01Facts
The petitioner held five electricity connections classified as LT-1 for domestic consumption.
Following an inspection on 18 February 2026, respondent No. 3 alleged that electricity was being used for commercial purposes and issued five communications dated 22 March 2026 imposing amounts ranging from Rs. 1,798 to Rs. 2,832.
pp. 2–4The petitioner challenged those communications under Article 226, contending that the authority had imposed penalties without following Section 126 of the Electricity Act, 2003.
pp. 2–4The respondents submitted that the communications were provisional and that the petitioner had filed objections.
pp. 2–4The Court found that the impugned communications had reached conclusions on amounts payable without following the statutory procedure.
p. 702Issues
i.1. Whether the impugned communications imposing amounts for alleged unauthorised use of electricity complied with the assessment procedure under Section 126 of the Electricity Act, 2003
pp. 6–7ii.2. Whether the petitioner’s electricity supply should remain connected while the authority undertakes assessment in accordance with law
p. 803Law Applied
Section 126(1) of the Electricity Act, 2003 requires the Assessing Officer, upon concluding that unauthorised use of electricity has occurred, to make a provisional assessment.
pp. 4–6Under Section 126(2)–(3), the provisional order must be served on the consumer, who is entitled to submit objections and receive a reasonable opportunity of hearing before the authority makes a final assessment.
pp. 4–6Section 126(5) addresses the period for which assessment may be made, and Section 126(6) prescribes assessment at twice the applicable tariff.
pp. 4–6The statutory sequence is provisional assessment, service, opportunity to object and be heard, and final assessment.
pp. 6–7Provisions in the judgment · 1 · Linked ones open on LawLens
Electricity Act, 2003 Section 126
04Reasoning
The Court treated the impugned communications as having determined amounts payable for the alleged misuse, rather than as orders made through the procedure required by Section 126.
p. 7It held that the authority could not reach such a conclusion without first issuing and serving a provisional assessment, considering the petitioner’s objections after giving a hearing, and then making a final assessment.
p. 7The communications were therefore contrary to the statutory procedure.
p. 7The Court reserved liberty for the authority to recommence the process in accordance with law.
p. 805Holding
The Court allowed the petition and quashed the five communications dated 22 March 2026.
p. 8It reserved liberty to respondent No. 3 to issue a provisional assessment and proceed in accordance with Section 126.
p. 8The petitioner’s electricity supply was not to be disconnected until such an order was passed.
p. 8No order as to costs was made.