01Facts
The Delhi Urban Shelter Improvement Board (“appellant”) filed a statutory commercial appeal under Section 13 of the Commercial Courts Act, 2015 read with Order XLI CPC against the impugned decree, with a delay of 439 days, seeking condonation under Section 5 of the Limitation Act, 1963.
¶ 1The appellant sought exclusion of time spent pursuing a review petition, obtaining certified copies, prosecuting an earlier appeal, and pursuing an application under Order IX Rule 13 CPC.
¶ 4–5For the remaining delay, the appellant attributed the delay to departmental approval and codal formalities, including the suspension of an official and the resultant vacancy of the concerned post.
¶ 4The Court held that, even after excluding the periods claimed by the appellant, a delay of 258 days remained unexplained.
¶ 602Issues
i.Whether the appellant had shown sufficient cause under Section 5 of the Limitation Act, 1963 for condonation of the 439-day delay in filing the commercial appeal.
¶ 1, 4–10ii.Whether the periods spent in review proceedings, obtaining certified copies, prosecuting the earlier appeal, and pursuing the Order IX Rule 13 application could be excluded for computing limitation.
¶ 4–6iii.Whether the unexplained administrative delay attributed to “approval and codal formalities” justified condonation in a commercial appeal.
¶ 7–1003Law Applied
The Court applied Section 13 of the Commercial Courts Act, 2015, read with Order XLI CPC, governing the statutory appeal, and Section 5 of the Limitation Act, 1963, under which delay may be condoned only upon sufficient cause.
¶ 1It considered the limitation framework under Section 13(1-A) of the Commercial Courts Act and the principles in Government of Maharashtra v. Borse Brothers Engineers & Contractors Pvt. Ltd., (2021) 6 SCC 460, that delay beyond the prescribed period in commercial appeals is to be condoned by way of exception and not as a rule, particularly where the party has acted negligently or without bona fides.
¶ 9The Court also relied on Jharkhand Urja Utpadan Nigam Ltd. v. Bharat Heavy Electricals Ltd., 2025 SCC OnLine SC 910, reiterating that the expression “sufficient cause” is not an elastic panacea for negligent or stale claims, that the object of the Commercial Courts Act is speedy resolution, and that Government entities are not entitled to a more lenient standard for condonation.
¶ 9The appellant’s reliance on exclusion of time under Section 14 of the Limitation Act was considered, but even the claimed exclusions did not eliminate the substantial remaining delay.
¶ 5–6Provisions in the judgment · 6 · Linked ones open on LawLens
Commercial Courts Act, 2015 Section 13
Limitation Act, 1963 Section 14Section 5Section 116Section 117
Arbitration and Conciliation Act, 1996 Section 37
04Reasoning
The Court accepted, for purposes of consideration, the periods claimed by the appellant for review proceedings, certified-copy procurement, the earlier appeal, and the Order IX Rule 13 proceedings; nevertheless, a delay of 258 days remained.
¶ 5–6The explanation that the file was pending for “approval and codal formalities” did not identify the period of movement between offices, the duration for which the file was retained, the identity or period of absence of the suspended official, or why processing could not continue during the vacancy.
¶ 7The Court therefore found the explanation vague and insufficient, reflecting negligence rather than bona fide diligence.
¶ 8, 10Applying the stricter approach mandated for commercial appeals under Borse Brothers and Jharkhand Urja, the Court concluded that the substantial unexplained delay could not be condoned merely because the appellant was a government instrumentality.
¶ 905Holding
The Court dismissed the application for condonation of delay, holding that no sufficient cause had been shown for the 439-day delay, including the remaining unexplained delay of 258 days.
¶ 10–11Consequently, RFA(COMM) 573/2026 was dismissed on the ground of limitation without examination of the merits.
¶ 11The legal question raised in the appeal was expressly left open.
¶ 12Original Court PDF
Delhi Urban Shelter Improvement BoardvsNageshwar Sharma Sole Prop. Of M/S Sarthak Construction Co.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
