Facts
The Petitioner (Union of India) awarded an e-tender to the Respondent for the construction of 100 Family Quarters at ITBP Campus, New Delhi.
Source reference: p.1-2The contract, executed in 2017, stipulated a 12-month completion period.
Source reference: p.2Although the work was completed after a delay of 452 days, the Petitioner granted repeated extensions without attributing the delay to the Respondent.
Source reference: p.4-5, 6Disputes regarding withheld amounts, GST reimbursements, penalties, and prolongation costs were referred to arbitration, resulting in an award dated 17.02.2023.
Source reference: p.1-2The Petitioner challenged this award under Section 34 of the Arbitration and Conciliation Act, 1996.
Source reference: p.1Issues
1. Whether the Arbitrator could direct the release of withheld amounts for milestones and award interest despite Clause 2 of the contract?
Source reference: p.2, para 3; p.6, para 82. Whether the award of a 3% difference between GST and VAT was sustainable without proof of actual payment?
Source reference: p.2-3, para 3.2; p.10, para 113. Whether the refund of a penalty for delay in a sample flat was valid in the absence of proven loss to the Petitioner?
Source reference: p.3, para 3.3; p.10, para 124. Whether damages for prolongation costs could be awarded based solely on a Chartered Accountant's certificate under Section 73 of the Contract Act?
Source reference: p.3, para 3.4; p.13-14, para 145. Whether the Court has the power to set aside only severable parts of an arbitral award?
Source reference: p.14, para 17Law Applied
The Court applied Section 34 of the Arbitration and Conciliation Act, 1996, regarding the limited scope for setting aside awards.
Source reference: p.1It relied on Section 73 of the Indian Contract Act, 1872, which mandates that a party claiming damages must prove actual loss or damage unless quantification is impossible.
Source reference: p.10-12The Court followed Kailash Nath Associates v. DDA, which holds that proof of loss is not dispensed with if it can be established.
Source reference: p.11, para 13.2The Court followed Unibros v. All India Radio, which requires credible evidence to substantiate loss of profit.
Source reference: p.11, para 13.1Regarding severability, the Court applied the principle from Gayatri Balasamy v. ISG Novasoft Technologies Ltd., permitting the setting aside of "invalid" portions of an award while preserving the "valid" ones.
Source reference: p.14-15, para 17Reasoning
The Court found that since the Petitioner extended the time without blaming the Respondent, milestones should have been rescheduled under Clause 5.4, justifying the refund of withheld amounts.
Source reference: p.6, para 7However, the award of interest on this refund was set aside as Clause 2 of the contract explicitly prohibited interest on withheld amounts.
Source reference: p.7, para 8Regarding the GST claim, the Court held it was unsustainable because the Respondent failed to prove actual payment of the 3% difference, and the Arbitrator’s speculative "split" of taxes ignored that Service Tax was repealed upon the introduction of GST.
Source reference: p.9-10, para 11The Court upheld the refund of the sample flat penalty, noting the Petitioner failed to prove any actual loss caused by the delay, consistent with the Kailash Nath doctrine.
Source reference: p.10, para 12Regarding prolongation damages, the Court ruled that a CA certificate merely showing expenses is not proof of actual loss under Section 73; the Arbitrator’s assessment was based on assumptions and lacked a legal foundation.
Source reference: p.14, para 14Finally, the Court determined that the invalid portions of the award were severable and could be set aside without nullifying the entire award.
Source reference: p.16, para 18Holding
The petition was partly allowed.
(i) The release of amounts withheld for milestones is upheld, but the interest on such amounts is set aside.
Source reference: p.16, para 19(A-B)(ii) The final bill amount is corrected to Rs. 54,44,112/- due to a clerical error.
Source reference: p.16, para 19(C)(iii) The 3% GST difference award and the prolongation damages are set aside for lack of proof of actual loss.
Source reference: p.16, para 19(D, F)(iv) The refund of the sample flat penalty is upheld as no loss was proven.
Source reference: p.16, para 19(E)(v) The litigation costs and general interest (9%) remain upheld.
Source reference: p.16, para 19(G)Original Court PDF
Union Of IndiavsM/S Anand And Company
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in