Facts
The Appellant (TML) entered into a Construction Agreement with the Respondent (NIRLAC) in 1995 to build on a plot leased from the President of India
Source reference: p. 3Clause 3.2(a) stipulated 36% interest p.a. on delayed payments
Source reference: p. 4TML completed construction in 1999, but NIRLAC defaulted
Source reference: p. 5To recover costs, TML leased portions of the building to third parties until the property was sealed by the MCD in 2006 for unauthorized subletting
Source reference: p. 6TML issued a demand notice on 20.01.2007 claiming construction costs and 36% interest
Source reference: p. 6In the subsequent two arbitrations, the Arbitrator reduced interest to 7.5% from 2007 (Arbitration I) and rejected maintenance claims (Arbitration II)
Source reference: p. 2A Single Judge set aside the reduction of the interest rate but upheld the date of commencement (2007) and the denial of maintenance penalties
Source reference: p. 3TML appealed under Section 37 of the Arbitration Act
Source reference: p. 1Issues
1. Whether the learned Arbitrator and Single Judge erred in reckoning the interest on construction costs from 20.01.2007 instead of the original default dates in 1995-1999
Source reference: p. 9 / para. 42. Whether the rejection of the claim for interest/penalty at 2% per month on outstanding electricity and maintenance charges was legally sustainable
Source reference: p. 12 / para. 12Law Applied
Section 37 and Section 34 of the Arbitration and Conciliation Act, 1996, which restrict judicial interference to grounds of patent illegality or conflict with public policy
Source reference: p. 14-15Jan De Nul Dredging India (P) Ltd. v. Tuticorin Port Trust (2026) regarding the "minimum intervention" principle
Source reference: p. 14Ssangyong Engineering & Construction Co. Ltd. v. NHAI (2015), which establishes that an arbitrator’s interpretation of a contract is final unless it is one that no fair-minded person could adopt
Source reference: p. 19-21Section 74 of the Indian Contract Act, 1872 was applied to differentiate between reasonable compensation and penal interest
Source reference: p. 29Reasoning
Regarding Issue 1, the Court held that the Arbitrator’s interpretation of "three options" for recovery under Clause 3.2 was a plausible reading of the contract
Source reference: p. 23The Court found that until the 2007 notice, TML acted as a "lessee" bearing costs to enjoy the property, rather than a "creditor" demanding payment, evidenced by TML’s own balance sheets which did not list NIRLAC as a debtor
Source reference: p. 24, 26Thus, shifting to the "debt recovery" option only occurred in 2007 after the property was sealed
Source reference: para. 84Regarding Issue 2, the Court analyzed Clause 11 of the Maintenance Agreement, agreeing with the Arbitrator that the 2% monthly charge was a "penalty" under Section 74 of the Contract Act
Source reference: p. 29Since the Arbitrator found no underlying debt for service charges due to prior excess recoveries by TML, the claim for penalty/interest could not survive
Source reference: p. 30Holding
The Court dismissed the appeal and upheld the Single Judge’s judgment
The Court affirmed that interest on construction costs is payable from 20.01.2007 (the date of the demand notice) and confirmed the rejection of penal interest on maintenance charges
Source reference: p. 26, 31It held that the scope of Section 37 is narrower than Section 34 and does not permit re-appreciation of evidence or choice between two plausible interpretations
Source reference: p. 17-18The liberty granted to TML by the Single Judge to seek a fresh reference on the rate of interest remained undisturbed
Source reference: p. 13Original Court PDF
Turner Morrison LtdvsKarma Konchok Namgyal
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in