Delhi High CourtArbitration and MediationContract Law

Scope of Section 34 inquiry excludes reappreciation of evidence or substitution of plausible contractual interpretations.

M/S Sdb Consultants Pvt. Ltd.v.Smc Pneumatics (I) Pvt . Ltd.

Scope of Section 34 inquiry excludes reappreciation of evidence or substitution of plausible contractual interpretations.. M/S Sdb Consultants Pvt. Ltd. vs Smc Pneumatics (I) Pvt . Ltd.. Delhi High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the Petitioner completed the project in terms of Clause 10 of the Agreement

The court held

The Court dismissed the petition, holding that the Petitioner failed to establish any grounds of patent illegality or perversity

It also directed

The Court affirmed the Arbitral Award, confirming the Petitioner's entitlement to only INR 4,48,316/- with interest at 18% p.a. from 20.07.2014

The Court concluded that the Arbitrator had provided a well-structured adjudication within the confines of the contract and the evidence provided

01Facts

The Petitioner, a project management consultancy, entered into a contract dated 23.08.2012 with the Respondent for architectural and engineering services for a factory project

p. 2

The contract outlined a consolidated fee of INR 31 Lakhs payable in seven stages

pp. 2-3

Clause 10 specified that the Petitioner’s obligations would continue for 12 months post-completion as per the official certificate

p. 2

Although the Petitioner claimed the project had a 6-month completion timeline, it withdrew its Site Engineer on 07.06.2014 before completion, citing non-payment of dues

pp. 4-5

The Petitioner raised an invoice on 04.04.2014 for the full 100% contract value (INR 31 Lakhs)

p. 4, 15

Following a Section 11 petition, a Sole Arbitrator was appointed who, on 27.09.2025, dismissed the Respondent’s counter-claims and partially allowed the Petitioner’s claims to the extent of INR 4,48,316/- with 18% interest

p. 1, 7

The Petitioner challenged this award under Section 34 of the Arbitration and Conciliation Act, 1996, seeking a higher recovery

p. 7

02Issues

i.1. Whether the Petitioner completed the project in terms of Clause 10 of the Agreement

p. 6 / para. 2(xii)

ii.2. Whether the Petitioner was entitled to the full invoice amount of INR 17,41,480/- dated 04.04.2014

p. 6 / para. 2(xii)

iii.3. Whether the Petitioner was entitled to supplementary claims for design deviations and prolonged supervision

p. 17 / para. 19

03Law Applied

The Court applied Section 34 of the Arbitration and Conciliation Act, 1996, emphasizing that an award can only be set aside for "patent illegality" or violation of "public policy," which does not permit reappreciation of evidence or correction of mere errors of law

pp. 8-10

It applied the "Possible View" doctrine from MMTC Ltd. v. Vedanta Ltd. and Associate Builders v. DDA, holding that if an arbitrator’s interpretation is plausible, the court cannot intervene

p. 9, 11

Sections 91 and 92 of the Indian Evidence Act, 1872, were applied to exclude oral evidence that contradicted the written terms of the contract regarding project timelines

p. 13

Provisions in the judgment · 8 · Linked ones open on LawLens

Arbitration and Conciliation Act, 1996 Section 11Section 14Section 15Section 28Section 34Section 37Section 75Section 81

04Reasoning

The Court found that the Arbitrator correctly interpreted Clause 10, noting the absence of any written 6-month completion deadline; the Petitioner’s reliance on oral understandings was barred by the Evidence Act

pp. 12-13

Regarding the 100% payment claim, the Court upheld the Arbitrator’s finding that since the Petitioner admitted in its own pleadings and letters that the building was "far from complete" and it had withdrawn its staff prematurely, it was only entitled to payment for the four stages actually completed (INR 20,89,896/- minus payments already received)

pp. 14, 16-17

On the issue of supplementary bills for deviations, the Court agreed with the Arbitrator that while Clause 6 of the contract usually barred extra costs for deviations, it only applied to changes made before bidding; since changes occurred during construction, the Arbitrator’s nominal award of INR 1 Lakh for extra work was a reasoned and plausible determination based on the evidence

pp. 18-19

05Holding

The Court dismissed the petition, holding that the Petitioner failed to establish any grounds of patent illegality or perversity

p. 20

The Court affirmed the Arbitral Award, confirming the Petitioner's entitlement to only INR 4,48,316/- with interest at 18% p.a. from 20.07.2014

p. 1, 20

The Court concluded that the Arbitrator had provided a well-structured adjudication within the confines of the contract and the evidence provided

pp. 19-20
Delhi High Court

Original Court PDF

M/S Sdb Consultants Pvt. Ltd.vsSmc Pneumatics (I) Pvt . Ltd.

Delhi High Court · July 16, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment