Facts
The Appellant (Promoter) and Respondents (Allottees) entered into an agreement on November 18, 2014, for a flat in the "Wintergreen" project. Clause 17 of the agreement stipulated possession by June 30, 2017.
Source reference: para. 3Despite paying over ₹2.05 Crores, the allottees did not receive possession by the agreed date.
Source reference: para. 4The MahaRERA Authority (1st Authority) initially directed possession by December 31, 2019, but deferred the issue of interest, giving allottees liberty to claim it later based on a request for parity with a connected matter.
Source reference: para. 6The Allottees appealed to the Maharashtra Real Estate Appellate Tribunal, which quashed the lower order and directed the Promoter to pay interest for the delayed period from July 1, 2017, until possession.
Source reference: para. 7-8The Promoter challenged this before the High Court, arguing that the allottees accepted delayed performance under Section 55 of the Contract Act and that the appeal was barred due to the "concession" made before the 1st Authority.
Source reference: para. 9-13Issues
1. Whether in view of Section 55 of the Indian Contract Act, 1872, the acceptance of delayed performance disentitles the promisee from claiming compensation?
Source reference: para. 2/222. Whether the provisions of Section 18 of the RERA Act, 2016 override Section 55 of the Indian Contract Act?
Source reference: para. 2/223. Whether force majeure events (specifically Covid-19) listed in the contract could have been ignored?
Source reference: para. 2/224. Whether the Appeal was maintainable in view of the "concession" given by the Respondents regarding the timing of interest claims?
Source reference: para. 2Law Applied
Section 18 of the Real Estate (Regulation and Development) Act, 2016 (RERA), which provides an "unqualified absolute right" to interest for delayed possession.
Source reference: para. 26, 35Principle from Newtech Promoters and Developers Pvt. Ltd. v. State of U.P., establishing that RERA is retroactive and Section 18 is not dependent on contingencies.
Source reference: para. 34, 45Section 55 of the Indian Contract Act, 1872 regarding the effect of accepting delayed performance.
Source reference: para. 27Section 89 of RERA, which gives the Act overriding effect over inconsistent laws.
Source reference: para. 51Principle from M/s. Pragatej Builders and Developers Pvt. Ltd. v. Abhishek Anju Sukhadia, holding that lockdowns do not excuse delays occurring prior to the pandemic.
Source reference: para. 53Reasoning
The Court reasoned that Section 18 of RERA confers a statutory right that is "unqualified" and "absolute," meaning it is not subject to the conditional notice requirement found in Section 55 of the Contract Act.
Source reference: para. 35-37Even if allottees accepted a revised schedule, this conduct does not constitute an "addendum" to the contract that can supersede the written statutory date.
Source reference: para. 43The Court found that Section 89 of RERA ensures that the specific protections of Section 18 prevail over the general provisions of the Contract Act.
Source reference: para. 51On the "concession" issue, the Court determined that the allottees' request for a similar order to a separate case was a "plea of parity," not an express waiver or abandonment of the right to interest.
Source reference: para. 57-58Since the delay occurred starting in June 2017, the 2020 Covid-19 pandemic could not be used as a force majeure defense for that prior default.
Source reference: para. 52-53Holding
The Court answered the issues in the negative for the Appellant, holding that Section 18 of RERA provides an absolute right to interest regardless of Section 55 of the Contract Act.
The Court further held that the appeal was maintainable as there was no express waiver of legal rights, noting that an advocate's concession on a question of law does not estop a party.
Source reference: para. 61(d)The Appellate Tribunal was correct in awarding interest from July 1, 2017, and the Second Appeal was dismissed with costs.
Source reference: para. 42, 62Original Court PDF
Cci Projects Private Limited Mumbai- 400066vsSriram Krishnan
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in