APTEL
Administrative and Public LawCommercial and Corporate Law

Transmission project cost and IDC determinations require fresh regulatory consideration.

M/s Devi Energies Pvt. Ltd. vs Arunachal Pradesh State Electricity Regulatory Commission

APTELJUDGMENT: October 06, 20262 MIN READSOURCE JUDGMENT
Transmission project cost and IDC determinations require fresh regulatory consideration.. M/s Devi Energies Pvt. Ltd. vs Arunachal Pradesh State Electricity Regulatory Commission. APTEL. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The appellant, a transmission licensee under Section 14 of the Electricity Act, 2003, developed a 132 kV transmission system to evacuate power from its 24 MW Dikshi Small Hydro Electric Project

Source reference: pp. 3–5

It sought approval of the system’s Aggregate Revenue Requirement and transmission charges for FYs 2019–20 to 2021–22.

Source reference: pp. 6–7

The Commission approved a capital cost of ₹50.7 crore and interest during construction (IDC) of ₹9.05 crore, below the appellant’s claims of ₹63.58 crore and ₹11.36 crore respectively.

Source reference: pp. 6–7, 10

The appellant appealed, challenging the Commission’s assessment of civil-works costs and IDC.

Source reference: no citation

During the appeal hearing, the Commission’s counsel stated that the matter could be remanded for reconsideration.

Source reference: para. 12
02

Issues

1. Whether the Commission’s assessment of civil-works costs and IDC, including its restriction of those amounts below the appellant’s claims, required reconsideration

Source reference: pp. 7, 10–11

2. Whether the impugned order should be set aside and the tariff petition remanded to the Commission for fresh consideration

Source reference: paras. 12–14
03

Law Applied

The appellant relied on Regulation 4.3 of the Arunachal Pradesh State Electricity Regulatory Commission (Multi-Year Tariff) Regulations, 2018, contending that the Commission’s prudence check should not consist of mechanically selecting the lowest among contract rates, rates in the PGCIL Detailed Project Report, and actual costs

Source reference: para. 11

The Tribunal did not interpret that regulation or apply any cited precedent; it ordered reconsideration in light of the issues raised and the Commission’s position before it

Source reference: paras. 12–14
04

Reasoning

The Tribunal recorded the appellant’s challenge to the Commission’s method of assessing civil-works costs and its consequential restriction of IDC, notwithstanding that time overruns had been condoned

Source reference: paras. 10–11

It did not decide whether the Commission’s methodology or approved amounts were legally or factually correct.

Source reference: no citation

Instead, given the Commission’s counsel’s statement supporting remand and the corresponding prayer in its written submissions, the Tribunal considered fresh consideration by the Commission appropriate

Source reference: paras. 12–13
05

Holding

The Tribunal set aside the Commission’s order only to the extent challenged in the appeal and remanded the matter for fresh consideration of the issues raised, after giving the parties a reasonable opportunity of hearing

It directed the Commission to endeavour to complete the exercise within three months and allowed the appeal to that limited extent; pending interlocutory applications, if any, were disposed of

Source reference: paras. 14–15
06

Acts & Sections Cited

1 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.

Electricity Act, 20031

APTEL

Original Court PDF

M/s Devi Energies Pvt. Ltd.vsArunachal Pradesh State Electricity Regulatory Commission

APTEL · October 06, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment