Facts
The Petitioner was awarded a contract for the upgradation of Jodhpur Railway Station on 29.09.2022
Source reference: p. 2Following an "appointed date" of 29.07.2023, the Respondent issued a notice of intent to terminate on 13.05.2026, alleging delays and inadequate resource deployment
Source reference: p. 3While a previous court order in OMP (I) COMM. 220/2026 restrained the imposition of liquidated damages pending a Dispute Adjudication Board (DAB) decision, the Respondent subsequently issued a formal Termination Notice on 29.05.2026
Source reference: p. 4-5The Petitioner approached the High Court seeking an interim injunction under Section 9 of the Arbitration and Conciliation Act to restrain the Respondent from encashing four Bank Guarantees totaling approximately INR 17.23 Crores
Source reference: p. 1-2, 5Issues
1. Whether the Petitioner made out a case of "egregious fraud" or "irretrievable injustice" sufficient to restrain the invocation of unconditional Bank Guarantees
Source reference: p. 13 / para. 112. Whether the Bank Guarantees were invoked by an officer below the mandated rank of Chief Engineer, thereby vitiating the invocation
Source reference: p. 14 / para. 12Law Applied
Section 9 of the Arbitration and Conciliation Act, 1996
Source reference: p. 1Settled principles from U.P. State Sugar Corpn. v. Sumac International Ltd. and Himadri Chemicals Industries Ltd. v. Coal Tar Refining Co., which establish that an unconditional bank guarantee is an independent contract.
Source reference: p. 7, 10Injunctions against invocation are only permissible in two strictly defined exceptions: (i) fraud of an egregious nature that vitiates the entire underlying transaction, and (ii) where encashment would result in irretrievable harm or injustice of an exceptional nature
Source reference: p. 8-12The beneficiary is the sole judge of the breach, and disputes regarding the underlying contract are not grounds for an injunction
Source reference: p. 7-8Reasoning
The Court observed that the Bank Guarantees in question were unconditional, irrevocable, and payable on first demand without demur
Source reference: p. 6-7Applying the Himadri Chemicals test, the Court found the Petitioner failed to demonstrate any "egregious fraud" or "irretrievable injustice"
Source reference: p. 13 / para. 11While the Petitioner argued the invocation was procedurally flawed because it was initiated by an Assistant Financial Adviser instead of a Chief Engineer (citing Hindustan Construction Co. Ltd. v. State of Bihar), the Court perused the Respondent's internal documents and concluded that the invocation was, in fact, performed by an officer of the rank of Chief Engineer
Source reference: p. 14 / para. 12-13The Court further noted that even if the termination was disputed, the proper remedy was to claim damages during arbitration rather than seeking to stay the bank guarantees
Source reference: p. 13-14Holding
The Court answered the issues in the negative, holding that there were no grounds to grant an injunction under Section 9 of the Arbitration Act
The Petition was dismissed, and the Respondent was permitted to proceed with the invocation of the Bank Guarantees. The Court clarified that the Petitioner remains at liberty to seek damages through the contractually stipulated arbitration and DAB process
Source reference: p. 13-14Original Court PDF
M/S Vishal Infrastructure Ltd. And M/S Ojsc Euro - Asian Construction Corporation Evrascon (Jv)vsChief Engineer (Const)-I, North Western Railway, Jaipur & Ors.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in