Facts
The dispute arose from an Agreement for Sale dated 12 April 2025 between the parties concerning machinery and equipment supplied by the petitioner to the respondents.
Source reference: p.3–4Alleging non-payment of agreed dues and apprehending that the machinery might be alienated, encumbered, or otherwise dealt with, the petitioner filed a petition under Section 9 of the Arbitration and Conciliation Act, 1996, seeking interim protection, inspection, security, and repossession-related reliefs.
Source reference: p.1–2By order dated 27 April 2026, the Court restrained the respondents from creating third-party rights, charges, or encumbrances over the machines until the next date of hearing.
Source reference: p.1–3On 23 September 2026, the Court noted that the petitioner had enjoyed the interim protection since April 2026 and directed it to take steps for constitution of the arbitral tribunal.
Source reference: p.4Issues
Whether the interim protection granted under Section 9 should continue indefinitely while the arbitral tribunal had not yet been constituted?
Source reference: p.4Whether the Section 9 petition should be placed before the arbitral tribunal as an application under Section 17 upon constitution of the tribunal?
Source reference: p.4Whether the interim arrangement should continue pending consideration of the matter by the arbitral tribunal, subject to its power to continue, modify, vary, or vacate it?
Source reference: p.4–5Law Applied
The Court applied Sections 9 and 17 of the Arbitration and Conciliation Act, 1996. Section 9 empowers the Court to grant interim measures before or during arbitral proceedings, while Section 17 empowers the arbitral tribunal to grant interim measures once constituted.
Source reference: no citationThe Court also gave effect to the parties’ arbitration agreement under Clause 13.5 of the Agreement for Sale, which required unresolved disputes to be referred to a sole arbitrator appointed under the 1996 Act and specified New Delhi as the place of arbitration.
Source reference: p.3–4The governing principle applied was that court-granted interim protection in aid of arbitration cannot be allowed to continue indefinitely without the arbitral process being commenced; upon constitution of the tribunal, the interim matter should ordinarily be considered under Section 17.
Source reference: p.4Reasoning
The Court found that the arbitration agreement was operative and that the petitioner had already obtained interim protection restraining alienation or encumbrance of the machinery.
Source reference: p.3–4However, because the petitioner had continued to enjoy that protection since April 2026, the Court held that it could not permit the relief to operate endlessly without constitution of the arbitral tribunal.
Source reference: p.4Accordingly, it directed the petitioner to take appropriate steps for constitution of the tribunal within three weeks.
Source reference: p.4To preserve the subject matter of the dispute during this transition, the existing interim arrangement was continued until the learned Sole Arbitrator considered the matter.
Source reference: p.4The tribunal was expressly empowered to assess the matter independently and to continue, modify, vary, or vacate the interim protection.
Source reference: p.4Holding
The Court directed the petitioner to take steps for constitution of the arbitral tribunal within three weeks from 23 September 2026.
Upon constitution, the Section 9 petition was to be treated as an application under Section 17 and placed before the Sole Arbitrator for consideration in accordance with law.
Source reference: p.4The interim restraint granted on 27 April 2026 was continued until the tribunal passed appropriate orders, subject to the tribunal’s power to modify, vary, or vacate it.
Source reference: p.4If the petitioner failed to commence arbitral proceedings within three weeks, the interim protection would automatically stand vacated.
Source reference: p.4–5All rights and contentions were kept open, and the petition and pending applications were disposed of accordingly.
Source reference: p.5Acts & Sections Cited
2 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.
Arbitration and Conciliation Act, 19962
Original Court PDF
Liugong India Pvt LtdvsCrosslite Infra Pvt Ltd And Ors
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
