Facts
The Petitioner (TBEA) was awarded a Purchase Order (PO) by the Respondent (BHEL) on 18.12.2017 for the supply of transformers
Source reference: p.3The Petitioner was required to meet Prequalification Requirements (PQR), involving an undertaking by its Parent Company to furnish an Additional Performance Bank Guarantee (APBG) of 10%
Source reference: p.3Delays occurred in delivery (supplied July 2019 against a tentative date of Nov 2018), leading BHEL to impose Liquidated Damages (LD) of ₹7,85,41,104
Source reference: p.8, 11BHEL withheld ₹5,23,76,868 due to the non-submission of the APBG by the Parent Company
Source reference: p.8A Sole Arbitrator issued an award on 06.01.2022, reducing the LD by 50%, allowing TBEA to submit the APBG itself (if authorized), granting proportionate costs, but denying future interest
Source reference: p.10Both parties filed cross-objections under Section 34 of the Arbitration and Conciliation Act, 1996
Source reference: p.2Issues
1. Whether the imposition of 50% Liquidated Damages was valid despite the alleged lack of actual loss and non-readiness of the site
Source reference: para. 6, 332. Whether the Arbitrator exceeded jurisdiction by allowing the Petitioner to furnish the APBG on behalf of its Parent Company
Source reference: para. 16, 413. Whether the Petitioner is entitled to post-award (future) interest under the statutory mandate of the Act
Source reference: para. 12, 53Law Applied
Section 34 of the Arbitration and Conciliation Act, 1996, regarding the limited grounds for setting aside awards, including "patent illegality"
Source reference: para. 34, 49Sections 73 and 74 of the Indian Contract Act, 1872, as interpreted in Kailash Nath v. DDA, regarding reasonable compensation and genuine pre-estimates of loss
Source reference: para. 6, 37Associate Builders v. DDA and Ssangyong Engg. v. NHAI to define the boundaries of judicial interference
Source reference: para. 35, 38Section 31(7)(b) of the Act and the precedent in Hyder Consulting (UK) Ltd. v. State of Orissa, which establishes that post-award interest is a statutory mandate
Source reference: para. 14, 55, 56Reasoning
Regarding LD, the court found the Arbitrator’s decision to award 50% (₹3,92,70,552) reasonable, as the Respondent proved actual monetary loss via debit notes from the end-customer (TANTRANSCO), and a 70-day delay was attributable to the Petitioner
Source reference: para. 33, 36, 38On the APBG issue, the court held that the Arbitrator’s interpretation—permitting the Petitioner to submit the guarantee if authorized by the parent—was a practical commercial approach within his jurisdiction and did not constitute "rewriting the contract"
Source reference: para. 42, 44Regarding costs, the court upheld the Arbitrator's discretion under Section 31A as the Petitioner was partially successful
Source reference: para. 46Regarding future interest, the court found the Arbitrator erred; while Union of India v. Manraj Enterprises allows contracting out of pendente lite interest, Section 31(7)(b) is a statutory mandate for post-award interest that cannot be waived or denied by the tribunal
Source reference: para. 56, 59Holding
The Court dismissed BHEL's petition [O.M.P. (COMM) 294/2022] and partially allowed TBEA's petition [O.M.P. (COMM) 307/2022]
It upheld the reduction of Liquidated Damages and the directions regarding the APBG and costs
Source reference: para. 39, 44, 46The Court modified the award to grant the Petitioner future interest at the rate of 2% higher than the current prevalent rate from the date of the award until payment, holding that post-award interest is a non-discretionary statutory requirement
Source reference: para. 58, 60Original Court PDF
Tbea Energy India Private LimitedvsM/S Bharat Heavy Electricals Limited
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in