Facts
The Petitioner entered into an Engineering, Procurement, and Construction (EPC) Contract with the Respondent on 27th October 2022 for the 6-laning of a section of NH-44 in Telangana
Source reference: p.1-2Delays occurred in the project, which the Petitioner attributed to the Respondent’s failure to provide Right of Way (ROW), land encumbrances, and delayed forest clearances
Source reference: p.2Following disputes and settlement attempts, the Respondent issued a Notice of Intention to Terminate on 10th March 2026
Source reference: p.1The Petitioner filed the present petition under Section 9 of the Arbitration and Conciliation Act, 1996, seeking a stay on the termination notice and the invocation of two Bank Guarantees (totaling approx. Rs. 18.6 crore) and a Surety Bond (approx. Rs. 29.3 crore)
Source reference: p.1-2During proceedings, both parties nominated their respective arbitrators, and a joint measurement of work was initiated
Source reference: p.3-4Issues
1. Whether interim protection against the invocation of Bank Guarantees and termination of contract should be granted under Section 9 of the Arbitration Act when the arbitral process has already been set in motion
Source reference: p.6 / para. 18-192. Whether a Section 9 petition can be converted into an application under Section 17 to be adjudicated by the Arbitral Tribunal once the tribunal is being constituted
Source reference: p.6-7 / para. 19(vi)Law Applied
Section 9 of the Arbitration and Conciliation Act, 1996, which empowers the court to grant interim measures before or during arbitral proceedings
Source reference: p.1Section 17 of the Act, which allows the Arbitral Tribunal to grant interim measures, and Section 12 regarding the mandatory disclosure by arbitrators
Source reference: p.6-7Contractual arbitration clause (Clauses 26.2 and 26.3), which mandates arbitration under the rules of the Society for Affordable Resolution of Disputes (SAROD)
Source reference: p.4-6Reasoning
The Court observed that a valid arbitration agreement exists and that both parties have already taken steps to nominate their nominee arbitrators, signaling the commencement of the arbitral process
Source reference: p.4, 6Given that the tribunal's formation was imminent, the Court determined that the merits of the interim protection should be evaluated by the Arbitral Tribunal rather than the Court
Source reference: p.6-7To balance the equities, the Court noted that the Bank Guarantees and Surety Bonds were still valid for several weeks
Source reference: p.4Consequently, the Court found it appropriate to provide a limited "pro-tem" protection to the Petitioner to prevent the immediate encashment of securities, thereby preserving the subject matter until the Tribunal could hear the matter under Section 17
Source reference: p.7The Court also recorded the Petitioner's undertaking not to remove plant and machinery from the site to ensure the status quo during joint measurement
Source reference: p.3, 7Holding
The Court disposed of the petition by referring the parties to arbitration and converting the Section 9 petition into a Section 17 application for the Arbitral Tribunal's consideration
The Court directed: (i) the nominee arbitrators to appoint a presiding arbitrator; (ii) the arbitration to proceed under SAROD rules
Source reference: para. 19(i), (iii)(iii) the Respondent not to encash the Bank Guarantees or Surety Bond for a period of six weeks
Source reference: para. 19(vii)(iv) the Petitioner to keep the Bank Guarantees alive and refrain from removing machinery from the site
Source reference: para. 19(viii)-(ix)The Court clarified it expressed no opinion on the merits of the underlying dispute
Source reference: para. 20Original Court PDF
M S Lakshmi Infrastructure And Developers India Private LimitedvsNational Highways Authority Of India
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in