01Facts
The Petitioner, Oriental Foundry Pvt. Ltd., entered into a contract (No. 2024/RS(l)/954/207/1940) with the Respondent, Union of India, on 01.08.2024
p. 2Disputes arose regarding the contract, leading the Petitioner to serve a notice under Section 21 of the Arbitration and Conciliation Act on 05.01.2026
p. 3The Petitioner approached the High Court seeking the appointment of a Sole Arbitrator under Section 11(6)
pp. 1-2The Petitioner also sought interim protection under Section 9 to stay the invocation of bank guarantees totaling approximately ₹14.4 Crore
pp. 8-9The Respondents expressed no objection to the reference of the dispute to arbitration
p. 302Issues
i.Whether a Sole Arbitrator should be appointed under Section 11(6) of the Act given the arbitration clause and the nature of the dispute
p. 2 · ¶ 1ii.Whether the Section 9 petition for interim relief should be adjudicated by the Court or referred to the Arbitral Tribunal under Section 17
p. 8 · ¶ 1603Law Applied
The Court primarily applied Section 11(6) and Section 11(6-A) of the Arbitration and Conciliation Act, 1996, which confines judicial scrutiny to the prima facie existence of an arbitration agreement
p. 2, 4It relied on the Supreme Court’s decision in *SBI General Insurance Co. Ltd. v. Krish Spinning* (2024), which established that the Referral Court must not conduct a "laborious enquiry" into contested facts like "accord and satisfaction," as these fall within the domain of the Arbitral Tribunal under the principle of competence-competence
pp. 3-7The Court also referenced Section 17 of the Act regarding the power of an Arbitral Tribunal to grant interim measures
p. 8Provisions in the judgment · 8 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 11Section 12Section 8Section 37Section 7Section 16Section 9Section 17
04Reasoning
The Court observed that the parties had a valid arbitration agreement
p. 2Following the mandate in *Krish Spinning*, the Court limited its role to a facilitative one, ensuring the agreed dispute resolution mechanism was activated without delving into the merits of the ₹7 Crore claim
p. 7Since the Respondents consented to arbitration, the Court found it appropriate to appoint an independent arbitrator despite the specific procedures mentioned in Clause 2905(b) (which involved panels of retired Railway Officers), thereby upholding arbitral autonomy
p. 3, 7For the interim relief sought under Section 9, the Court determined that since an Arbitrator was being appointed, the application should be converted into a Section 17 application to be decided by the Tribunal, maintaining the status quo in the interim to protect the Petitioner from coercive steps regarding bank guarantees
p. 805Holding
The Court allowed the petition and appointed Mr. Shashank Garg, Senior Advocate, as the Sole Arbitrator
p. 7 · ¶ 8It directed that the Section 9 petition be treated as an application under Section 17 to be decided by the Arbitrator
p. 8 · ¶ 16The interim order dated 12.12.2025 (staying coercive steps/BG invocation) was ordered to continue until the Arbitrator adjudicates the Section 17 application
p. 8 · ¶ 16The petitions were disposed of with a direction for the parties to share costs and fees equally per the Fourth Schedule
p. 7 · ¶ 10-11Original Court PDF
Oriental Foundry Private Limited v. Union of India & Anr. O.M.P.(I) (COMM.) 507/2025 & ARB.P. 354/2026
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
