Delhi High Court

Stay of Cure Period Notice maintainable where termination appears premature and malicious despite contract being terminable.

Igatpuri Highway Private Limited v. National Highways Authority of India [O.M.P. (I) (COMM.) 84/2026]

Delhi High Court2 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Petitioner, a concessionaire under an Agreement dated 14.10.2005 for a highway project, sought interim relief under Section 9 of the Arbitration and Conciliation Act, 1996, to stay a Cure Period Notice (CPN) dated 11.02.2026 issued by the Respondent (NHAI).

Source reference: para. 1

The Petitioner alleged the CPN was a "counterblast" to a prior arbitral award they won against NHAI and noted that the contract is set to expire on 05.05.2026.

Source reference: para. 2-5

NHAI contended the contract is terminable and that the Petitioner failed to perform Periodical Renewals (PR) on certain road stretches, necessitating third-party intervention for public safety.

Source reference: para. 8-9
02

Issues

Whether the Petitioner is entitled to interim protection under Section 9 of the Act to stay the operation of the Cure Period Notice pending arbitration.

Source reference: para. 13-15

Whether the Court should appoint an Arbitral Tribunal following the parties' waiver of formal notices under Sections 21 and 11 of the Act.

Source reference: para. 16-17
03

Law Applied

The court primarily applied Section 9 of the Arbitration and Conciliation Act, 1996, which grants the court power to issue interim measures of protection.

Source reference: p. 1

It also considered Section 17 regarding the Tribunal's power to grant interim relief and Section 12(2) regarding arbitrator disclosures.

Source reference: p. 5-6

The court relied on the Supreme Court precedent in *Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.* (2024), which emphasizes the sanctity of contracts and the requirement of fairness by public authorities to maintain the integrity of public procurement.

Source reference: para. 14
04

Reasoning

The Court found the Petitioner’s arguments regarding the timing of the CPN (issued less than two months before contract expiry) and the overlap of issues with ongoing conciliation proceedings to be substantive.

Source reference: para. 12-13

It reasoned that because the project involves foreign investment and a statutory body, the balance of convenience favored the Petitioner to ensure contractual fairness.

Source reference: para. 14

The Court determined that allowing the CPN to operate would cause irreparable harm by disrupting toll collection, which is the "subject matter" of the agreement.

Source reference: para. 15

While acknowledging NHAI's argument that the contract is terminable, the Court clarified that it was not granting specific enforcement but merely preserving the status quo so as not to render the impending arbitral process "nugatory".

Source reference: para. 21
05

Holding

The Court stayed the operation of the Cure Period Notice until the Arbitral Tribunal hears the Section 17 application.

By consent, the parties waived Section 21 and Section 11 requirements, and the Court referred the matter to a three-member Arbitral Tribunal to be nominated within two weeks.

Source reference: para. 16-18

The Petitioner is directed not to withdraw ₹94 crores from the Escrow account until the Tribunal hears the matter.

Source reference: para. 22

The Section 9 petition was disposed of with a direction that it be treated as a Section 17 application before the newly constituted Tribunal.

Source reference: para. 19, 29
Delhi High Court

Original Court PDF

Igatpuri Highway Private Limited v. National Highways Authority of India [O.M.P. (I) (COMM.) 84/2026]

Delhi High Court

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment