CAT - ['Delhi']Social Security and PensionsEmployment and Labour Law

Tribunal Orders Interest on Retired Principal's MACP Arrears Paid Over 10 Years Late, Rejecting Funds Plea

RAJENDRA SINGHv.MUNICIPAL CORPORATION OF DELHI

Tribunal Orders Interest on Retired Principal's MACP Arrears Paid Over 10 Years Late, Rejecting Funds Plea. RAJENDRA SINGH vs MUNICIPAL CORPORATION OF DELHI. CAT - ['Delhi']. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the applicant is entitled to interest on the delayed payment of MACP-III arrears, notwithstanding the respondents' objection on limitation and delay.

The court held

The applicant is entitled to interest on the delayed payment of MACP arrears, in view of the ruling in Rajbir Singh.

It also directed

The respondents are directed to pay interest on the delayed MACP arrears from the date they became due until actual payment, at the rates applicable to GPF deposits, within two months of receipt of a certified copy of the order. The applicant's prayer for 24% interest was not granted.

The O.A. was disposed of accordingly, with no order as to costs.

01Facts

The applicant retired as Principal of a Delhi Nagar Nigam school in 2013 and was allotted PPO No. 18040.

¶ 2

MACP-III arrears of ₹91,289 were sanctioned on 20.08.2014, and further arrears of ₹54,180 for July 2013 to September 2014 were sanctioned on 30.04.2015.

¶ 2

Despite repeated applications to Respondent No. 2, the arrears remained unpaid. The applicant served a legal notice dated 11.11.2024.

¶ 2

The O.A. was filed on 25.02.2025 under Section 19 of the Administrative Tribunals Act, 1985.

¶ 1, 3

The applicant sought payment of the arrears with 24% interest, production of records, and costs.

¶ 1

The limited grievance pressed was interest on the delayed payment of MACP arrears.

¶ 2

The respondents contended that the O.A. was barred by limitation under Section 21 of the Act, given a delay of roughly 10 to 12 years, and that no condonation application had been filed.

¶ 3

The respondents had paid the due amounts on 05.10.2026 and 14.05.2026, after a delay of more than 10 years.

¶ 5

02Issues

i.1. Whether the applicant is entitled to interest on the delayed payment of MACP-III arrears, notwithstanding the respondents' objection on limitation and delay.

¶ 3, 5, 8

ii.2. Whether financial constraints of the respondent-employer can justify the inordinate delay in discharging sanctioned retiral/MACP dues.

¶ 5, 6

03Law Applied

The MACP scheme provides for interest on delayed payment of MACP-III arrears; the order does not quote the specific clause.

¶ 6

Financial constraints cannot justify delaying employees' due payments, as laid down in S.K. Dua v. State of Haryana & Anr., 2008 AIR SCW 689.

¶ 5

Rajbir Singh v. Municipal Corporation of Delhi & Ors., O.A. No. 2821/2023 (dated 30.10.2025) sets out the law on interest for delayed payment of retiral dues; the order is under challenge before the Delhi High Court but no stay is operating.

¶ 7

Section 21 of the Administrative Tribunals Act, 1985 and Supreme Court authority on limitation and stale claims were relied on by the respondents in objecting to the O.A.

¶ 3

Provisions in the judgment · 2 · Linked ones open on LawLens

Administrative Tribunals Act, 1985 Section 19Section 21

04Reasoning

The Tribunal held that the respondents, as a model employer, had delayed payment of arrears due in 2014-15 and 2015-16 for want of funds, and relying on S.K. Dua, rejected paucity of funds as a justification.

¶ 5

The substantial payments were made only in 2026, more than ten years after the arrears accrued, and no explanation beyond financial constraint was found. The Tribunal observed that the MACP scheme provides for interest on delayed MACP-III arrears.

¶ 6

The respondents' limitation objection was not separately adjudicated; the Tribunal stated that the delay could not be reconciled with the findings on limitation.

¶ 6

Since the applicant's limited prayer was for interest, the Tribunal applied Rajbir Singh to award interest on the delayed payment. The order does not expressly decide whether the O.A. is time-barred under Section 21 or whether condonation was required.

¶ 7–8

05Holding

The applicant is entitled to interest on the delayed payment of MACP arrears, in view of the ruling in Rajbir Singh.

¶ 8

The respondents are directed to pay interest on the delayed MACP arrears from the date they became due until actual payment, at the rates applicable to GPF deposits, within two months of receipt of a certified copy of the order. The applicant's prayer for 24% interest was not granted.

¶ 9

The O.A. was disposed of accordingly, with no order as to costs.

¶ 10
CAT - ['Delhi']

Original Court PDF

RAJENDRA SINGHvsMUNICIPAL CORPORATION OF DELHI

CAT - ['Delhi'] · October 28, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment