Delhi High Court

Specific performance of commercial contracts is the general rule post-2018 Amendment to the Specific Relief Act.

Conscient Infrastructure Pvt Ltd vs Mahesh Kapoor And Another

Delhi High CourtJUDGMENT: May 29, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Petitioner (a real estate developer) and Respondents (landowners) entered into a "Binding Heads of Terms" (Binding HoT) on 17.05.2023 for the development of 6.76 acres of land in Mehrauli, Delhi

Source reference: para. 2, 8

The agreement contemplated a 42.3/57.7 revenue share and the future execution of a Definitive Collaboration Agreement

Source reference: para. 10-11

Over 30 months, three addenda were executed extending the validity of the HoT, and the Petitioner paid approximately ₹8 Crores while pursuing statutory approvals

Source reference: para. 22-23, 32

On 10.03.2026, the Respondents claimed the agreement had lapsed by efflux of time and subsequently refunded ₹2.8 Crores

Source reference: para. 29-30

Apprehending the creation of third-party rights, the Petitioner sought interim protection under Section 9 of the Arbitration and Conciliation Act, 1996

Source reference: para. 1, 33
02

Issues

1. Whether the "Binding HoT" constitutes a concluded and specifically enforceable contract despite contemplating a future definitive agreement

Source reference: para. 35, 108

2. Whether time was of the essence of the contract, thereby terminating the agreement upon expiry of the stipulated timelines

Source reference: para. 92, 98

3. Whether the court should grant interim protection to preserve the subject matter of the dispute pending arbitration

Source reference: para. 34, 131
03

Law Applied

The court primarily applied Section 9 of the Arbitration and Conciliation Act, 1996, which grants courts broad discretionary power to provide interim measures that are "just and convenient" to promote the efficacy of arbitration

Source reference: para. 1, 134

It relied on the post-2018 amendment framework of the Specific Relief Act (SRA), specifically Section 10, which makes specific performance a general rule rather than a discretionary exception

Source reference: para. 79, 122

The court cited Trimex International FZE Ltd. v. Vedanta Aluminium Ltd. regarding the binding nature of "Heads of Terms" when essential terms are settled

Source reference: para. 111

Global Music Junction Pvt. Ltd. v. Shatrughan Kumar regarding the legislative shift toward stronger enforcement of contracts

Source reference: para. 80, 122
04

Reasoning

The court reasoned that since the HoT identified the land, revenue share, and financial obligations, it was not a mere "agreement to agree" but a binding commercial arrangement

Source reference: para. 109-110

The court found that the continuous execution of addenda and substantial payments by the Petitioner demonstrated that the parties did not initially treat time as being of the essence

Source reference: para. 138-139

Applying the principles from Essar House Private Limited, the court held that Section 9 jurisdiction is not strictly bound by the rigours of the CPC (Order XXXVIII Rule 5 or Order XXXIX) but is aimed at preventing the frustration of the arbitral process

Source reference: para. 133-134

The court noted that the 2018 SRA amendment mandates enforcement of contracts unless specific statutory bars are proven, an exercise best left to the Arbitral Tribunal rather than decided summarily at the Section 9 stage

Source reference: para. 127-128
05

Holding

The court held that the Petitioner established a strong prima facie case and that the balance of convenience favoured preservation of the status quo to prevent the creation of irreversible third-party interests

The Petition was allowed, and the Respondents were restrained from creating any third-party rights, alienating, or encumbering the Collaboration Land until the Arbitral Tribunal considers the matter

Source reference: para. 151

The court clarified that these observations are prima facie and do not prejudice the final adjudication by the learned Arbitral Tribunal

Source reference: para. 152
Delhi High Court

Original Court PDF

Conscient Infrastructure Pvt LtdvsMahesh Kapoor And Another

Delhi High Court · May 29, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment