Court held that since the material on record showed the mobilization advance was accounted for and the factual plea was not raised during arbitration, the award did not suffer from patent illegality

It also directed

The Court dismissed the appeal, holding that the learned Single Judge correctly declined to interfere with the Award. The final order upheld the judgment dated 24.07.2024 and dismissed the Appellant's challenge to the computation of Claim No. 6

01Facts

The parties entered into a Contract Agreement on 07.12.2012 for certain works

p. 2

The Arbitrator, vide award dated 23.01.2020, awarded the Respondent ₹4,80,37,967/-, finding that the termination of the contract by the Appellant was wrongful due to a force majeure event (Nepal earthquake)

pp. 3-4

The Appellant challenged this award under Section 34 of the Arbitration and Conciliation Act, 1996, primarily alleging a computational error in Claim No. 6 (Performance Bank Guarantee - PBG) and Claim No. 12

p. 5

Specifically, the Appellant argued that a mobilization advance of ₹93,01,410/- already recovered was not adjusted in the PBG refund

p. 7

The Single Judge dismissed the Section 34 petition on 24.07.2024, noting that this adjustment plea was never raised before the Arbitrator

p. 6

The Appellant then filed this appeal under Section 37, restricting the challenge solely to Claim No. 6

p. 7

02Issues

i.1. Whether the learned Single Judge erred in declining to interfere with the Award under Section 34 when the Appellant alleged a failure to account for the adjustment of mobilization advance in Claim No. 6.

p. 2 / para 3

ii.2. Whether the Court in an appeal under Section 37 can entertain a fresh factual plea regarding computational errors that was not raised before the Arbitrator.

p. 15 / para 41

03Law Applied

The Court applied Section 37 of the Arbitration and Conciliation Act, 1996, which governs appeals against orders setting aside or refusing to set aside an arbitral award

p. 1

The scope of interference under Section 37 is narrower than under Section 34 and does not permit re-appreciation of evidence or de novo factual findings, as established in MMTC Ltd. v. Vedanta Ltd., UHL Power Co. Ltd. v. State of Himachal Pradesh, and NHAI v. M. Hakeem.

pp. 10-11

The supervisory role of the court is limited to instances of patent illegality or jurisdictional error as per McDermott International Inc. v. Burn Standard Co. Ltd.

p. 11

Provisions in the judgment · 3 · Linked ones open on LawLens

Arbitration and Conciliation Act, 1996 Section 33Section 34Section 37

04Reasoning

The Court observed that Claim No. 6 (PBG refund) and Claim No. 7 (Mobilization Advance) were distinct. The Arbitrator found the contract termination illegal, making the PBG encashment wrongful

p. 12

Regarding the alleged non-adjustment of ₹93,01,410/-, the Court noted that the Appellant failed to raise this specific plea in its Statement of Defence before the Arbitrator

p. 3 & 6

the Respondent filed an affidavit clarifying that the mobilization advance was indeed adjusted through RA bills and PBG encashment, and the final award was computed after such adjustments

pp. 13-14

The Court reasoned that to interfere would require a reconciliation of accounts and re-evaluation of facts, which is prohibited under Section 37

¶ 39

Since the Appellant could not demonstrate "patent illegality" but only a "speculative apprehension" of double payment, no grounds for interference existed

¶ 40

05Holding

The Court held that since the material on record showed the mobilization advance was accounted for and the factual plea was not raised during arbitration, the award did not suffer from patent illegality

¶ 40-42

The Court dismissed the appeal, holding that the learned Single Judge correctly declined to interfere with the Award. The final order upheld the judgment dated 24.07.2024 and dismissed the Appellant's challenge to the computation of Claim No. 6

pp. 15 / para 40-43
Delhi High Court

Original Court PDF

Ircon International LimitedvsM/S. Tantia Construction Limited

Delhi High Court · May 19, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment