Calcutta High Court
Arbitration and MediationCivil Procedure and Evidence

Section 34 courts cannot reappreciate evidence or substitute plausible arbitral findings.

JAY BHARAT CONSTRUCTION vs UNION OF INDIA

Calcutta High CourtJUDGMENT: September 02, 20264 MIN READSOURCE JUDGMENT
Section 34 courts cannot reappreciate evidence or substitute plausible arbitral findings.. JAY BHARAT CONSTRUCTION vs UNION OF INDIA. Calcutta High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The South Eastern Railway awarded the appellant a construction contract for an electric locomotive shed at Bokaro Steel City Station for approximately Rs. 7.32 crore, with a stipulated completion period of 24 months.

Source reference: paras. 12–14

The contract required reciprocal performance: the Railway was to provide layout and GAT drawings, while the appellant was to execute the construction work.

Source reference: para. 14

The appellant repeatedly sought drawings and extensions of time, which the Railway granted without imposing liquidated damages.

Source reference: paras. 15–16

After the Railway directed the appellant to mobilise and resume the work, the appellant requested closure of the contract under Clause 61 of the General Conditions of Contract. The Railway thereafter issued a seven-day notice, followed by a 48-hour notice, and terminated the contract under Clause 62 on 29 May 2007.

Source reference: paras. 17–19

The disputes were referred to arbitration. The appellant raised 13 claims and the Railway raised seven counterclaims. The Arbitral Tribunal allowed, inter alia, the appellant’s claims for the final bill, refund of security deposits and PVC price escalation, and allowed certain counterclaims relating to risk and costs, royalty and unreturned materials.

Source reference: paras. 19–20, 33–40

The Railway challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996, while the appellant initiated execution proceedings.

Source reference: para. 21

The learned Single Judge allowed the Section 34 challenge, held the termination valid, found the award of refund of security deposit patently illegal, treated the award concerning risk and costs as perverse, and dismissed the execution petition. The appellant challenged that decision under Section 37.

Source reference: paras. 22–24, 1
02

Issues

1. Whether the learned Single Judge exceeded the limited scope of jurisdiction under Section 34 by re-evaluating the evidence and substituting the Arbitral Tribunal’s findings on security deposit and risk-and-cost claims.

Source reference: paras. 23–24, 32–33

2. Whether the Arbitral Tribunal’s reasoned and plausible findings, including its assessment of the parties’ reciprocal breaches and the appellant’s entitlement to refund of security deposit, were liable to be set aside for patent illegality or perversity.

Source reference: paras. 35–42

3. Whether the Court could sever or modify portions of the arbitral award while exercising jurisdiction under Sections 34 and 37 of the Act.

Source reference: paras. 26–27
03

Law Applied

The Court applied Sections 34 and 37 of the Arbitration and Conciliation Act, 1996. A Section 34 court does not sit as a court of appeal and cannot reappreciate evidence, correct mere errors of fact or substitute its own view for a plausible view taken by the Arbitral Tribunal.

Source reference: paras. 28–29, 32

Interference is confined to the statutory grounds, including patent illegality, fundamental policy of Indian law and the basic notions of justice, which are to be applied narrowly and in exceptional cases.

Source reference: para. 25

Ssangyong Engineering & Construction Co. Ltd. v. NHAI, (2019) 15 SCC 131, restricts expansion of “public policy” and patent illegality beyond the statutory framework.

Source reference: para. 25

Parsa Kente Collieries Ltd. v. Rajasthan Rajya Vidyut Utpadan Nigam Ltd., (2019) 7 SCC 236, and Delhi Airport Metro Express Pvt. Ltd. v. DMRC, (2022) 1 SCC 131, prohibit appellate reassessment of factual and legal findings under Section 34.

Source reference: paras. 28–29

Project Director, NHAI v. M. Hakeem, (2021) 9 SCC 1, holds that Section 34 does not ordinarily confer power to modify an award, while Gayatri Balasamy v. ISG Novasoft Technologies Ltd., (2025) 7 SCC 1, recognises limited modification, including severance of invalid and valid portions and correction of clerical or manifest errors, where no impermissible merits review is undertaken.

Source reference: paras. 26–27

The Court also relied on Kailash Nath Associates v. DDA, (2015) 4 SCC 136, concerning compensation and forfeiture principles under Section 74 of the Indian Contract Act.

Source reference: para. 31
04

Reasoning

The Arbitral Tribunal had examined each claim and counterclaim and provided reasons for allowing or rejecting them.

Source reference: paras. 33, 40–41

Its finding on the security deposit was based on the Railway’s failure to provide drawings in advance and the conclusion that both parties had contributed to the incomplete project; the Tribunal therefore considered the appellant’s breach insufficient to justify forfeiture.

Source reference: paras. 34–36

This was a plausible contractual and factual assessment, not a perverse or patently illegal conclusion.

Source reference: no citation

Similarly, the Tribunal’s treatment of risk and costs arose from its evaluation of the parties’ reciprocal obligations and the available drawings.

Source reference: no citation

The Single Judge, by preferring a different interpretation of the evidence and documents, effectively conducted an appellate review, which Section 34 does not permit.

Source reference: paras. 24, 32, 41–42

The Section 37 court’s role was consequently limited to examining whether the Single Judge applied the correct Section 34 parameters; since the Tribunal’s findings were reasoned and plausible, interference was unwarranted.

Source reference: para. 32
05

Holding

The High Court held that the learned Single Judge impermissibly re-evaluated the evidence and substituted the Arbitral Tribunal’s plausible findings.

The Tribunal’s award was not shown to be perverse, patently illegal or contrary to the fundamental policy of Indian law.

Source reference: paras. 33, 41–42

Accordingly, the judgment and order dated 10 September 2024 was set aside; AP 780 of 2012, the Section 34 challenge, was dismissed; the execution petition, EC No. 3 of 2024, was restored to its original file and number; and APOT 10 of 2025 along with the connected applications was disposed of without costs.

Source reference: paras. 43–44
06

Acts & Sections Cited

5 provisions across 2 statutes referred to in this judgment. Each provision opens on LawLens.

Arbitration and Conciliation Act, 19964

Indian Contract Act, 18721

Calcutta High Court

Original Court PDF

JAY BHARAT CONSTRUCTIONvsUNION OF INDIA

Calcutta High Court · September 02, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment