Karnataka High Court

Substantial implementation of development scheme precludes lapsing of land acquisition under the BDA Act.

KRISHNA MURTHY. P vs THE STATE OF KARNATAKA

Karnataka High CourtJUDGMENT: March 12, 20263 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The dispute concerns the acquisition of lands in Survey Nos. 47/1, 47/3, 47/4, and 47/5 at Gubbalala Village for the formation of the "Further Extension of Banashankari VI Stage Layout"

Source reference: p. 26

The Preliminary Notification was issued on 07.11.2002, followed by a Final Notification on 09.09.2003

Source reference: p. 26-27

An award was passed on 12.12.2003, and the Bangalore Development Authority (BDA) claimed to have taken possession on 08.01.2004

Source reference: p. 30

The petitioners (landowners), through a GPA holder, challenged these notifications in 2016—approximately 12 years after the acquisition—alleging that possession was never legally taken, compensation was not deposited in court, and the scheme had lapsed

Source reference: p. 27-29

The Learned Single Judge (LSJ) quashed the notifications on 27.01.2025, holding that the BDA failed to prove legal possession or deposit of compensation

Source reference: p. 28

The BDA appealed, asserting substantial implementation of the scheme, including the allotment of 53 sites and infrastructure development

Source reference: p. 33-34
02

Issues

1. Whether the acquisition scheme had lapsed under Section 27 of the Bangalore Development Authority Act, 1976, due to failure to implement the scheme within five years?

Source reference: p. 34-35

2. Whether the acquisition proceedings lapsed under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, due to non-payment of compensation or failure to take physical possession?

Source reference: p. 29-30

3. Whether the Learned Single Judge erred in quashing the notifications despite a gross delay of 12 years and the creation of third-party rights?

Source reference: p. 32-33
03

Law Applied

The court primarily applied Section 27 of the Bangalore Development Authority (BDA) Act, 1976, which governs the lapsing of schemes

Source reference: p. 35, 43

It relied on the precedent in Offshore Holdings Pvt. Ltd. v. Bangalore Development Authority (2011) 3 SCC 139, which established that the BDA Act is a self-contained code and that Section 11-A of the Land Acquisition Act (regarding lapsing) does not apply to it

Source reference: p. 41-43

the court applied the principles from Indore Development Authority v. Manoharlal and Others (2020) 8 SCC 129, clarifying that "paid" under Section 24(2) of the 2013 Act includes tendering amount to the treasury and that the refusal of a landowner to accept compensation does not lead to the lapsing of proceedings

Source reference: p. 44-48
04

Reasoning

The Division Bench found that the LSJ failed to appreciate the substantial implementation of the project. Evidence, including Google Maps (2000–2025) and an affidavit from the BDA Commissioner, demonstrated that 53 sites had been allotted, conveyance deeds registered, roads formed, and houses constructed by allottees

Source reference: p. 33, 48-49

Citing Offshore Holdings, the court noted that once substantial development commences, the acquisition cannot be deemed to have lapsed under Section 27 of the BDA Act

Source reference: p. 38

Regarding the 2013 Act, the court held that since the award amount was deposited in the Treasury and the BDA had taken steps for possession, Section 24(2) was inapplicable, especially as the proceedings were concluded under the BDA Act

Source reference: p. 48-49

The court also emphasized that the 12-year delay in challenging the notifications was fatal, particularly as third-party rights (allottees) had intervened and the LSJ had brushed aside the issue of laches

Source reference: p. 32
05

Holding

The court answered the issues in the negative regarding the lapsing of the scheme. It held that the scheme was substantially implemented and the legal requirements for compensation and possession were met as per the evolved interpretation of the 2013 Act

Consequently, the High Court set aside the impugned judgment and order dated 27.01.2025 passed by the Learned Single Judge. The writ petitions were dismissed, and all intra-court appeals filed by the BDA and the allottees were allowed

Source reference: p. 49
Karnataka High Court

Original Court PDF

KRISHNA MURTHY. PvsTHE STATE OF KARNATAKA

Karnataka High Court · March 12, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment