Facts
The petitioners, a partnership firm and its partners, moved the High Court to quash a notice issued under Section 7 of the Bihar and Orissa Public Demand Recovery (PDR) Act, 1914, dated May 6, 2013, in Certificate Case No. 17/2013-14.
Source reference: p. 1-2They challenged the initiation of recovery proceedings on the grounds that no valid agreement existed under Clause 15 of Schedule-1 read with Section 3(6) of the Act, thereby arguing the dues did not constitute a "public demand".
Source reference: p. 2They further alleged that the Certificate Officer failed to record satisfaction as required under Sections 5 and 6 of the Act and contested a warrant of arrest issued against them.
Source reference: p. 2During the hearing, both parties agreed that the legal issues were squarely covered by a recent Supreme Court precedent.
Source reference: p. 2Issues
1. Whether the initiation of the certificate proceeding was illegal due to the absence of a jurisdictional agreement to qualify the dues as a "public demand" under the PDR Act.
Source reference: p. 22. Whether the petitioners should be relegated to the statutory remedy of appeal despite the challenge to the jurisdiction of the Certificate Officer.
Source reference: p. 3-4Law Applied
The court primarily relied on the precedent established by the Hon’ble Supreme Court of India in Pawapuri Rice Mills v. Bihar State Food and Civil Supplies Corporation Ltd. & Ors. (2024 SCC OnLine SC 3777), which held that while Rice Millers may raise jurisdictional facts in writ petitions, they should generally avail themselves of the statutory remedies provided under the PDR Act.
Source reference: p. 2-3Section 60 of the Bihar & Orissa Public Demand Recovery Act, 1914, which provides for a statutory appeal against orders passed by a Certificate Officer.
Source reference: p. 3Reasoning
The High Court observed that the controversy regarding the recovery of dues from Rice Millers under the PDR Act had been recently resolved by the Supreme Court in the Pawapuri Rice Mills case.
Source reference: p. 2The Supreme Court had clarified that even if procedural deviations or jurisdictional facts are alleged, the appropriate course is for the aggrieved parties to invoke the statutory remedy of appeal rather than seeking extraordinary relief under Article 226.
Source reference: p. 3Following this logic, the High Court determined that the petitioners have an efficacious statutory remedy under Section 60 of the PDR Act.
Source reference: p. 3To ensure justice, the Court applied the Supreme Court's direction to condone any delays in filing such appeals, given the time spent pursuing the writ remedy.
Source reference: p. 4Holding
The Court disposed of the writ petition without interfering with the certificate proceedings at this stage.
It directed the petitioners to file a statutory appeal under Section 60 of the PDR Act within one month from the receipt of the order.
Source reference: p. 4The Court ordered the appellate authority to condone the delay and dispose of the appeal on its merits within three months of filing.
Source reference: p. 4All pending interlocutory applications were disposed of accordingly.
Source reference: p. 4Original Court PDF
Sri Ram Rice MillvsThe State of Bihar
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in