Facts
The petitioner participated in an NHAI tender for Package-VIII of the Vadodara–Mumbai Expressway Project under an RFP dated 23.01.2026.
Source reference: p.12, para.10The RFP, as modified by Corrigendum No. 4, required bidders to demonstrate experience of constructing at least one similar Major Bridge/ROB/Flyover having a span of at least 53.6 metres and a structure length of at least 132 metres.
Source reference: p.12, para.10The petitioner relied, inter alia, on an Experience Certificate dated 17.04.2026 issued by MSRDC, which recorded VOP span arrangements of 1×15 m + 1×55.80 m + 1×15 m at Chainage 316+759 and 1×15 m + 1×53.80 m + 1×15 m at Chainage 344+075.
Source reference: p.18, para.18NHAI had earlier declared the bid non-responsive for non-submission of a Provisional Completion Certificate; that decision was set aside in W.P.(C) 8524/2026, with a direction for fresh evaluation after considering the PCC dated 30.06.2026.
Source reference: pp.3–4, paras.2.3–2.4During fresh evaluation, NHAI compared the 17.04.2026 certificate with an earlier MSRDC certificate dated 13.05.2023, which recorded the relevant VOPs as having two spans of 41.50 m and two spans of 35 m, respectively.
Source reference: p.19, para.18NHAI sought clarification from MSRDC, which by letter dated 27.07.2026 confirmed that the VOP at Chainage 316+759 comprised two spans of 41.50 m each and that its total structural length was 83 m.
Source reference: pp.20–23, paras.22, 26NHAI issued a show-cause notice dated 28.07.2026 concerning alleged misrepresentation and subsequently declared the petitioner’s technical bid non-responsive on 31.07.2026 for failure to satisfy the additional bridge-experience criterion.
Source reference: pp.3–4, paras.2.5–2.7Issues
Whether NHAI correctly interpreted the term “span” under the modified Clause 2.2.2.2(ii) of the RFP and rightly concluded that the petitioner’s VOP at Chainage 316+759 had a span of 41.50 m, rather than 83 m, thereby failing the 53.6 m eligibility threshold?
Source reference: pp.22–26, paras.25–37Whether the petitioner could rely on the 67 m skew dimension of the Minor Bridge shown in the RFP drawings, or contend that the relevant dimension was 37.949 m, for assessing the applicable eligibility threshold?
Source reference: pp.27–29, paras.39–42Whether NHAI was entitled to verify the apparent inconsistencies between the two MSRDC Experience Certificates and to issue the show-cause notice dated 28.07.2026?
Source reference: pp.29–30, paras.44–48Whether the earlier judgment in W.P.(C) 8524/2026 precluded NHAI from undertaking such verification during the fresh technical evaluation?
Source reference: p.30, para.45Law Applied
The Court exercised limited judicial review under Article 226 over the evaluation of a public tender and applied the principle that the authority which authors a tender document is ordinarily best placed to interpret its requirements, relying on Agmatel India Pvt. Ltd. v. Resoursys Telecom, (2022) 5 SCC 362, particularly the principle that the tendering authority’s interpretation should not be interfered with unless arbitrary or irrational.
Source reference: p.11, para.7.2; p.26, para.35The Court applied the express terms of modified Clause 2.2.2.2(ii) of the RFP, requiring prior experience of a similar Major Bridge/ROB/Flyover with a span of at least 53.6 m and structure length of at least 132 m.
Source reference: p.12, para.10It also relied on the definition of “span” in IRC-5/2024 as the horizontal distance between the centre lines of adjacent supports of a bridge superstructure.
Source reference: p.21, para.23A bidder relying upon documents as part of its bid is responsible for their accuracy and cannot avoid accountability merely because the documents were issued by a third party.
Source reference: p.30, para.46The Court further recognised NHAI’s authority to verify contradictory bid documents before determining responsiveness, while refraining from deciding the ultimate merits of the pending debarment proceedings.
Source reference: pp.29–30, paras.44–48Reasoning
The Court held that the relevant measure of span was the distance between adjacent supports, namely, from abutment A1 to pier P1 and from pier P1 to abutment A2, rather than the aggregate distance between the two abutments.
Source reference: pp.22–25, paras.26–32The MSRDC as-built drawing showed two spans of 41.50 m each at Chainage 316+759, and the RFP drawing for the comparable Minor Bridge showed two spans of 67 m each measured in the same manner.
Source reference: pp.23–25, paras.27–30Consequently, the petitioner’s reliance on the aggregate structural length of 83 m was rejected because it did not constitute a single span of at least 53.6 m.
Source reference: pp.25–26, paras.30–38The Court also rejected the argument that the 67 m dimension in the RFP drawing was merely a skew dimension and that the 37.949 m dimension should govern, finding the submission misleading and inconsistent with the corresponding treatment of the MSRDC drawing.
Source reference: pp.27–29, paras.40–42The Court further found that the two MSRDC certificates contained prima facie material contradictions regarding the same structures.
Source reference: pp.19–23, paras.19–23, 26–34NHAI was therefore entitled to seek clarification from MSRDC, and the clarification dated 27.07.2026, together with the as-built drawing, supported NHAI’s conclusion that the petitioner lacked the requisite span experience.
Source reference: pp.19–23, paras.19–23, 26–34The earlier judgment only required reconsideration of the petitioner’s bid after taking the PCC into account; it did not prevent NHAI from evaluating the remaining technical requirements or verifying bid documents.
Source reference: p.30, para.45Since the petitioner had relied on the Experience Certificate in its bid, it could not disclaim responsibility for its contents.
Source reference: p.30, para.46The Court nevertheless expressly refrained from deciding whether the 17.04.2026 certificate was fraudulent, leaving that question to the proceedings arising from the show-cause notice.
Source reference: p.30, para.47Holding
The Court upheld NHAI’s decision declaring the petitioner’s technical bid non-responsive.
It held that the petitioner’s VOP experience demonstrated two spans of 41.50 m each, not a qualifying single span of 83 m, and therefore did not satisfy the minimum 53.6 m requirement under modified Clause 2.2.2.2(ii) of the RFP.
Source reference: pp.26–29, paras.34–43The challenge to the show-cause notice was also rejected; NHAI was entitled to investigate the contradictory certificates, and the earlier judgment did not bar such verification.
Source reference: pp.29–30, paras.44–49The petitioner was permitted to file its reply to the show-cause notice within three days, after which NHAI was directed to proceed in accordance with law.
Source reference: p.30, para.49The writ petition was dismissed with costs of ₹25,000 payable to NHAI; pending applications were disposed of and interim orders, if any, were vacated.
Source reference: p.31, paras.50–51Acts & Sections Cited
4 provisions across 2 statutes referred to in this judgment. Linked provisions open on LawLens.
RFP3
Corrigendum No. 4 dated 15.04.20261
Original Court PDF
Roadway Solutions India Infra LimitedvsUnion Of India & Anr.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
