Karnataka High CourtAdministrative and Public LawCivil Procedure and Evidence

Section 126 Requires Provisional Assessment and Opportunity to Object Before Final Electricity Assessment.

POONAM K JAJEEv.THE MANAGING DIRECTOR

Section 126 Requires Provisional Assessment and Opportunity to Object Before Final Electricity Assessment.. POONAM K JAJEE vs THE MANAGING DIRECTOR. Karnataka High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the impugned communications imposing amounts for alleged unauthorised use of electricity complied with the assessment procedure under Section 126 of the Electricity Act, 2003

The court held

The Court allowed the petition and quashed the five communications dated 22 March 2026.

It also directed

It reserved liberty to respondent No. 3 to issue a provisional assessment and proceed in accordance with Section 126.

The petitioner’s electricity supply was not to be disconnected until such an order was passed.

No order as to costs was made.

01Facts

The petitioner held five electricity connections classified as LT-1 for domestic consumption.

Following an inspection on 18 February 2026, respondent No. 3 alleged that electricity was being used for commercial purposes and issued five communications dated 22 March 2026 imposing amounts ranging from Rs. 1,798 to Rs. 2,832.

pp. 2–4

The petitioner challenged those communications under Article 226, contending that the authority had imposed penalties without following Section 126 of the Electricity Act, 2003.

pp. 2–4

The respondents submitted that the communications were provisional and that the petitioner had filed objections.

pp. 2–4

The Court found that the impugned communications had reached conclusions on amounts payable without following the statutory procedure.

p. 7

02Issues

i.1. Whether the impugned communications imposing amounts for alleged unauthorised use of electricity complied with the assessment procedure under Section 126 of the Electricity Act, 2003

pp. 6–7

ii.2. Whether the petitioner’s electricity supply should remain connected while the authority undertakes assessment in accordance with law

p. 8

03Law Applied

Section 126(1) of the Electricity Act, 2003 requires the Assessing Officer, upon concluding that unauthorised use of electricity has occurred, to make a provisional assessment.

pp. 4–6

Under Section 126(2)–(3), the provisional order must be served on the consumer, who is entitled to submit objections and receive a reasonable opportunity of hearing before the authority makes a final assessment.

pp. 4–6

Section 126(5) addresses the period for which assessment may be made, and Section 126(6) prescribes assessment at twice the applicable tariff.

pp. 4–6

The statutory sequence is provisional assessment, service, opportunity to object and be heard, and final assessment.

pp. 6–7

Provisions in the judgment · 1 · Linked ones open on LawLens

Electricity Act, 2003 Section 126

04Reasoning

The Court treated the impugned communications as having determined amounts payable for the alleged misuse, rather than as orders made through the procedure required by Section 126.

p. 7

It held that the authority could not reach such a conclusion without first issuing and serving a provisional assessment, considering the petitioner’s objections after giving a hearing, and then making a final assessment.

p. 7

The communications were therefore contrary to the statutory procedure.

p. 7

The Court reserved liberty for the authority to recommence the process in accordance with law.

p. 8

05Holding

The Court allowed the petition and quashed the five communications dated 22 March 2026.

p. 8

It reserved liberty to respondent No. 3 to issue a provisional assessment and proceed in accordance with Section 126.

p. 8

The petitioner’s electricity supply was not to be disconnected until such an order was passed.

p. 8

No order as to costs was made.

p. 8
Karnataka High Court

Original Court PDF

POONAM K JAJEEvsTHE MANAGING DIRECTOR

Karnataka High Court · October 12, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment