Madras High Court

The earlier order’s observations continue to operate following the temple’s unlocking.

R.Subramanian vs The Commissioner

Madras High CourtJUDGMENT: October 15, 20261 MIN READSOURCE JUDGMENT
The earlier order’s observations continue to operate following the temple’s unlocking.. R.Subramanian vs The Commissioner. Madras High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

Both petitions under Article 226 concerned the locking of Arasalwar Pillaiyar Temple, Theppakulatheru, Tiruchendur.

Source reference: pp. 1–3

The petitioners sought consideration of their respective representations and directions to remove the lock and prevent rival claimants from locking the temple.

Source reference: pp. 1–3

The temple had also been the subject of W.P.(MD) No. 28924 of 2026, disposed of on 5 October 2026.

Source reference: p. 4, para. 1

At the hearing, petitioners’ counsel stated that the temple had been unlocked after these petitions were filed; the Special Government Pleader produced the Joint Commissioner’s order dated 12 October 2026 concerning the unlocking and related measures.

Source reference: p. 4, paras. 2–3
02

Issues

1. Whether further directions were required on the petitioners’ requests to remove the lock and prevent rival claimants from locking the temple, given that it had been unlocked.

Source reference: pp. 1–4, paras. 2–3

2. Whether the observations in paragraphs 9 to 11 of the order dated 5 October 2026 in W.P.(MD) No. 28924 of 2026 should continue to operate in these petitions.

Source reference: p. 4, para. 4
03

Law Applied

The petitions invoked the High Court’s jurisdiction under Article 226.

Source reference: pp. 1–3

The order does not set out or apply a separate substantive statutory rule or precedent; it records the temple’s unlocking and the Joint Commissioner’s subsequent order, and expressly continues the observations in paragraphs 9 to 11 of the earlier order dated 5 October 2026.

Source reference: p. 4, paras. 2–4
04

Reasoning

Since the temple had been unlocked after the petitions were instituted, and the Joint Commissioner’s order addressing the unlocking and related measures was placed on record, the Court disposed of the petitions on those developments rather than issuing the requested directions anew.

Source reference: p. 4, paras. 2–4

It further preserved the operation of the specified observations in the earlier order.

Source reference: p. 4, para. 4
05

Holding

The Court disposed of both writ petitions, holding that the observations in paragraphs 9 to 11 of its order dated 5 October 2026 in W.P.(MD) No. 28924 of 2026 would continue to operate.

No order as to costs was made.

Source reference: p. 4, para. 5
Madras High Court

Original Court PDF

R.SubramanianvsThe Commissioner

Madras High Court · October 15, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment