Facts
The petitioner, a C-Class contractor registered with the Chhattisgarh Housing Board, was awarded a tender for construction of a Tehsil office building at Daura Kochli, District Balrampur-Ramanujganj, at an estimated cost of ₹64,70,826.
Source reference: no citationThe petitioner claimed to have completed the work within the stipulated period and submitted the bill. Although ₹32,29,000 was paid, the alleged balance of ₹32,41,826 remained unpaid.
Source reference: no citationThe petitioner asserted that repeated requests for payment were unsuccessful and that a representation dated 20.02.2026 submitted to the Executive Engineer was not decided.
Source reference: para. 3The Housing Board respondents submitted that payment could not be released because the work was State-financed and the required funds had not been disbursed by the Collector.
Source reference: para. 4The State respondents contended that, since the tender had been floated by the Housing Board authorities, the liability to pay rested upon them.
Source reference: para. 5Issues
Whether the petitioner was entitled to a writ directing the respondents to release the alleged balance contract amount of ₹32,41,826 with interest at 18% per annum.
Source reference: paras. 2–3Whether the respondents should be directed to consider and decide the petitioner’s representation seeking payment of the outstanding contract amount.
Source reference: paras. 2, 9Law Applied
The Court applied the constitutional principle that an instrumentality of the State must act fairly, reasonably, and consistently with public interest even in contractual matters.
Source reference: no citationRelying on ABL International Ltd. v. Export Credit Guarantee Corporation of India Ltd., (2004) 3 SCC 553, the Court reiterated that when a State instrumentality acts unfairly, unjustly, or unreasonably in the discharge of its contractual, constitutional, or statutory obligations, such conduct may violate Article 14 of the Constitution.
Source reference: para. 8Reasoning
The Court noted that the Housing Board respondents did not dispute that they had floated the tender or that the petitioner had completed the work within the stipulated period.
Source reference: para. 7Their explanation was that payment had not been made because the State agency had not released the requisite funds.
Source reference: no citationThe Court did not finally adjudicate the petitioner’s entitlement to the claimed balance or interest.
Source reference: no citationInstead, in light of the State respondents’ and Housing Board respondents’ competing positions regarding responsibility for payment, and applying the requirement of fairness under Article 14 as explained in ABL International, it considered it appropriate to require all respondents to examine the petitioner’s claim through a fresh representation.
Source reference: para. 8Holding
The petition was disposed of.
The petitioner was permitted to submit a fresh representation before all the respondents.
Source reference: para. 9Upon receipt, the authorities were directed to consider and decide it within three months, keeping in view the principles stated by the Supreme Court in ABL International Ltd.
Source reference: para. 9No direct writ for immediate release of the claimed amount or award of 18% interest was granted.
Source reference: no citationOriginal Court PDF
M/S AWADHESH AND GENERAL HARDWAREvsSTATE OF CHHATTISGARH
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
