Facts
The Petitioner, a registered ‘A’ Class contractor, was allotted road restoration contracts in September 2014 following damage caused by heavy rains and flash floods
Source reference: para. 1The Petitioner completed the works within two months
Source reference: para. 2Despite communications from the Executive Engineer in February 2020 admitting a pending liability of ₹25.20 lakhs and recommendations for fund release, the respondents failed to clear the dues
Source reference: para. 2–3The Public Works Department (PWD) contended that the funds were never placed at their disposal by the District Disaster Authority
Source reference: para. 8The Petitioner filed this writ petition seeking payment of the admitted liability with interest, while the respondents raised the preliminary objection of delay and laches, as the work was completed in 2015
Source reference: para. 4, 8Issues
1. Whether the petition is barred by the doctrine of delay and laches given that the claim pertains to work completed in 2015
Source reference: para. 4, 102. Whether the Petitioner is entitled to the release of the admitted liability of ₹25.20 lakhs along with interest for the delay in payment
Source reference: para. 11Law Applied
The Court applied the principle of "recurring cause of action" to negate the plea of delay and laches in cases where the state admits to a pending liability
Source reference: para. 10It further relied on the guidelines of the State Disaster Response Fund (SDRF) and the administrative responsibility of the District Disaster Authority to release funds for executed works
Source reference: para. 5, 12The court exercised its writ jurisdiction to ensure the settlement of admitted claims, noting that official "wrangles" between departments cannot be a ground to withhold payments to a contractor
Source reference: para. 7, 10Reasoning
The Court rejected the respondents' argument regarding delay and laches, observing that the PWD had continuously acknowledged the debt in internal communications, specifically as recently as February 2020, thereby creating a recurring cause of action
Source reference: para. 10The Court noted that the Petitioner had been forced to run "from pillar to post" for over a decade due to administrative failures between the Disaster Management Authority and the PWD
Source reference: para. 7, 10Since the Executive Engineer had explicitly admitted the liability of ₹25.20 lakhs in official correspondence, the claim was deemed "admitted" and not a matter of factual dispute
Source reference: para. 9, 11The Court emphasized that withholding payment for work completed in 2015 for over ten years was a serious matter that caused undue suffering to the Petitioner
Source reference: para. 10Holding
The Court allowed the petition, holding that the Petitioner is entitled to the admitted claim
The District Development Commissioner (Respondent No. 6) was directed to release ₹25.20 lakhs from the SDRF to the Executive Engineer, PWD (R&B), within four weeks
Source reference: para. 12(I)The Executive Engineer was directed to pay the Petitioner within four weeks of receiving said funds
Source reference: para. 12(II)Furthermore, the Court ordered that if the payment is not made within the cumulative eight-week period, the Petitioner shall be entitled to simple interest at 10% per annum from the date of completion of the work until its realization
Source reference: para. 12(III)Original Court PDF
KIRPAL SINGHvsGOVT OF JAMMU AND KASHMIR DEPTT OF DISASTER MANGT RELIEF AND REHABILITATION AND DEPTT AND OTHERS
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in