Rajasthan High Court

Third-party obstructions beyond a contractor's control constitute force majeure, rendering contract termination for consequential delays arbitrary.

M/S UNITED COAL CARRIER vs RAJASTHAN STATE MINES AND MINERAL LIMITED

Rajasthan High CourtJUDGMENT: March 30, 20263 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Petitioner was awarded a tender by Rajasthan State Mines and Minerals Ltd. (RSMML) on 17.07.2023 for loading and transporting limestone at Sanu mines, Jaisalmer

Source reference: para. 2, 2.1

A formal agreement was executed on 16.08.2023

Source reference: para. 2.1

The Petitioner failed to commence work within the stipulated 30 days due to obstructions and illegal pressure from the Jaisalmer Truck and Dumper Association

Source reference: para. 2.3, 3.1

The Petitioner sought police protection via a writ petition and subsequent contempt proceedings, wherein the State admitted to establishing a police outpost to resolve the law-and-order crisis

Source reference: para. 2.3, 2.4

Internal note-sheets of RSMML acknowledged that the delay (53 days) and subsequent production shortfall were due to "force majeure" conditions beyond the Petitioner's control

Source reference: para. 3.3, 12.1

Despite these internal findings, RSMML issued an order on 24.12.2023 terminating the contract, forfeiting the security deposit (including a bank guarantee of ₹5.27 crores), and blacklisting the Petitioner for three years

Source reference: para. 1, 2.7

The Petitioner challenged this order, asserting that the delay was covered under the Force Majeure clause of the NIT

Source reference: para. 3.1
02

Issues

1. Whether the writ petition is maintainable in a contractual matter involving alleged disputed questions of fact regarding the performance of the contract

Source reference: para. 5.1, 10, 11.1

2. Whether the obstruction by a third-party truck union constitutes "Force Majeure" under Clause 4.65 of the NIT

Source reference: para. 5.2, 15.1, 16

3. Whether the termination of the contract and the consequential blacklisting and forfeiture of security deposit were arbitrary and legally sustainable

Source reference: para. 3.5, 10.4, 20
03

Law Applied

The Court applied the principles of judicial review in contractual matters as established in Tata Cellular v. Union of India, which permits intervention in cases of arbitrariness, irrationality, or procedural impropriety

Source reference: para. 10.1

It relied on M.P. Power Management Co. Ltd. v. Sky Power Southeast Solar India Pvt. Ltd., holding that the State must act fairly even in non-statutory contracts and that writ jurisdiction is not barred by the mere existence of a contract if the State’s action is palpably unreasonable

Source reference: para. 10.3, 82.3

The Court further interpreted Clause 4.65 of the NIT regarding "Force Majeure," which includes "any other cause beyond reasonable control of the party affected"

Source reference: para. 15.1

Principles regarding the sanctity of public tenders from Subodh Kumar Singh Rathour v. CEO were also applied to prevent the capricious exercise of executive power

Source reference: para. 19
04

Reasoning

The Court rejected the Respondent's objection to maintainability, noting that while courts exercise restraint in tender matters, they must intervene when State action is arbitrary

Source reference: para. 10.4

It found that the "disputed questions of fact" regarding law-and-order issues were actually admitted facts, as evidenced by RSMML’s own internal note-sheets and submissions made in previous contempt proceedings

Source reference: para. 11.2, 12.2

On the merits, the Court observed that Clause 4.65 was illustrative, not exhaustive; the truck union agitation and the necessity of police escort for daytime-only operations fell within the ambit of "causes beyond reasonable control"

Source reference: para. 16, 16.1

The Court highlighted the "contradictory approach" of the State: RSMML’s internal records treated the situation as Force Majeure and recommended waiving penalties, yet the formal impugned order cited the same delays as grounds for termination

Source reference: para. 12.1, 20

This inconsistency rendered the termination, forfeiture, and blacklisting arbitrary and irrational

Source reference: para. 20, 22

Since the underlying termination was void, the consequential blacklisting and forfeiture lacked any legal foundation

Source reference: Epilogue para. 2
05

Holding

The Court answered the issues in favour of the Petitioner, holding that the situation constituted a Force Majeure event under Clause 4.65

It ruled that the Petitioner could not be held liable for delays or shortfalls occasioned by circumstances beyond their control

Source reference: para. 18

The Court quashed and set aside the impugned order dated 24.12.2023 in its entirety, including the termination, blacklisting, and forfeiture

Source reference: para. 23, Epilogue para. 2

The Petitioner was permitted to continue the balance duration of the contract, especially as RSMML admitted the Petitioner's performance post-Force Majeure was satisfactory

Source reference: Epilogue para. 3, 4

The writ petition was allowed

Source reference: para. 23
Rajasthan High Court

Original Court PDF

M/S UNITED COAL CARRIERvsRAJASTHAN STATE MINES AND MINERAL LIMITED

Rajasthan High Court · March 30, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment