Delhi High CourtArbitration and MediationConstruction Law

Section 9 petition converted to Section 17 application with interim protection against bank guarantee invocation.

M S Lakshmi Infrastructure And Developers India Private Limitedv.National Highways Authority Of India

Section 9 petition converted to Section 17 application with interim protection against bank guarantee invocation.. M S Lakshmi Infrastructure And Developers India Private Limited vs National Highways Authority Of India. Delhi High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether interim protection against the invocation of Bank Guarantees and termination of contract should be granted under Section 9 of the Arbitration Act when the arbitral process has already been set in motion

The court held

The Court disposed of the petition by referring the parties to arbitration and converting the Section 9 petition into a Section 17 application for the Arbitral Tribunal's consideration

It also directed

The Court directed: (i) the nominee arbitrators to appoint a presiding arbitrator; (ii) the arbitration to proceed under SAROD rules

(iii) the Respondent not to encash the Bank Guarantees or Surety Bond for a period of six weeks

(iv) the Petitioner to keep the Bank Guarantees alive and refrain from removing machinery from the site

The Court clarified it expressed no opinion on the merits of the underlying dispute

01Facts

The Petitioner entered into an Engineering, Procurement, and Construction (EPC) Contract with the Respondent on 27th October 2022 for the 6-laning of a section of NH-44 in Telangana

pp. 1-2

Delays occurred in the project, which the Petitioner attributed to the Respondent’s failure to provide Right of Way (ROW), land encumbrances, and delayed forest clearances

p. 2

Following disputes and settlement attempts, the Respondent issued a Notice of Intention to Terminate on 10th March 2026

p. 1

The Petitioner filed the present petition under Section 9 of the Arbitration and Conciliation Act, 1996, seeking a stay on the termination notice and the invocation of two Bank Guarantees (totaling approx. Rs. 18.6 crore) and a Surety Bond (approx. Rs. 29.3 crore)

pp. 1-2

During proceedings, both parties nominated their respective arbitrators, and a joint measurement of work was initiated

pp. 3-4

02Issues

i.1. Whether interim protection against the invocation of Bank Guarantees and termination of contract should be granted under Section 9 of the Arbitration Act when the arbitral process has already been set in motion

pp. 6 / para. 18-19

ii.2. Whether a Section 9 petition can be converted into an application under Section 17 to be adjudicated by the Arbitral Tribunal once the tribunal is being constituted

pp. 6-7 / para. 19(vi)

03Law Applied

Section 9 of the Arbitration and Conciliation Act, 1996, which empowers the court to grant interim measures before or during arbitral proceedings

p. 1

Section 17 of the Act, which allows the Arbitral Tribunal to grant interim measures, and Section 12 regarding the mandatory disclosure by arbitrators

pp. 6-7

Contractual arbitration clause (Clauses 26.2 and 26.3), which mandates arbitration under the rules of the Society for Affordable Resolution of Disputes (SAROD)

pp. 4-6

Provisions in the judgment · 3 · Linked ones open on LawLens

Arbitration and Conciliation Act, 1996 Section 9Section 12Section 17

04Reasoning

The Court observed that a valid arbitration agreement exists and that both parties have already taken steps to nominate their nominee arbitrators, signaling the commencement of the arbitral process

p. 4, 6

Given that the tribunal's formation was imminent, the Court determined that the merits of the interim protection should be evaluated by the Arbitral Tribunal rather than the Court

pp. 6-7

To balance the equities, the Court noted that the Bank Guarantees and Surety Bonds were still valid for several weeks

p. 4

Consequently, the Court found it appropriate to provide a limited "pro-tem" protection to the Petitioner to prevent the immediate encashment of securities, thereby preserving the subject matter until the Tribunal could hear the matter under Section 17

p. 7

The Court also recorded the Petitioner's undertaking not to remove plant and machinery from the site to ensure the status quo during joint measurement

p. 3, 7

05Holding

The Court disposed of the petition by referring the parties to arbitration and converting the Section 9 petition into a Section 17 application for the Arbitral Tribunal's consideration

¶ 19(vi)

The Court directed: (i) the nominee arbitrators to appoint a presiding arbitrator; (ii) the arbitration to proceed under SAROD rules

¶ 19(i), (iii)

(iii) the Respondent not to encash the Bank Guarantees or Surety Bond for a period of six weeks

¶ 19(vii)

(iv) the Petitioner to keep the Bank Guarantees alive and refrain from removing machinery from the site

¶ 19(viii)-(ix)

The Court clarified it expressed no opinion on the merits of the underlying dispute

¶ 20
Delhi High Court

Original Court PDF

M S Lakshmi Infrastructure And Developers India Private LimitedvsNational Highways Authority Of India

Delhi High Court · April 20, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment