01Facts
The petitioner challenged an adjudication order dated 15 December 2025 under Section 73 of the KGST/CGST Acts and a subsequent garnishee notice in Form GST DRC-13 dated 17 August 2026.
pp. 3–4The adjudication proceeded on the basis that the petitioner had not responded to the audit note, intimation, or show-cause notice.
p. 4However, the record showed that the petitioner had replied to the Form GST ASMT-10 intimation on 19 September 2024, explaining that an apparent discrepancy in its GSTR-9 for FY 2021–22 arose from a clerical error in reporting SGST, and that tax had not been short-paid.
pp. 4–6The petitioner also relied on a reply dated 1 March 2025 concerning the inspection.
pp. 4–502Issues
i.1. Whether the adjudication order could stand when the petitioner’s prior response explaining the discrepancy was not considered.
pp. 4–6ii.2. Whether the consequential garnishee notice should be set aside and the petitioner given an opportunity to respond to the show-cause notice.
pp. 6–703Law Applied
Section 73 of the KGST/CGST Acts governs determination of tax not paid, short-paid, or erroneously refunded, or input tax credit wrongly availed or utilised.
pp. 3–4The Court applied the principle that a taxpayer’s relevant explanation on record must be considered when deciding whether the allegations in a show-cause notice should be affirmed.
p. 6Although the petition also sought rectification under Section 161 of the KGST Act, the Court did not determine that request.
pp. 2–3, 7Provisions in the judgment · 3 · Linked ones open on LawLens
KARNATAKA GOODS AND SERVICES TAX ACT, 2017 Section 161Section 73
Central Goods and Services Tax Act, 2017 Section 73
04Reasoning
The adjudication order treated the petitioner as having failed to respond, but the record contained an earlier reply asserting that the GSTR-9 discrepancy was clerical and that there had been no short payment of tax.
pp. 4–6The Court considered that explanation material to deciding whether the show-cause notice’s allegations should be sustained.
p. 6Because the explanation had not been considered in the adjudication, the Court concluded that the proceedings should be restored for the petitioner to file a detailed response.
pp. 6–705Holding
The Court allowed the petition and quashed the adjudication order dated 15 December 2025 and the consequential garnishee notice dated 17 August 2026.
pp. 6–7It directed the petitioner to file a detailed response to the show-cause notice with the third respondent by 27 October 2026, without further notice.
p. 7Original Court PDF
M/S 3 PACE POWER SYSTEMvsTHE STATE OF KARNATAKA
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in