Facts
The Petitioner, a lessee of commercial space at Pitampura Metro Station, sub-leased Shop No. PTP G-1 to the Respondent under a registered Sub-Lease Deed dated 25 September 2024, which contained an arbitration clause.
Source reference: p. 1, para. 2; p. 2, para. 11The Petitioner alleged rent and other dues of ₹32,53,502 as of 1 May 2026, together with continuing defaults, and stated that the Respondent remained in possession despite a termination notice.
Source reference: p. 2, paras. 5–8The Petitioner sought interim measures under Section 9 of the Arbitration and Conciliation Act, 1996, including restraint against creating third-party rights in the premises.
Source reference: pp. 2–4, para. 9The Respondent did not appear despite service and was proceeded against ex parte.
Source reference: p. 4, para. 10By order dated 7 August 2026, the Court restrained the Respondent from creating third-party rights in the premises pending further consideration.
Source reference: p. 4, paras. 16–20; p. 5, para. 17Issues
Whether the interim arrangement restraining the Respondent from creating third-party rights in the premises should continue pending consideration by an Arbitral Tribunal.
Source reference: p. 5, paras. 17–20; p. 6, paras. 9, 11–13Whether the Section 9 petition should be disposed of with liberty for the Arbitral Tribunal to consider the interim measures under Section 17 of the Act.
Source reference: p. 6, paras. 8–15Law Applied
The Court proceeded under Sections 9 and 17 of the Arbitration and Conciliation Act, 1996.
Source reference: p. 6, paras. 9–11The order treated the Section 9 petition, upon constitution of the Arbitral Tribunal, as an application under Section 17 for the Tribunal’s consideration; the Tribunal may continue, vacate, or modify the interim arrangement, and is not bound by the Court’s directions.
Source reference: p. 6, paras. 9–11No precedents or further legal tests are cited in the judgment.
Source reference: no citationReasoning
The registered Sub-Lease Deed, evidence of possession, invoices, and payments made by the Respondent established prima facie the sub-lease relationship and its implementation; the alleged defaults remained unrebutted because the Respondent did not appear or dispute the material.
Source reference: pp. 4–5, paras. 11–16The Court had accordingly granted a limited restraint against creating third-party rights.
Source reference: p. 5, para. 17Rather than finally adjudicating the requested interim relief, it preserved that arrangement only until the Arbitral Tribunal could consider the matter, leaving the Tribunal free to determine the appropriate protection independently.
Source reference: p. 5, para. 17; p. 6, paras. 9–13Holding
The Court disposed of the Section 9 petition and directed that appropriate arbitral proceedings be initiated within 45 days.
Upon constitution, the petition is to be treated as an application under Section 17 and placed before the Arbitral Tribunal, which may continue, vacate, or modify the interim arrangement.
Source reference: p. 6, paras. 9–11The restraint granted on 7 August 2026 continues only until the Tribunal considers the matter and passes appropriate orders; it automatically stands vacated if the Petitioner fails to initiate arbitral proceedings within the stipulated period.
Source reference: p. 6, paras. 13–14All rights and contentions were left open, with no opinion expressed on the merits.
Source reference: p. 6, para. 12Acts & Sections Cited
2 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.
Arbitration and Conciliation Act, 19962
Original Court PDF
Singla Gateway Private LimitedvsRebel Mass Exports Private Limited
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
