Facts
The Appellant (PWD) and Respondent entered into a contract on 27.04.2016 for road widening at a total price of Rs. 155.89 Crores.
Source reference: para. 2The contract commenced under the old tax regime (VAT) but work continued after 01.07.2017 following the introduction of Goods and Service Tax (GST).
Source reference: para. 4A dispute arose regarding the calculation of GST on running bills and price adjustments.
Source reference: para. 7The Respondent successfully invoked arbitration, leading to an award dated 27.01.2024, which applied the Ministry of Road Transport and Highways (MoRTH) Standard Operating Procedure (SOP) dated 19.11.2018 for calculations.
Source reference: para. 18.2This awarded the Respondent Rs. 11.35 Crores plus 15% penalty and 18% interest.
Source reference: para. 18.9The Commercial Court, Lucknow affirmed the award under Section 34 of the Arbitration and Conciliation Act, 1996 ("the Act") on 18.07.2025.
Source reference: para. 1, 19The Appellant challenged this in the present Section 37 appeal.
Source reference: para. 20Issues
1. Whether a dispute relating to the quantum and manner of tax calculation is arbitrable.
Source reference: para. 22.1, 392. Whether the Technical Specifications borrowed from MoRTH in the contract also made MoRTH’s tax-related SOP binding over State Government Orders.
Source reference: para. 23.1, 513. Whether the Arbitral Tribunal can delegate its duty by making an award subject to final assessment by Tax Authorities.
Source reference: para. 26, 100Law Applied
The Court applied Section 37 and Section 34 of the Arbitration and Conciliation Act, 1996, which severely restrict the scope of judicial interference to "patent illegality" and "fundamental policy of Indian Law".
Source reference: para. 1, 105It categorized tax disputes into Head-A (arbitrable contractual obligations like inter-se liability/indemnity) and Head-B (non-arbitrable statutory determinations like tax rates/classification).
Source reference: para. 41Reliance was placed on Vidya Droliya v. Durga Trading Corpn. regarding the non-arbitrability of sovereign functions.
Source reference: para. 40Reliance was placed on Gayatri Balasamy v. ISG Novasoft Technologies Ltd., establishing that courts may modify an award only through severing invalid portions if they are independent of valid portions.
Source reference: para. 107-108Sections 142(2), (10), and (11) of the GST Act, 2017 were noted as the substantive law for transitional tax revisions.
Source reference: para. 102(vii)Reasoning
The Court first held the dispute arbitrable under "Head-A," as it concerned which calculation method (MoRTH vs. State GO) applied between the parties, rather than challenging the State’s taxing power.
Source reference: para. 47-48However, the Court found the award patently illegal because the Arbitrator assumed that borrowing "technical specifications" (engineering standards) for road construction implicitly imported MoRTH’s financial/tax SOPs.
Source reference: para. 70, 77The Court reasoned that tax is governed by statutory law and executive instructions (State GOs), which are binding on the Department.
Source reference: para. 65, 87The Arbitrator erred by applying an EPC-contract SOP to an "item-rate" contract without evidence of mutual consent or contractual basis.
Source reference: para. 81, 84The award lacked finality and was perverse as it calculated penalties/interest under Section 50 of the GST Act without evidence of an actual tax demand or assessment by the authorities, effectively acting as an "Assessing Officer".
Source reference: para. 97, 102(v)Holding
The Court partly allowed the appeal.
It set aside the Commercial Court’s judgment and modified the Arbitral Award. Applying the doctrine of severability, the Court upheld the findings on Issue 1 (contract type) and Issue 10 (reimbursement of DRE fees of Rs. 66,500).
Source reference: para. 110-111The findings on GST calculation, interest, and penalties (Issues 2–4, 8, and 9) were set aside and remitted to a newly constituted Arbitral Tribunal for fresh adjudication in light of the High Court’s observations.
Source reference: para. 111Parties were directed to bear their own costs.
Source reference: para. 111Original Court PDF
U.P. Public Works Deptt. Thru. Chief Engineer Central Zone Lko.vsM/S Vriddhi Infratech India Pvt. Ltd. Thru. Signatory Sandeep Anne
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in