Facts
The petitioner submitted a bid for restoration and lining of the left side of Main Canal No. 01, Khatima, Udham Singh Nagar District, for the reach between Km 2.200 and Km 4.500.
Source reference: paras. 2–4, 7–8The petitioner’s bid was declared technically non-responsive on the grounds that he lacked the prescribed experience and had not submitted the audit report for 2021.
Source reference: paras. 2–4, 7–8The contract was subsequently awarded to respondent no. 4.
Source reference: paras. 2–4, 7–8The audit-report defect was later cured when the petitioner supplied the report, and the Court treated that defect as minor.
Source reference: paras. 2–4, 7–8The dispute therefore concerned whether the petitioner’s previous experience—relating to construction of a canal for channelising flood water and other channel/sewage-related works—qualified as experience in a “similar work” under the tender conditions.
Source reference: paras. 2–4, 7–8The tender required satisfactory completion of at least one similar work involving canal lining in brickwork, with similarity assessed by reference to the nature, physical size, complexity, methods, technology and other characteristics of the required work.
Source reference: paras. 5–6It also prescribed minimum quantities of cement concrete, including RCC/PCC, and brickwork.
Source reference: paras. 5–6The Department treated the petitioner’s previous works as materially different from irrigation-canal restoration and lining works.
Source reference: paras. 3, 8–10The petitioner challenged the rejection of his bid and the award of the contract under Article 226 of the Constitution.
Source reference: paras. 3, 8–10Issues
Whether the petitioner’s experience in constructing a flood-water channel and other channel/sewage-related works constituted experience in a “similar work” involving restoration and lining of an irrigation canal under Clause 2.2A(b) of the tender document?
Source reference: paras. 5, 7–9, 12–14Whether the petitioner could satisfy the tender’s experience requirement merely by establishing that he had executed the prescribed quantities of RCC/PCC and brickwork, notwithstanding the absence of similarity in the nature and purpose of the works?
Source reference: paras. 6, 9, 12, 14Whether the Department’s technical evaluation and rejection of the petitioner’s bid warranted interference under Article 226 of the Constitution?
Source reference: paras. 10, 15–18Law Applied
The Court applied Clause 2.2A(b) of the Standard Bidding Document, which required completion of at least one “similar work” and directed that similarity be assessed strictly with reference to the nature, physical size, complexity, methods, technology and other characteristics of the required work.
Source reference: paras. 5, 14The quantity requirements under Clause 2.2A(d) could not be read in isolation so as to render the separate “similar work” requirement redundant.
Source reference: para. 14Relying on Afcons Infrastructure Ltd. v. Nagpur Metro Rail Corporation Ltd., (2016) 16 SCC 818, along with the principles reiterated from Central Coalfields Ltd. v. SLL-SML (Joint Venture Consortium), (2016) 8 SCC 622, Dwarkadas Marfatia & Sons v. Port of Bombay, (1989) 3 SCC 293, and Ramana Dayaram Shetty v. International Airport Authority of India, (1979) 3 SCC 489, the Court held that the author of tender conditions is ordinarily the best judge of the project’s requirements and its interpretation should receive judicial deference.
Source reference: paras. 15–16Interference is justified only where the decision is mala fide, arbitrary, irrational, perverse, or reflects a defective decision-making process.
Source reference: paras. 15–16Reasoning
The Court distinguished between the petitioner’s previous works and the tendered work by examining their nature, purpose and functional requirements.
Source reference: paras. 12–13The present contract concerned restoration and lining of an irrigation canal, which is designed to carry and distribute water to agricultural fields.
Source reference: paras. 12–13In contrast, flood-protection works are intended to control or divert floodwater and prevent damage, while sewage or drainage works serve different functional purposes.
Source reference: paras. 12–13Although the works could contain common civil-construction components, such as concrete and brickwork, the common quantities did not establish the required similarity.
Source reference: para. 14Clause 2.2A(d) therefore could not override Clause 2.2A(b), which expressly required experience in a similar work, specifically canal lining in brickwork.
Source reference: para. 14Applying the deferential standard in Afcons Infrastructure, the Court held that the Department’s distinction between irrigation-canal works and flood-water/sewage-related works was neither arbitrary nor perverse.
Source reference: paras. 17–18The Technical Evaluation Committee’s assessment was consequently not amenable to interference under Article 226.
Source reference: paras. 17–18Holding
The Court held that the petitioner’s prior experience did not satisfy the tender requirement of experience in a “similar work.”
Execution of the stipulated quantities of RCC/PCC and brickwork, without corresponding similarity in the nature and purpose of the work, was insufficient.
Source reference: paras. 17–19The Department’s rejection of the petitioner’s technical bid was found neither mala fide, arbitrary nor perverse.
Source reference: paras. 17–19The writ petition challenging the rejection of the bid and award of the contract to respondent no. 4 was accordingly dismissed.
Source reference: paras. 17–19Acts & Sections Cited
1 provisions across 1 statute referred to in this judgment. Linked provisions open on LawLens.
Commercial Documents Evidence Act, 19391
Original Court PDF
BAHADUR SINGH PATNIvsSTATE OF UTTARAKHAND
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
