Facts
The Petitioner, a Class-I Government Contractor, was awarded a works contract for road improvement via a tender notice dated 20.03.2017
Source reference: p.2At the time of the bid, the tax liability was 6% under the Tripura Value Added Tax (TVAT) Act
Source reference: p.2Before the work order was issued, the TVAT Act was repealed and replaced by the CGST/TSGST Acts on 01.07.2017, increasing the tax rate to 12%
Source reference: p.3The Petitioner notified the department that he would not bear the increased tax liability, and the PWD Department's Advisory Board allegedly approved this
Source reference: p.3However, the formal agreement signed on 24.11.2017 did not explicitly cap the tax at 6% but included Clause 42.1, stating that any Central/State taxes paid by the contractor would be reimbursed on proof of payment
Source reference: p.4The Petitioner sought reimbursement of Rs. 2,21,48,746.08 representing the GST paid, which the state refused to refund, citing Section 142(10) of the GST Act
Source reference: p.8-9Issues
1. Whether the Petitioner is liable to pay tax at the GST rate of 12% even if the tender originated under the VAT regime.
Source reference: p.11 / para. 48-492. Whether the Petitioner is entitled to reimbursement of the paid GST under Clause 42.1 of the agreement, despite the absence of "Part-II of Schedule A" mentioned therein.
Source reference: p.12 / para. 51-533. Whether the High Court can exercise its writ jurisdiction under Article 226 in a matter arising out of a commercial contract.
Source reference: p.14 / para. 57-59Law Applied
The court applied Section 9 of the CGST/TSGST Acts regarding the levy of tax
Source reference: p.11Section 142(10) of the TSGST Act, which mandates GST liability for supplies made after the appointed day (01.07.2017) even for prior contracts
Source reference: p.11Regarding reimbursement, the court relied on the contractual principle of Clause 42.1
Source reference: p.12The precedent in State of Tripura v. Sri Arun Kumar Dey (affirmed by the Supreme Court), which held that the absence of a specific schedule does not defeat a contractor's right to reimbursement if proof of payment is provided
Source reference: p.12-13On jurisdiction, the court followed ABL International Ltd. v. Export Credit Guarantee Corp. and Unitech Ltd. v. TSIIC, establishing that writ jurisdiction is maintainable against arbitrary state action in contractual matters
Source reference: p.15Reasoning
The court reasoned that since the contract was signed after 01.07.2017, the incidence of tax was governed strictly by the GST regime, negating the Petitioner’s claim to pay only 6% VAT
Source reference: para. 48-49the court found the State’s refusal to reimburse the tax paid as "patently arbitrary"
Source reference: para. 55It held that Clause 42.1 explicitly promised reimbursement of "other taxes" (which includes GST) upon proof of payment
Source reference: para. 50The court dismissed the State’s technical defense regarding the missing "Schedule A," noting that the PWD department drafted the agreement and cannot benefit from its own drafting omissions
Source reference: para. 52-53By reviewing the GSTR-1 and GSTR-3B filings, the court confirmed the Petitioner had proven the payment of Rs. 2.21 Crores, creating a duty on the State to fulfill its contractual obligation of reimbursement
Source reference: para. 54-56Holding
The court allowed the Writ Petition, holding that the Petitioner is entitled to reimbursement of the GST paid under Clause 42.1
The Court directed the Respondents to pay Rs. 2,21,48,746.08 (less any prior reimbursements) along with interest at 12% per annum, citing the commercial nature of the contract and Clause 89 of the agreement which allowed the state to charge similar interest on contractor defaults
Source reference: para. 61-63The payment must be made within three months
Source reference: para. 63Original Court PDF
Sri Nimai KarvsThe State of Tripura and Ors.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in