Delhi High CourtArbitration and MediationCivil Procedure and Evidence

Section 5 of the Limitation Act applies to Chamber Appeals under the Delhi High Court Original Side Rules.

M/S Ramacivil India Construction Pvt Ltd Through Its Authorized Representative Director Sh R N Guptav.Central Public Works Department Through Its Addl Director General

Section 5 of the Limitation Act applies to Chamber Appeals under the Delhi High Court Original Side Rules.. M/S Ramacivil India Construction Pvt Ltd Through Its Authorized Representative Director Sh R N Gupta vs Central Public Works Department Through Its Addl Director General. Delhi High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the Court has the jurisdiction to condone delay in filing a Chamber Appeal under Chapter II Rule 5 of the Delhi High Court (Original Side) Rules, 2018, or if the Limitation Act is excluded by implication.

The court held

The Court allowed the applications for condonation of delay

It also directed

set aside the Joint Registrar’s orders impleading IIM Jammu

The Court allowed ARB.P. 1787/2025, directing CPWD to appoint a nominee arbitrator in strict accordance with the mandatory qualifications in Clause 25 of the GCC

The three Section 9 petitions were converted into Section 17 applications to be adjudicated by the newly constituted Arbitral Tribunal

01Facts

The Petitioner, an enlisted contractor, was awarded an EPC contract by the Respondent (CPWD) for the construction of the IIM Jammu campus

¶ 6(a)-(c)

Disputes arose regarding project delays, alleged defects, and payments

¶ 6(e)

The Petitioner invoked the arbitration clause (Clause 25 of the GCC) and filed a Section 11 petition for the appointment of an arbitrator, along with three Section 9 petitions for interim protection

¶ 6(j)-(k)

During proceedings, IIM Jammu (the project beneficiary) sought impleadment, which was granted by the Joint Registrar

¶ 6(l)-(m)

The Petitioner challenged this via Chamber Appeals, which were initially allowed but remanded by a Division Bench to adjudicate a one-day delay in filing and the merits of impleadment

¶ 6(o)-(p)

02Issues

i.1. Whether the Court has the jurisdiction to condone delay in filing a Chamber Appeal under Chapter II Rule 5 of the Delhi High Court (Original Side) Rules, 2018, or if the Limitation Act is excluded by implication.

¶ 9, 46

ii.2. Whether IIM Jammu, as the non-signatory "ultimate beneficiary" of the project, is a necessary or proper party to the arbitration proceedings.

¶ 72, 82

03Law Applied

The Court applied Section 5 of the Limitation Act, 1963, noting that the general law of limitation applies to "any appeal" unless expressly excluded by a special law

¶ 33-35

It distinguished Ram Sarup Lugani v. Nirmal Lugani, stating that unless a rule uses prohibitory language like "but not thereafter," Section 5 remains applicable

¶ 62-65

Regarding impleadment, the Court relied on the "Group of Companies" doctrine and the principle of party autonomy as reiterated in Cox and Kings Ltd. v. SAP India Pvt. Ltd. and Hindustan Petroleum Corporation Ltd. v. BCL Secure Premises Pvt. Ltd., which mandate that non-signatories can only be joined if there is clear evidence of consensual intent to be bound by the arbitration agreement

¶ 94

Provisions in the judgment · 12 · Linked ones open on LawLens

Arbitration and Conciliation Act, 1996 Section 2Section 7Section 9Section 11Section 12Section 16Section 17

Code of Civil Procedure, 1908 Section 114Section 151Section 1

Limitation Act, 1963 Section 5

Delhi High Court Act, 1966 Section 10

04Reasoning

The Court rejected the argument that Chapter II Rule 5 of the Original Side Rules is an absolute bar to condonation, finding no "peremptory embargo" or exclusionary phraseology in the rule's text

¶ 64-66

Given the delay was only one day and no prejudice was shown, the Court condoned the delay in the interest of substantial justice

¶ 66-70

On the merits of impleadment, the Court found that while IIM Jammu was the beneficiary, the contract was exclusively between the Petitioner and CPWD

¶ 83-85

It held that "ultimate beneficiary" status is not a valid legal test for joining a non-signatory to arbitration

¶ 94-95

The Court observed that Clause 36 of the NIT maintained a clear distinction between the executing authority (CPWD) and the beneficiary (IIM Jammu), and impleading the latter would violate the principle of party autonomy

¶ 96-99

05Holding

The Court allowed the applications for condonation of delay

¶ 70

set aside the Joint Registrar’s orders impleading IIM Jammu

¶ 103

The Court allowed ARB.P. 1787/2025, directing CPWD to appoint a nominee arbitrator in strict accordance with the mandatory qualifications in Clause 25 of the GCC

¶ 116-118

The three Section 9 petitions were converted into Section 17 applications to be adjudicated by the newly constituted Arbitral Tribunal

¶ 122-126
Delhi High Court

Original Court PDF

M/S Ramacivil India Construction Pvt Ltd Through Its Authorized Representative Director Sh R N GuptavsCentral Public Works Department Through Its Addl Director General

Delhi High Court · May 29, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment