Patna High Court

Statutory Appeal Remedy Under PDR Act Must Be Exhausted Despite Jurisdictional Challenges to Public Demand

Sri Ram Rice Mill vs The State of Bihar

Patna High CourtJUDGMENT: June 30, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioners, a partnership firm and its partners, moved the High Court to quash a notice issued under Section 7 of the Bihar and Orissa Public Demand Recovery (PDR) Act, 1914, dated May 6, 2013, in Certificate Case No. 17/2013-14.

Source reference: p. 1-2

They challenged the initiation of recovery proceedings on the grounds that no valid agreement existed under Clause 15 of Schedule-1 read with Section 3(6) of the Act, thereby arguing the dues did not constitute a "public demand".

Source reference: p. 2

They further alleged that the Certificate Officer failed to record satisfaction as required under Sections 5 and 6 of the Act and contested a warrant of arrest issued against them.

Source reference: p. 2

During the hearing, both parties agreed that the legal issues were squarely covered by a recent Supreme Court precedent.

Source reference: p. 2
02

Issues

1. Whether the initiation of the certificate proceeding was illegal due to the absence of a jurisdictional agreement to qualify the dues as a "public demand" under the PDR Act.

Source reference: p. 2

2. Whether the petitioners should be relegated to the statutory remedy of appeal despite the challenge to the jurisdiction of the Certificate Officer.

Source reference: p. 3-4
03

Law Applied

The court primarily relied on the precedent established by the Hon’ble Supreme Court of India in Pawapuri Rice Mills v. Bihar State Food and Civil Supplies Corporation Ltd. & Ors. (2024 SCC OnLine SC 3777), which held that while Rice Millers may raise jurisdictional facts in writ petitions, they should generally avail themselves of the statutory remedies provided under the PDR Act.

Source reference: p. 2-3

Section 60 of the Bihar & Orissa Public Demand Recovery Act, 1914, which provides for a statutory appeal against orders passed by a Certificate Officer.

Source reference: p. 3
04

Reasoning

The High Court observed that the controversy regarding the recovery of dues from Rice Millers under the PDR Act had been recently resolved by the Supreme Court in the Pawapuri Rice Mills case.

Source reference: p. 2

The Supreme Court had clarified that even if procedural deviations or jurisdictional facts are alleged, the appropriate course is for the aggrieved parties to invoke the statutory remedy of appeal rather than seeking extraordinary relief under Article 226.

Source reference: p. 3

Following this logic, the High Court determined that the petitioners have an efficacious statutory remedy under Section 60 of the PDR Act.

Source reference: p. 3

To ensure justice, the Court applied the Supreme Court's direction to condone any delays in filing such appeals, given the time spent pursuing the writ remedy.

Source reference: p. 4
05

Holding

The Court disposed of the writ petition without interfering with the certificate proceedings at this stage.

It directed the petitioners to file a statutory appeal under Section 60 of the PDR Act within one month from the receipt of the order.

Source reference: p. 4

The Court ordered the appellate authority to condone the delay and dispose of the appeal on its merits within three months of filing.

Source reference: p. 4

All pending interlocutory applications were disposed of accordingly.

Source reference: p. 4
Patna High Court

Original Court PDF

Sri Ram Rice MillvsThe State of Bihar

Patna High Court · June 30, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment