Delhi High CourtArbitration and MediationContract Law

Section 73 damages require proof of actual loss; expense certificates without quantification of loss are insufficient evidence.

Union Of Indiav.M/S Anand And Company

Section 73 damages require proof of actual loss; expense certificates without quantification of loss are insufficient evidence.. Union Of India vs M/S Anand And Company. Delhi High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the Arbitrator could direct the release of withheld amounts for milestones and award interest despite Clause 2 of the contract?

The court held

The petition was partly allowed.

It also directed

(i) The release of amounts withheld for milestones is upheld, but the interest on such amounts is set aside.

(ii) The final bill amount is corrected to Rs. 54,44,112/- due to a clerical error.

(iii) The 3% GST difference award and the prolongation damages are set aside for lack of proof of actual loss.

(iv) The refund of the sample flat penalty is upheld as no loss was proven.

(v) The litigation costs and general interest (9%) remain upheld.

01Facts

The Petitioner (Union of India) awarded an e-tender to the Respondent for the construction of 100 Family Quarters at ITBP Campus, New Delhi.

pp. 1-2

The contract, executed in 2017, stipulated a 12-month completion period.

p. 2

Although the work was completed after a delay of 452 days, the Petitioner granted repeated extensions without attributing the delay to the Respondent.

pp. 4-5, 6

Disputes regarding withheld amounts, GST reimbursements, penalties, and prolongation costs were referred to arbitration, resulting in an award dated 17.02.2023.

pp. 1-2

The Petitioner challenged this award under Section 34 of the Arbitration and Conciliation Act, 1996.

p. 1

02Issues

i.1. Whether the Arbitrator could direct the release of withheld amounts for milestones and award interest despite Clause 2 of the contract?

p. 2, para 3 · p. 6, para 8

ii.2. Whether the award of a 3% difference between GST and VAT was sustainable without proof of actual payment?

pp. 2-3, para 3.2 · p. 10, para 11

iii.3. Whether the refund of a penalty for delay in a sample flat was valid in the absence of proven loss to the Petitioner?

p. 3, para 3.3 · p. 10, para 12

iv.4. Whether damages for prolongation costs could be awarded based solely on a Chartered Accountant's certificate under Section 73 of the Contract Act?

p. 3, para 3.4 · pp. 13-14, para 14

v.5. Whether the Court has the power to set aside only severable parts of an arbitral award?

p. 14, para 17

03Law Applied

The Court applied Section 34 of the Arbitration and Conciliation Act, 1996, regarding the limited scope for setting aside awards.

p. 1

It relied on Section 73 of the Indian Contract Act, 1872, which mandates that a party claiming damages must prove actual loss or damage unless quantification is impossible.

pp. 10-12

The Court followed Kailash Nath Associates v. DDA, which holds that proof of loss is not dispensed with if it can be established.

p. 11, para 13.2

The Court followed Unibros v. All India Radio, which requires credible evidence to substantiate loss of profit.

p. 11, para 13.1

Regarding severability, the Court applied the principle from Gayatri Balasamy v. ISG Novasoft Technologies Ltd., permitting the setting aside of "invalid" portions of an award while preserving the "valid" ones.

pp. 14-15, para 17

Provisions in the judgment · 5 · Linked ones open on LawLens

Arbitration and Conciliation Act, 1996 Section 16Section 34

Indian Contract Act, 1872 Section 73Section 74Section 75

04Reasoning

The Court found that since the Petitioner extended the time without blaming the Respondent, milestones should have been rescheduled under Clause 5.4, justifying the refund of withheld amounts.

p. 6, para 7

However, the award of interest on this refund was set aside as Clause 2 of the contract explicitly prohibited interest on withheld amounts.

p. 7, para 8

Regarding the GST claim, the Court held it was unsustainable because the Respondent failed to prove actual payment of the 3% difference, and the Arbitrator’s speculative "split" of taxes ignored that Service Tax was repealed upon the introduction of GST.

pp. 9-10, para 11

The Court upheld the refund of the sample flat penalty, noting the Petitioner failed to prove any actual loss caused by the delay, consistent with the Kailash Nath doctrine.

p. 10, para 12

Regarding prolongation damages, the Court ruled that a CA certificate merely showing expenses is not proof of actual loss under Section 73; the Arbitrator’s assessment was based on assumptions and lacked a legal foundation.

p. 14, para 14

Finally, the Court determined that the invalid portions of the award were severable and could be set aside without nullifying the entire award.

p. 16, para 18

05Holding

The petition was partly allowed.

p. 17, para 20

(i) The release of amounts withheld for milestones is upheld, but the interest on such amounts is set aside.

pp. 16, para 19(A-B)

(ii) The final bill amount is corrected to Rs. 54,44,112/- due to a clerical error.

p. 16, para 19(C)

(iii) The 3% GST difference award and the prolongation damages are set aside for lack of proof of actual loss.

p. 16, para 19(D, F)

(iv) The refund of the sample flat penalty is upheld as no loss was proven.

p. 16, para 19(E)

(v) The litigation costs and general interest (9%) remain upheld.

p. 16, para 19(G)
Delhi High Court

Original Court PDF

Union Of IndiavsM/S Anand And Company

Delhi High Court · April 04, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment