01Facts
The Petitioner entered into an Engineering, Procurement, and Construction (EPC) Contract with the Respondent on 27th October 2022 for the 6-laning of a section of NH-44 in Telangana
pp. 1-2Delays occurred in the project, which the Petitioner attributed to the Respondent’s failure to provide Right of Way (ROW), land encumbrances, and delayed forest clearances
p. 2Following disputes and settlement attempts, the Respondent issued a Notice of Intention to Terminate on 10th March 2026
p. 1The Petitioner filed the present petition under Section 9 of the Arbitration and Conciliation Act, 1996, seeking a stay on the termination notice and the invocation of two Bank Guarantees (totaling approx. Rs. 18.6 crore) and a Surety Bond (approx. Rs. 29.3 crore)
pp. 1-2During proceedings, both parties nominated their respective arbitrators, and a joint measurement of work was initiated
pp. 3-402Issues
i.1. Whether interim protection against the invocation of Bank Guarantees and termination of contract should be granted under Section 9 of the Arbitration Act when the arbitral process has already been set in motion
pp. 6 / para. 18-19ii.2. Whether a Section 9 petition can be converted into an application under Section 17 to be adjudicated by the Arbitral Tribunal once the tribunal is being constituted
pp. 6-7 / para. 19(vi)03Law Applied
Section 9 of the Arbitration and Conciliation Act, 1996, which empowers the court to grant interim measures before or during arbitral proceedings
p. 1Section 17 of the Act, which allows the Arbitral Tribunal to grant interim measures, and Section 12 regarding the mandatory disclosure by arbitrators
pp. 6-7Contractual arbitration clause (Clauses 26.2 and 26.3), which mandates arbitration under the rules of the Society for Affordable Resolution of Disputes (SAROD)
pp. 4-6Provisions in the judgment · 3 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 9Section 12Section 17
04Reasoning
The Court observed that a valid arbitration agreement exists and that both parties have already taken steps to nominate their nominee arbitrators, signaling the commencement of the arbitral process
p. 4, 6Given that the tribunal's formation was imminent, the Court determined that the merits of the interim protection should be evaluated by the Arbitral Tribunal rather than the Court
pp. 6-7To balance the equities, the Court noted that the Bank Guarantees and Surety Bonds were still valid for several weeks
p. 4Consequently, the Court found it appropriate to provide a limited "pro-tem" protection to the Petitioner to prevent the immediate encashment of securities, thereby preserving the subject matter until the Tribunal could hear the matter under Section 17
p. 7The Court also recorded the Petitioner's undertaking not to remove plant and machinery from the site to ensure the status quo during joint measurement
p. 3, 705Holding
The Court disposed of the petition by referring the parties to arbitration and converting the Section 9 petition into a Section 17 application for the Arbitral Tribunal's consideration
¶ 19(vi)The Court directed: (i) the nominee arbitrators to appoint a presiding arbitrator; (ii) the arbitration to proceed under SAROD rules
¶ 19(i), (iii)(iii) the Respondent not to encash the Bank Guarantees or Surety Bond for a period of six weeks
¶ 19(vii)(iv) the Petitioner to keep the Bank Guarantees alive and refrain from removing machinery from the site
¶ 19(viii)-(ix)The Court clarified it expressed no opinion on the merits of the underlying dispute
¶ 20Original Court PDF
M S Lakshmi Infrastructure And Developers India Private LimitedvsNational Highways Authority Of India
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
