Delhi High CourtBanking and Finance LawArbitration and Mediation

Unconditional Bank Guarantees Cannot Be Enjoined Absent Proven Egregious Fraud or Irretrievable Injustice

M/S Vishal Infrastructure Ltd. And M/S Ojsc Euro - Asian Construction Corporation Evrascon (Jv)v.Chief Engineer (Const)-I, North Western Railway, Jaipur & Ors.

Unconditional Bank Guarantees Cannot Be Enjoined Absent Proven Egregious Fraud or Irretrievable Injustice. M/S Vishal Infrastructure Ltd. And M/S Ojsc Euro - Asian Construction Corporation Evrascon (Jv) vs Chief Engineer (Const)-I, North Western Railway, Jaipur & Ors.. Delhi High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the Petitioner made out a case of "egregious fraud" or "irretrievable injustice" sufficient to restrain the invocation of unconditional Bank Guarantees

The court held

The Court answered the issues in the negative, holding that there were no grounds to grant an injunction under Section 9 of the Arbitration Act

It also directed

The Petition was dismissed, and the Respondent was permitted to proceed with the invocation of the Bank Guarantees. The Court clarified that the Petitioner remains at liberty to seek damages through the contractually stipulated arbitration and DAB process

01Facts

The Petitioner was awarded a contract for the upgradation of Jodhpur Railway Station on 29.09.2022

p. 2

Following an "appointed date" of 29.07.2023, the Respondent issued a notice of intent to terminate on 13.05.2026, alleging delays and inadequate resource deployment

p. 3

While a previous court order in OMP (I) COMM. 220/2026 restrained the imposition of liquidated damages pending a Dispute Adjudication Board (DAB) decision, the Respondent subsequently issued a formal Termination Notice on 29.05.2026

pp. 4-5

The Petitioner approached the High Court seeking an interim injunction under Section 9 of the Arbitration and Conciliation Act to restrain the Respondent from encashing four Bank Guarantees totaling approximately INR 17.23 Crores

pp. 1-2, 5

02Issues

i.1. Whether the Petitioner made out a case of "egregious fraud" or "irretrievable injustice" sufficient to restrain the invocation of unconditional Bank Guarantees

p. 13 / para. 11

ii.2. Whether the Bank Guarantees were invoked by an officer below the mandated rank of Chief Engineer, thereby vitiating the invocation

p. 14 / para. 12

03Law Applied

Section 9 of the Arbitration and Conciliation Act, 1996

p. 1

Settled principles from U.P. State Sugar Corpn. v. Sumac International Ltd. and Himadri Chemicals Industries Ltd. v. Coal Tar Refining Co., which establish that an unconditional bank guarantee is an independent contract.

p. 7, 10

Injunctions against invocation are only permissible in two strictly defined exceptions: (i) fraud of an egregious nature that vitiates the entire underlying transaction, and (ii) where encashment would result in irretrievable harm or injustice of an exceptional nature

pp. 8-12

The beneficiary is the sole judge of the breach, and disputes regarding the underlying contract are not grounds for an injunction

pp. 7-8

Provisions in the judgment · 1 · Linked ones open on LawLens

Arbitration and Conciliation Act, 1996 Section 9

04Reasoning

The Court observed that the Bank Guarantees in question were unconditional, irrevocable, and payable on first demand without demur

pp. 6-7

Applying the Himadri Chemicals test, the Court found the Petitioner failed to demonstrate any "egregious fraud" or "irretrievable injustice"

p. 13 / para. 11

While the Petitioner argued the invocation was procedurally flawed because it was initiated by an Assistant Financial Adviser instead of a Chief Engineer (citing Hindustan Construction Co. Ltd. v. State of Bihar), the Court perused the Respondent's internal documents and concluded that the invocation was, in fact, performed by an officer of the rank of Chief Engineer

pp. 14 / para. 12-13

The Court further noted that even if the termination was disputed, the proper remedy was to claim damages during arbitration rather than seeking to stay the bank guarantees

pp. 13-14

05Holding

The Court answered the issues in the negative, holding that there were no grounds to grant an injunction under Section 9 of the Arbitration Act

p. 15 / para. 15

The Petition was dismissed, and the Respondent was permitted to proceed with the invocation of the Bank Guarantees. The Court clarified that the Petitioner remains at liberty to seek damages through the contractually stipulated arbitration and DAB process

pp. 13-14
Delhi High Court

Original Court PDF

M/S Vishal Infrastructure Ltd. And M/S Ojsc Euro - Asian Construction Corporation Evrascon (Jv)vsChief Engineer (Const)-I, North Western Railway, Jaipur & Ors.

Delhi High Court · July 16, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment