Facts
The Petitioner, Oriental Foundry Private Limited, entered into Contract No. 2022/RS(I)/954/212/1945 dated 17.05.2025 with the Union of India
Source reference: p. 2Disputes emerged regarding the contract, leading the Petitioner to issue a notice under Section 21 of the Arbitration and Conciliation Act, 1996, on 24.12.2025
Source reference: p. 3The Petitioner filed a petition under Section 11(6) for the appointment of a Sole Arbitrator and a separate petition under Section 9 seeking interim protection against the encashment of a Bank Guarantee dated 07.02.2025
Source reference: p. 2, 9The Respondent expressed no objection to the reference of the dispute to arbitration
Source reference: p. 3Issues
1. Whether a Sole Arbitrator should be appointed under Section 11(6) of the Arbitration and Conciliation Act, 1996, to resolve disputes arising from the contract
Source reference: p. 22. Whether the interim protection sought regarding the Bank Guarantee should be maintained during the pendency of the arbitral proceedings
Source reference: p. 9Law Applied
The court primarily applied Section 11(6) of the Arbitration and Conciliation Act, 1996, regarding the court's power to appoint an arbitrator when the agreed procedure fails
Source reference: p. 2It relied on the Supreme Court's decision in *SBI General Insurance Co. Ltd. v. Krish Spinning*, which clarified that judicial scrutiny under Section 11 is confined solely to a *prima facie* examination of the existence of the arbitration agreement
Source reference: p. 4-7The court also referenced the "Competence-Competence" principle, noting that issues such as "accord and satisfaction" or contested facts fall within the exclusive jurisdiction of the Arbitral Tribunal under Section 16
Source reference: para. 114, 119Reasoning
The Court noted that the contract contained an arbitration clause (Clause 18) incorporating the Railway Board’s arbitration policy
Source reference: p. 2Following the mandate in *Krish Spinning*, the Court limited its enquiry to the existence of the arbitration agreement and found that both parties reached a consensus to refer the matter to arbitration
Source reference: p. 8Regarding the Section 9 petition for interim relief, the Court observed that since an Arbitrator was being appointed, the petition should be converted into a Section 17 application to be decided by the Tribunal, thereby upholding the principle of minimal judicial interference
Source reference: p. 9The Court determined that a retired judge should be appointed given the claim valuation exceeded Rs. 9 Crores
Source reference: p. 8Holding
The Court allowed the petition and appointed Hon’ble Mr. Justice M. K. Hanjura (Retd.) as the Sole Arbitrator
The Section 9 petition was disposed of with directions that it be treated as an application under Section 17 before the learned Arbitrator, and the interim order dated 11.12.2025 was extended until the Arbitrator adjudicates the stay application
Source reference: p. 9The parties were directed to share the costs and fees as per the Fourth Schedule of the Act
Source reference: p. 8Original Court PDF
Oriental Foundry Private Limited v. Union of India [ARB.P. 357/2026 & O.M.P.(I) (COMM.) 506/2025]
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in